E 38/3958 is a pending exploration licence in the Shire of Laverton, Western Australia, applied for by Duketon Gold Project Pty Ltd (part of Great Southern Mining Limited). The application was received on 17 May 2024 and is awaiting a decision. The ground is covered by 54 historical WAMEX reports.
Register summary
- Holder
- Duketon Gold Project Pty Ltd
- Part of
- Great Southern Mining Limited (ASX:GSN) as at 2025-06-30
- Local government
- Shire of Laverton
- Application received
- 17 May 2024
The full record on E 38/3958
The register summary says who has applied for it. The rest of the record says what is attached to the application and how it is progressing.
- Current holders and their shares (no change of holder on record)
- Expenditure history, conditions and endorsements
- Native title context, combined reporting and rent status
- Expenditure compliance, expiry and ownership signals, once the application is granted
- Every register dealing (2 on record), with mortgages, caveats and transfers flagged
Exploration history on this ground
| Report | Year | Operator | Project | On this ground | Title |
|---|---|---|---|---|---|
| A143576 | 2024 | Golden State Mining Limited | Four Mile Well | 100% | Four Mile Well E38/3632 Final Surrender Report for the period ending 16/5/2024 |
| A139399 | 2024 | Golden State Mining | Four Mile Well | 100% | Four Mile Well E38/3632 Exploration Activity Report for the period ending 31/12/2023 |
| A137294 | 2023 | Formidable Resources Pty Ltd | West Windarra | <1% | West Windarra Annual Report E39/2279 for the period ending 08/10/2023. |
| A137806 | 2023 | Golden State Mining Pty Ltd | E38/3633 | <1% | E38/3633 Final Surrender Report for the period ending 8/11/2023 |
| A134572 | 2023 | Golden State Mining Limited | Four Mile Well | 28% | Four Mile Well Project C61/2022 for the period ending 31/12/2022. E 38/3282,E 38/3632,E 38/3633 |
49 more reports
| A123165 | 2020 | Murrin Murrin Operations Pty Ltd | Mount Zephyr | <1% | Annual Report Mount Zephyr Calcrete Project - C17/2000 - 1 January 2019 to 31 December 2019 |
| A124517 | 2020 | Regis Resources Limited | Camel Hump | <1% | Combined Surrender report for the Camel Hump group tenements for the period 3 July 2008 to 16 June 2020. E 38/ |
| A119546 | 2019 | Murrin Murrin Operations Pty Ltd | Mount Zephyr | <1% | Combined Annual Report Mount Zephyr Calcrete Project C17/2000 for the period 1 January 2018 to 31 December 20 |
| A121211 | 2019 | Regis Resources Limited | Duketon Central | <1% | Annual Report C95/2016 Duketon Central Project for the period 1 July 2018 to 30 June 2019 |
| A117884 | 2018 | Regis Resources Limited | Duketon Central | <1% | Duketon Central C95/2016 Annual Report for the period 1 July 2017 to 30 June 2018 |
| A116258 | 2018 | Murrin Murrin Operations Pty Ltd | Mount Zephyr | <1% | Combined Annual Report for the Mount Zephyr Project - C17/2000 For the Period 1 January 2017 to 31 December 20 |
| A112421 | 2017 | Murrin Murrin Operations Pty Ltd | Mount Zephyr | <1% | Combined Annual Report for the Mount Zephyr Calcrete Project - C17/2000 For the Period 1 January 2016 to 31 De |
| A108254 | 2016 | Murrin Murrin Operations Pty Ltd | Mount Zephyr | <1% | Combined Annual Report for the Mount Zephyr Calcrete Project 1 January 2015 to 31 December 2015, M 39/00446, M |
| A105111 | 2015 | Murrin Murrin Operations Pty Ltd | Mount Zephyr | <1% | Combined Annual Report, Mount Zephyr Project, C17/2000 for the period 1 January 2014 to 31 December 2014 |
| A101239 | 2014 | Ausrich Resources Pty Ltd | Laverton | 5.6% | E38/2466 Laverton Project Final Surrender Report for the period 18/08/ 2011 to 17/08/2013 |
| A101282 | 2014 | Ishine International Resources Ltd | Laverton | <1% | E38/2635, E38/2435 and E38/2601 Laverton Project Final Surrender Report for the period: 01/03/2013 to 10/03/20 |
| A101678 | 2014 | Murrin Murrin Operations Pty Ltd | Mount Zephyr | <1% | Combined Annual Report For The Period: 1 January 2013 to 31 December 2013 Mount Zephyr Calcrete Project C17/20 |
| A97315 | 2013 | Murrin Murrin Operations Pty Ltd | Mount Zephyr | <1% | Combined Annual Report, Mount Zephyr Project, C17/2000 for the period 1 January 2012 to 31 December 2012, E39/ |
| A93176 | 2012 | Ishine International Resources Ltd | Laverton Downs | <1% | E38/2435 Laverton Downs Project Annual Report for the period: 21st January 2011 to 20th January 2012 |
| A94667 | 2012 | Poseidon Nickel Ltd | Windarra | 1.9% | Windarra Nickel Project Final Surrender Report E38/1450 for the period 22nd April 2004 to 29th May 2012 |
| A95797 | 2012 | Ausrich Resources Pty Ltd | Laverton | 5.6% | E38/2466 Laverton Project Annual Report for the period: 18th August 2011 to 17th August 2012 |
| A96804 | 2012 | Ishine International Resources Ltd | Laverton Downs | <1% | E38/2435 Laverton Downs Project, Annual Report for the period: 21st Jan 2012 to 20th Jan 2013 |
| A93512 | 2012 | Murrin Murrin Operations Pty Ltd | Mount Zephyr | <1% | Combined Annual Report for the Period 1 January 2011 to 31 December 2011, Mt Zephyr Project, C17/2000, E 39/12 |
| A94461 | 2012 | Poseidon Nickel Limited | Windarra | <1% | Windarra Nickel Project - Combined Annual Report for the Period 22 April 2011 to 21 April 2012, C79/2006, E38/ |
| A89851 | 2011 | Murrin Murrin Operations Pty Ltd | Mount Zephyr | <1% | Combined Annual Technical Report for C17/2000, 1 January 2010 to 31 December 2010 |
| A91181 | 2011 | Poseidon Nickel Limited | Windarra | <1% | Windarra Nickel Project - Combined Annual Report for the Period 22 April 2010 to 21 April 2011, C79/2006, E38/ |
| A87137 | 2010 | Poseidon Nickel Limited | Windarra | <1% | Windarra Nickel Project - Combined Annual Report for the Period 22 April 2009 to 21 April 2010, CR# C79/2006, |
| A86678 | 2010 | Minara Resources Ltd | Mount Zephyr | <1% | Mt Zephyr Project Eleventh Combined Annual Technical Report C17/2000, 1st January 2009 to 31st December 2009, |
| A82530 | 2009 | Poseidon Nickel Ltd | Windarra | <1% | Windarra Project - Combined Annual Report for the Period 22 April 2008 to 21 April 2009, C79/2006 |
| A84627 | 2009 | Gryphon Minerals Ltd | Mt Windarra | 26% | Mt Windarra E38/2098 Final Surrender Report E38/2098, 30 December 2008 to 21 September 2009 |
| A84628 | 2009 | Gryphon Minerals Ltd | Mt Windarra | 4.9% | Final Surrender Report E38/2095, 17 July 2008 to 24 August 2009 |
| A78633 | 2008 | Poseidon Nickel Ltd | Windarra | <1% | Windarra Nickel Project - Combined Annual Report for the period 22 April 2007 to 21 April 2008, CR79/2006 |
| A75758 | 2007 | Dynasty Metals Australia Ltd | Laverton | 1.9% | Laverton Project, EL38/1450 Partial Surrender Report for the Period Ended 21/06/2007 (E381450_200706_00_prr) |
| A75957 | 2007 | Dynasty Metals Australia Ltd | Laverton | <1% | LAVERTON PROJECT COMBINED REPORT E38/1450/1586/1587/1622/ 1752, E39/929/930/1325/1326/3272-3274 Annual Technic |
| A72558 | 2006 | Dynasty Metals Australia Ltd | Laverton | 1.9% | Laverton Project E38/1450, Annual Technical Report Period Ending 21 April 2006. |
| A70791 | 2005 | Target Minerals Australia Pty Ltd | Laverton | 1.9% | Laverton (Four Mile Well) Project E38/1450, Annual technical report for the period ending 21st April 2005. |
| A71073 | 2005 | Western Areas Nl | Windarra | 26% | 2005 Annual report for the Windarra JV Project, E39/1058 (For the period 12/07/04 - 11/07/05, Laverton). |
| A68340 | 2004 | Minara Resources Ltd | Mt Zephyr | 3.9% | Combined Annual Report for the period 01/01/2003-31/12/2003 Mount Zephyr (C17/2000), E39/541, E39/482, M39/446 |
| A66299 | 2003 | Anaconda Operations Pty Ltd | Mt Zephyr | 3.9% | Fourth Combined Annual Technical Report for the period 1st January 2002 to 31st December 2002 Mt Zephyr Projec |
| A66763 | 2003 | Anaconda Operations Pty Ltd | Mount Zephyr (MurrinMurrin) | 7.8% | Mt Zephyr Project, Surrender Report, , E39/541,for the period 7 February 1997 to 12 May 2003, Report Number T |
| A64553 | 2002 | Anaconda Operations Pty Ltd | Mount Zephyr | 7.8% | Mt Zephyr Project, Partial Surrender Report, April 2002, E39/541. |
| A65047 | 2002 | Anaconda Operations Pty Ltd | Mt Zephyr | 3.9% | Mt Zephyr Project Combined Reporting Number C17/2000 Third Annual Technical Report For The Period 1 January 20 |
| A62098 | 2001 | Anaconda Operations Pty Ltd | Mount Zephyr | 3.9% | Mt Zephyr Project Second Combined Annual Technical Report number C17/2000 for the period 1st January 2000 to 3 |
| A60027 | 2000 | Anaconda Nickel Ltd | Mount Zephyr | 3.9% | Mt Zephyr Project M39/446,E39/482,E39/541 Combined Reporting Number C17/2000 First Annual Technical Report for |
| A57879 | 1999 | Anaconda Nickel Ltd | Windarra | 7.8% | Windarra Calcrete Project - E39/541 07/02/98 - 06/02/99 |
| A53919 | 1998 | Voyager Gold Nl | Laverton Downs | <1% | Annual Report E38/882 Laverton Downs Project for the year ending 27/11/1997. |
| A54427 | 1998 | Anaconda Nickel Ltd | Windarra | 7.8% | Windarra Calcrete Prospect, E39/541 Mt Margaret Mineral Field, First annual technical report, 7 February 1997 |
| A6945 | 1973 | Kennecott Exp Aust Pty Ltd | Erlistoun | <1% | Aeromag- Raw Data |
| A2765 | 1972 | Conwest Australia Nl | Windarra North | 53% | Windarra North Project, Non-statutory Report: Brief Exploration Report, July 1972, MC39/1138-1142 & 5313. |
| A9159 | 1972 | Cominco Exploration Pty Ltd | Erlistoun- Baneygo | <1% | Erlistoun-Baneygo Project, Non-statutory Report:Exploration Report for the period 01/01/1971 to 31/12/1971, TR |
| A9156 | 1971 | Cominco Exploration Pty Ltd | Erlistoun - Baneygo | <1% | Erlistoun - Baneygo (JV) Project, Non-statutory Report:Progress Report for the period 31st May 1970 to 1st Ja |
| A9157 | 1971 | Cominco Exploration Pty Ltd | Erlistoun - Baneygo | <1% | Erlistoun - Baneygo Project, Annual Report for the period 01/01/1970 to 31/12/1970, TR70/3813; MC38/3917...... |
| A9158 | 1971 | Cominco Exploration Pty Ltd | Erlistoun - Baneygo | <1% | Erlistoun-Baneygo (JV) Project, Non-statutory Report, Progress Report for the period 01/01/1971 to 30/06/1971, |
| A38751 | 1753 | Inco Australia Ltd | Eastern Goldfields regional mapping | <1% | Eastern Goldfields regional mapping |
What does the exploration record say about this ground?
NextMaps reads the WAMEX reports over E 38/3958 into a referenced prospectivity assessment: the geology, the historical programs, the drill intercepts and geochemistry, and the untested gaps, with every claim cited back to its source report. New accounts include a free report (how the reports work). Prefer the raw due diligence? A Tenure Pack bundles the full register record, tenure history and spatial datasets for this ground.
Get the free report Full register record on the mapDo you hold E 38/3958? Listing is free. A facilitation fee applies only if the ground ends up with a buyer we introduce.
List this tenementTenure data sourced from the DMPE public registers and SLIP WA (© Government of Western Australia, CC BY 4.0), as at 2026-10-08. Compiled by NextMaps. Verify against primary sources before reliance.