E 47/4596
Register summary
- Holders
- Mitsui Iron Ore Development Pty Ltd, North Mining Limited, Robe River Mining Co. Pty. Ltd., Cape Lambert Iron Associates, Pannawonica Iron Associates
- Local government
- Shire of East Pilbara
- Application received
- 17 Sept 2021
- Commenced
- 15 Dec 2021
- Expiry
- 14 Dec 2026
- Term
- 5 Years
Exploration history on this ground
| Report | Year | Operator | Project | On this ground | Title |
|---|---|---|---|---|---|
| A127661 | 2021 | Fortescue Metals Group Ltd | Central Wonmunna | 20% | Central Wonmunna E47/3444 Final Surrender Report for the period 25 May 2017 to 27 May 2021 |
| A124767 | 2020 | Australian Aboriginal Mining Corporation Limited | First | 1.4% | First Iron Annual Technical Report E 47/1137 for the period ending 28 August 2020 |
| A125387 | 2020 | Wonmunna Iron Ore Pty Ltd | Wonmunna | 1.4% | C24/2015 Wonmunna Annual Report for the period 29/8/2019 to 28/8/2020 |
| A121894 | 2019 | Australian Aboriginal Mining Corporation Pty Ltd | First Iron | 1.4% | First Iron Project C24/2015 Activity Report for the period 29 August 2018 to 28 August 2019 |
| A118301 | 2018 | Ascot Resources Limited | Wonmunna | 1.4% | Combined Annual Technical Report C24/2015 Wonmunna Project for the period 29/08/2017 - 28/08/2018, E47/01137, |
27 more reports
| A115274 | 2017 | Ascot Resources Limited | Wonmunna | 1.4% | Wonmunna Project C24/2015 Combined Annual Technical Report for the period 29/08/2016 - 28/08/2017, E47/01137, |
| A110378 | 2016 | Ascot Resources Limited | Wonmunna | 1.4% | Wonmunna Project C24/2015 Combined Annual Technical Report for the period 29 August 2015 to 28 August 2016, E4 |
| A108248 | 2016 | Ascot Resources Ltd | Wonmunna | 1.4% | Wonmunna E47/1137-I Partial Surrender Report for the period 29/08/2002 to 20/11/2015 |
| A107367 | 2015 | Ascot Resources Ltd | Wonmunna | 1.4% | WONMUNNA PROJECT COMBINED MINERAL EXPLORATION REPORT 2015 C24/2015 Annual Technical Reports for Year ending 28 |
| A107245 | 2015 | Bhp Billiton Iron Ore Pty Ltd | Mudlark Well | <1% | ANNUAL REPORT COMBINED REPORTING C417/1995 Mudlark Well E47/13 E47/14 E47/15 E47/17 E47/1540 E47/1431 E47/1871 |
| A104081 | 2014 | Bhp Billiton Iron Ore Pty Ltd | Mudlark Well | <1% | Combined Annual Report Mudlark Well: E47/13, E47/14, E47/15, E47/17, E47/1540, E47/1431, E47/1871, E47/1875, P |
| A104312 | 2014 | Ochre Group Holdings | Wonmunna | 1.4% | Wonmunna Project, Annual Report for the period 29/08/2013 to 28/08/2014, E47/1137. |
| A100199 | 2013 | Bhp Billiton Iron Ore Pty Ltd | Mudlark Well | <1% | Annual Report C417/1995 Mudlark Well E47/13, E47/14, E47/15, E47/17, E47/1540, E47/1431, E47/1871, E47/1875, E |
| A99438 | 2013 | Rico Resources Ltd | Wonmunna | 1.4% | Wonmunna Project, Annual Report for the period 29/08/2012 to 28/08/2013, e47/1137. |
| A95789 | 2012 | Bhp Billiton Iron Ore Pty Ltd | Mudlark Well | <1% | Annual Report – Mudlark Well Combined Reporting Group E47/13, E47/14, E47/15, E47/17, E47/1540, E47/1431, E47/ |
| A95898 | 2012 | Rico Resources Ltd | Wonmunna | 1.4% | Wonmunna Project, Annual Report for the period 29/08/2011 to 28/08/2012, E47/1137. |
| A91731 | 2011 | Bhp Billiton Iron Ore Pty Ltd | Mudlark Well | <1% | Annual Report – Mudlark Well Combined Reporting Group E47/13, E47/14, E47/15, E47/17, E47/1540, E47/1431 and E |
| A91513 | 2011 | Rico Resources Ltd | Wonmunna | 1.4% | Annual Technical Report on E47/1137, Wonmunna, located in the Central Pilbara Region of Western Australia, for |
| A88479 | 2010 | Bhp Billiton Iron Ore Pty Ltd | Mudlark Well | <1% | Annual Report - Mudlark Well Combined Reporting Group C417/1995, Reporting period October 2009 to October 2010 |
| A88175 | 2010 | Talisman Mining Ltd | Wonmunna | 1.4% | Annual Exploration Report for the period 29 August 2009 to 28 August 2010 |
| A84613 | 2009 | Talisman Mining Ltd | Wonmunna | 1.4% | Wonmunna Project E47/1137, Annual Exploration Report for the period 29 August 2008 to 28 August 2009 |
| A84971 | 2009 | Bhp Billiton Iron Ore Pty Ltd | Mudlark Well | <1% | Annual Report – Mudlark Well Project Area E47/13, E47/14, E47/15, E47/17 and E47/1540 Reporting Period 4th Oct |
| A79952 | 2008 | Talisman Mining Ltd | Wonmunna | 1.4% | Annual Exploration Report for the period 29 August 2007 to 28 August 2008 |
| A80213 | 2008 | Bhp Billiton Iron Ore Pty Ltd | Mudlark Well | <1% | Annual Report - Mudlark Well Project E47/13, 14, 15, 17, and E47/1540, Reporting Period 4/10/2008 to 03/10/200 |
| A75573 | 2007 | Talisman Mining Ltd | Wonmunna | 1.4% | Wonmunna Project 'Tavros' Resource Estimate 2007 Report No R2014-PWMN850 |
| A76365 | 2007 | Talisman Mining Ltd | Wonmunna | 1.4% | Wonmunna Project E47/1137 Annual Exploration Report for the period 29 August 2006 to 28 August 2007; Report N |
| A72961 | 2006 | Talisman Mining Ltd | Wonmunna | 1.4% | Wonmunna Project E47/1137, Third Annual Report for the Period Ended 28 August 2005, (Talisman Mining Report No |
| A73805 | 2006 | Talisman Mining Ltd | Wonmunna | 1.4% | Wonmunna Project E47/1137 Fourth Annual Report for the Period Ended 28 August 2006 Report No.R2007-PWNM300 (Ne |
| A69290 | 2004 | Talisman Mining Ltd | Wonmunna | 1.4% | Technical report 1007 Wonmunna project (E47/1137), Second annual report (29/8/03 - 28/8/04) |
| A67407 | 2003 | Talisman Mining Ltd | Wonmunna | 1.4% | First Annual Report for the period August 2002 - August 2003 Wonmunna Project E47/1137 Technical Report 1006 |
| A50760 | 1997 | Hamersley Iron Pty Ltd | Padtherung Hill | 2.4% | Padtherung Hill Project, Surrender Report Exploration Licence E47/726, March 1997. |
| A781 | 1964 | Us Metals Refining Co | Wonmunna | <1% | Wonmunna Project, Annual Report for the period 01/02/1964 to 31/08/1964,(Field Report) TR70/2749H. |
Tenure detail Free account
- Current holders & shares
- Holder change history
- Expenditure history
- Conditions & endorsements
- Native title context
- Combined reporting
- Rent status
Tenement intelligence Premium
- Time to expiry
- 4 months · 14 Dec 2026
- At-risk & opportunity signals
- Expenditure compliance
- 5-year track record
- Spend trend & exploration intensity
- Expiry band
- Ownership age
- Dealings, mortgages & caveats
- Transfer history
What does the exploration record say about this ground?
NextMaps reads every WAMEX report over E 47/4596 into a referenced prospectivity assessment: the geology, the historical programs, the drill intercepts and geochemistry, and the untested gaps — every claim cited back to its source report. New accounts include a free prospectivity report. Prefer the raw due diligence? The Tenure Pack bundles the full register record, tenure history and spatial datasets for this ground.
Open on the map — full register record About AI reports About Tenure PacksDo you hold E 47/4596? Listing is free. A facilitation fee applies only if you sell to a buyer we introduce.
List this tenementTenure data sourced from the DMPE public registers and SLIP WA (© Government of Western Australia, CC BY 4.0), as at 2026-08-21. Compiled by NextMaps. Verify against primary sources before reliance.