E 52/4199
Register summary
- Holder
- Pingem Metals Pty Ltd
- Local government
- Shire of Meekatharra
- Application received
- 3 Nov 2022
- Commenced
- 17 July 2023
- Expiry
- 16 July 2028
- Term
- 5 Years
Exploration history on this ground
| Report | Year | Operator | Project | On this ground | Title |
|---|---|---|---|---|---|
| A149785 | 2025 | Aic Mines Limited | Thaddona Hill | <1% | Final Surrender Report forThaddona Hill Project E52/3317, E52/3318 and E52/3319 (C53/2017) for the period endi |
| A143960 | 2024 | Sandfire Resources Limited | Neds Creek | <1% | E52/3479 Ned’s Creek Surrender Report 3 July 2017 to 10 July 2024 |
| A138794 | 2024 | Sandfire Resources Limited | Ned’s Creek | <1% | E 52/1858, E 52/2356 and E 52/2405 ‘Ned’s Creek” Surrender Report for the period ending 16/01/2024 |
| A134287 | 2023 | Sandfire Resources Limited | East Plutonic | <1% | E52/3714 East Plutonic Surrender Report for the period ending 15/12/2022. (C83/2014) |
| A132572 | 2022 | Aic Mines Limited | Thaddona Hill | 15% | Annual Technical Report C53/2017 Thaddona Hill Project for the period ending 25/07/2022 |
124 more reports
| A129945 | 2022 | Sandfire Resources Limited | East Plutonic | 42% | P52/1457 to P52/1465 East Plutonic Surrender Report for the period 24/01/2014 to 20/01/2022 |
| A130908 | 2022 | Aic Mines Limited | Marymia | 27% | E52/3346 - Final Surrender Report Marymia project for the period ending 19/05/2022. |
| A131929 | 2022 | Sandfire Resources Limited | East Plutonic | 8.1% | C83/2014 East Plutonic Project Combined Annual Report 2022r the period ending 28/06/2022. |
| A132387 | 2022 | Sandfire Resources Ltd | Neds Creek | <1% | E52/3479 Neds Creek Project Partial Surrender Report 3 July 2017 to 5 August 2022 |
| A133103 | 2022 | Sandfire Resources Limited | Neds Creek | <1% | E52/3479 Neds Creek Project Partial Surrender Report for the period 3/7/2017 to 11/10/2022 |
| A127870 | 2021 | Sandfire Resources Limited | East Plutonic | 8.1% | C83/2014 East Plutonic Combined Annual Technical Report for the period 29 June 2020 to 28 June 2021 |
| A128652 | 2021 | Aic Mines Limited | Thaddona Hill | 15% | Thaddona Hill C53/2017 Annual Technical Report for the period ending 25/07/2021 |
| A123468 | 2020 | Billabong Gold Pty Ltd | Plutonic | <1% | Plutonic Project C94/1999 Annual Mineral Exploration Report for the period ending 31/12/2019 |
| A124404 | 2020 | Sandfire Resources Limited | Neds Creek | <1% | C144/2005 Ned’s Creek Project Combined Annual Technical Report for the period ending 11/05/2020 |
| A124628 | 2020 | Sandfire Resources Limited | East Plutonic | 42% | C83/2014 East Plutonic Project Combined Annual Technical Report for the period 29 June 2019 to 28 June 2020 |
| A125207 | 2020 | Aic Mines Limited | Thaddona Hill | 15% | Thaddona Hill C53/2017 Annual Report for the period ending 9 August 2020 |
| A123106 | 2020 | Vango Mining Limited | Marymia | 2.3% | Annual Report for the Marymia Gold Project C93/2018 for the period 1 January 2019 to 31 December 2019 |
| A119558 | 2019 | Vango Mining Limited | Marymia | 2.3% | Annual Report for the Marymia Gold Project C93/2018 for the period 1 January 2018 to 31 December 2018 |
| A119608 | 2019 | Sandfire Resources Nl | East Plutonic | <1% | East Plutonic E52/2927 Surrender Report for the period 11 February 2014 to 7 February 2019 |
| A119841 | 2019 | Billabong Gold Pty Ltd | Plutonic - Marymia | <1% | Plutonic / Marymia Annual Mineral Exploration Report For the Period 1 January 2018 to 31 December 2018 |
| A120927 | 2019 | Sandfire Resources Nl | East Plutonic | 42% | C83/2014 East Plutonic Project Combined Annual Technical Report for the period 29 June 2018 to 28 June 2019, P |
| A120649 | 2019 | Sandfire Resources Nl | Ned's Creek | <1% | C144/2005 Ned’s Creek Project Combined Annual Technical Report For the period 12 May 2018 to 11 May 2019 |
| A120703 | 2019 | Aic Resources Limited | Thadoona | 15% | Annual Report for C53/2017 Thadoona project for the period 27 July 2018 to 26 July 2019 |
| A121615 | 2019 | Vango Mining Limited | Ned's Creek | 7% | Ned's Creek C212/2010 Annual report for the period 12 September 2018 to 11 September 2019, E 52/02440, E 52/02 |
| A116353 | 2018 | Billabong Gold Pty Ltd | Plutonic - Marymia | <1% | Annual Mineral Exploration Report for the Plutonic/Marymia Group C94/1999 For the Period 1 January 2017 to 31 |
| A116602 | 2018 | Dampier (Plutonic) Pty Ltd | Plutonic Dome | 2.9% | Plutonic Dome Project - Combined Annual Report - C226/2011, 01 January 2017 to 31 December 2017 |
| A117323 | 2018 | Sandfire Resources Nl | Ned's Creek | <1% | C144/2005 Ned’s Creek Project Combined Annual Technical Report For the Period 12 May 2017 to 11 May 2018, E52/ |
| A117485 | 2018 | Aic Resources Limited | Thadoona | 15% | Annual Report on Explorations Activies for C53/2017, Thadoona, 27 July 2017 - 26 August 2018 |
| A117547 | 2018 | Sandfire Resources Nl | East Plutonic | 8.1% | C38/2014 East Plutonic Project Combined Annual Technical Report 2018, 29 June 2017 - 28 June 2018 |
| A118596 | 2018 | Lodestar Minerals Limited | Ned's Creek | 7% | Annual Report for the Ned's Creek Project, C212/2010, 12 September 2017 - 11 September 2018 |
| A112759 | 2017 | Dampier (Plutonic) Pty Ltd | Plutonic Dome | 2.8% | Combined Annual Report - C226/2011 Plutonic Dome Gold Project for the period 01/01/2016 to 31/12/2016 |
| A114356 | 2017 | Sandfire Resources Nl | Ned's Creek | <1% | C144/2005 Ned’s Creek Project Combined Annual Technical Report For the Period 12 May 2016 to 11 May 2017, E52/ |
| A115417 | 2017 | Lodestar Minerals Ltd | Neds Creek | 7.5% | Neds Creek C212/2010 Annual Report for the period 12 September 2016 to 11 September 2017, E52/02440, E52/02456 |
| A112361 | 2017 | Billabong Gold Pty Ltd | Plutonic | <1% | Annual Mineral Exploration Report for the Plutonic Group C94/1999 For the Period 1 January 2016 to 31 December |
| A114585 | 2017 | Sandfire Resources Nl | East Plutonic | 8.1% | C38/2014 East Plutonic Project Combined Annual Technical Report for the period 29 June 2016 to 28 June 2017, E |
| A115009 | 2017 | Aic Resources Limited | Marymia | 15% | Annual Report for Thadoona Group of Tenements C53/2017, E52/03317, E52/03318, E52/03319, E52/03346 for the per |
| A108310 | 2016 | Sandfire Resources Nl | Ned’s Creek | <1% | Ned’s Creek Project E52/2405 Partial Surrender Report 06/04/2010 to 11/02/2016 |
| A108562 | 2016 | Northern Star Resources Ltd | Plutonic | <1% | Annual Mineral Exploration Report for the Plutonic Group C94/1999 for the period 1 January 2015 to 31 December |
| A108642 | 2016 | Vango Mining Limited | Plutonic Dome | 2.5% | Annual Exploration Report for C226/2011, The Plutonic Dome Project from 01/01/2015 to 31/12/2015 |
| A109345 | 2016 | Sandfire Resources Nl | East Plutonic | 8.1% | C83/2014 East Plutonic Project Combined Annual Technical Report for the period 29/06/2015 to 28/06/2016, E52/0 |
| A110507 | 2016 | Lodestar Minerals Limited | Ned's Creek | 7.5% | Ned's Creek Project C212 Annual Report for the period 12 September 2015 to 11 September 2016, E52/02440, E52/0 |
| A109385 | 2016 | Sandfire Resources Nl | Ned's Creek | <1% | C144/2005 Ned’s Creek Project Combined Annual Technical Report for the period 12/05/2015 to 11/05/2016, E52/01 |
| A104392 | 2015 | Lodestar Minerals Ltd | Peak Hill - Doolgunna - Neds Creek | 4.1% | Peak Hill - Doolgunna - Neds Creek Project C212/2010 Annual Report for the period 12th September 2013 to 11th |
| A105239 | 2015 | Vango Mining Limited | Plutonic Dome | 1.6% | Annual Exploration Report for C226/2011, The Plutonic Dome Project from 01/01/2014 to 31/12/2014, E52/2071.... |
| A105369 | 2015 | Northern Star Resources Ltd | Plutonic | <1% | Plutonic Project C94/1999 Annual Report to the Department of Mines and Petroleum for the period 01/01/14 to 31 |
| A106213 | 2015 | Sandfire Resources Nl | Ned’s Creek | <1% | Ned’s Creek C144/2005, E52/1673, E52/1674. E52/1858, E52/2356, E52/2357, E52/2405 Combined Annual Report for t |
| A106521 | 2015 | Sandfire Resources Nl | East Plutonic | 8.1% | East Plutonic C83/2015 2015 Combined Mineral Exploration Annual Report for the period 29/06/2014 to 28/06/2015 |
| A107487 | 2015 | Lodestar Minerals Limited | Peak Hill - Doolgunna - Neds Creek | 4.9% | Peak Hill - Doolgunna - Neds Creek Project C212/2010 Annual Report for the period 12/09/2014 to 11/09/2015, E5 |
| A101168 | 2014 | Lodestar Minerals Ltd | Peak - Doolgunna - Marymia | 32% | Peak / Doolgunna / Marymia Project (C213/2010) Final Surrender Report E52/2505 for the period 12th September 2 |
| A102563 | 2014 | Dampier (Plutonic) Pty Ltd | Plutonic | 6.7% | Plutonic Project, Final Surrender Report for the period 22/03/2010 - 28/03/2013, P52/1224. |
| A102565 | 2014 | Dampier (Plutonic) Pty Ltd | Plutonic | 35% | Plutonic Project,Final Surrender Report for the period 10/06/1993 – 27/06/2013, M52/368. |
| A102570 | 2014 | Dampier (Plutonic) Pty Ltd | Plutonic | 27% | Plutonic Project, Final Surrender Report for the period 13/01/1992 – 27/06/2013, M52/281. |
| A102573 | 2014 | Dampier (Plutonic) Pty Ltd | Plutonic | 73% | Plutonic Project, Final Surrender Report for the period 13/01/1992 to 27/06/2013, M52/277. |
| A102574 | 2014 | Dampier (Plutonic) Pty Ltd | Plutonic | 64% | Plutonic Project, Final Surrender Report for the pPeriod 13/01/1992 – 27/06/2013, M52/280. |
| A102575 | 2014 | Dampier (Plutonic) Pty Ltd | Plutonic | 10% | Plutonic Project, Final Surrender Report for the period 13/01/1992 to 27/06/2013, M52/285. |
| A103001 | 2014 | Sipa Exploration Nl | Thaduna | <1% | THADUNA PROJECT E52/1673, E52/1674, E52/1858, E52/2356, E52/2357 & E52/2405 ANNUAL REPORT COVERING THE PERIOD |
| A101167 | 2014 | Lodestar Minerals Ltd | Maymia | 24% | Partial Surrender Report for Marymia Project E52/2493 for the period 17th September 2012 to 25th October 2013 |
| A101717 | 2014 | Northern Star Resources Ltd | Plutonic | <1% | PLUTONIC PROJECT ANNUAL REPORT to the Department of Mines and Petroleum for the period 01/01/13 to 31/12/13 fo |
| A103159 | 2014 | Sandfire Resources Nl | East Plutonic | 8.1% | East Plutonic 2014 Combined Mineral Exploration Annual Report Combined Report Group C83/2014 E52/2927, P52/14 |
| A97128 | 2013 | Dampier Gold Ltd | Plutonic Dome | 3.6% | Combined Annual Report for the period 1 January 2012 to 31 December 2012 Plutonic Dome Project C226/2012, E52/ |
| A97197 | 2013 | Barrick (Plutonic) Ltd | Plutonic / Marymia | <1% | Plutonic / Marymia Project, Annual Report for the period 1st January2012 to 31st December 2012, M52/148-150,17 |
| A97675 | 2013 | Dampier Gold Ltd | Plutonic Dome | 8.8% | Combined Surrender Report Plutonic Dome Project C226/2011 for the period ending 26/02/2013 |
| A98659 | 2013 | Sipa Exploration Nl | Thaduna | <1% | Thaduna Project E52/1673, E52/1674, E52/1858, E52/2356, E52/2357 & E52/2405 Annual Report covering the report |
| A99878 | 2013 | Lodestar Minerals Ltd | Peak Hill - Doolgunna - Marymia | 12% | Peak Hill - Doolgunna - Marymia (C213/2010) E52/2492, E52/2493, E52/2505, E52/2734 Annual Report for the perio |
| A101570 | 2013 | Ord River Resources Ltd | Plutonic Dome | 1.6% | C226/2011 ANNUAL EXPLORATION REPORT Reporting Period 01/01/2013 to 31/12/2013 |
| A96687 | 2013 | Baracus Pty Ltd | Marymia | <1% | Marymia Project E52/2686 Annual Technical Report for the period 16 December 2011 – 15 December 2012 |
| A100157 | 2013 | Baracus Pty Ltd | Marymia | <1% | Marymia Project Final Surrender Report for E 52/2686 for the period 16 December 2011 – 7 October 2013 |
| A93152 | 2012 | Dampier Gold Ltd | Plutonic Dome | 3.6% | Combined Annual Report for the period 1 January 2011 to 31 December 2011 Plutonic Dome Project C226/2011 |
| A93217 | 2012 | Barrick (Plutonic) Ltd | Plutonic - Marymia | <1% | PROJECT 6490 MARYMIA PROJECT PROJECT 6520 PLUTONIC PROJECT PROJECT 6523 PLUTONIC EXTENDED PROJECT PROJECT 6530 |
| A94113 | 2012 | Sipa Exploration Nl | Thaduna | <1% | Thaduna Project E52/1673, E52/1674, E52/1858, E52/2356, E52/2357 & E52/2405 annual report covering the period |
| A96076 | 2012 | Lodestar Minerals Ltd | Marymia | 6.5% | Marymia Project, C213/2010, Annual Report for period 12th September 2011 to 1th September 2012. |
| A89778 | 2011 | Barrick (Plutonic) Ltd | Plutonic - Marymia | 3.1% | Marymia Project, Plutonic Project, Plutonic Extended Project, Freshwater Project, Annual Report, Period 1 Janu |
| A90160 | 2011 | Sipa Exploration Nl | Thaduna | <1% | Thaduna Project, Co-Funded Drilling Report for the period ending 30/06/2011, E52/1673,1674, 1858, 2356, 2357,& |
| A90997 | 2011 | Sipa Exploration Nl | Thaduna | <1% | Thaduna Project E52/1673, E52/1674, E52/1858, E52/2356 (provisional inclusion), E52/2357 (provisional inclusio |
| A92371 | 2011 | Lodestar Minerals Ltd | Marymia | 6.5% | MARYMIA PROJECT TENEMENTS E52/2492, E52/2493, E52/2505, E69/2662, 52/2544, 52/2558 ANNUAL TECHNICAL REPORT YEA |
| A86710 | 2010 | Barrick (Plutonic) Ltd | Plutonic / Marymia | 3.1% | 6490 MARYMIA PROJECT 6520 PLUTONIC PROJECT 6523 PLUTONIC EXTENDED Project 6530 FRESHWATER PROJECT ANNUAL REPO |
| A87651 | 2010 | Sipa Exploration Nl | Thaduna | <1% | Thaduna Project E52/1673, E52/1674, E52/1858, E52/2356 (provisional inclusion), E52/2357 (provisional inclusio |
| A81899 | 2009 | Barrick Gold Of Australia Ltd | Plutonic - Marymia | 2.7% | PROJECT 6490 MARYMIA PROJECT, PROJECT 6520 PLUTONIC PROJECT, PROJECT 6523 PLUTONIC EXTENDED PROJECT, PROJECT 6 |
| A77831 | 2008 | Barrick Gold Of Australia Ltd | Plutonic / Marymia | 2.8% | Annual Report Period 1 January 2007 - 31 December 2007 Technical Report No. 1257 Plutonic/ Marymia Project |
| A74697 | 2007 | Barrick Gold Of Australia Ltd | Marymia/ Plutonic | 2.8% | Marymia/ Plutonic Project C94/1999 Annual Report Period 1 January 2006 - 31 December 2006 (Peak Hill) |
| A72015 | 2006 | Barrick Gold Of Australia Ltd | Marymia, Plutonic, Plutonic Extended & F | 2.4% | Marymia, Plutonic, Plutonic Extended & Freshwater Projects, Annual Report, Period 1 January 2005 to 31 Decembe |
| A70185 | 2005 | Barrick Gold Of Australia Ltd | Plutonic/ Marymia | 2.4% | Annual Report Period 1 January 2004 to 31 December 2004 Technical Report No. 1152 Projects 6490 - Marymia, 652 |
| A68298 | 2004 | Barrick Gold Of Australia Ltd | Marymia / Plutonic / Plutonic Extended / | 2.4% | Annual Report for the period 01/01/2003-31/12/2003 Marymia Project,Plutonic Project,Plutonic Extended Project, |
| A66308 | 2003 | Barrick Gold Of Australia Ltd | Plutonic | 2.4% | Annual Report period 1 January 2002 - 31 December 2002 Project 6490 Marymia Project 6520 Plutonic Project 6523 |
| A64818 | 2002 | Barrick Gold Of Australia Ltd | Plutonic - Marymia | 2.3% | Plutonic/Marymia M52/148-150, M52/170-171, M52/183, M52/185 M52/217-220, M52/222-223, M52/226-235, M52/246-247 |
| A64505 | 2002 | Barrick Gold Of Australia Ltd | Plutonic / Marymia | 2.3% | Annual Report Period 1 January 2001 - 31 December 2001. Vertification Report Technical Report No. 1024. Projec |
| A62112 | 2001 | Homestake Gold Of Australia Ltd | Plutonic - Marymia | 1.6% | Development Drilling Annual Report period 1/01/00-31/12/00 Project 520 Plutonic, Project 523 Plutonic Extended |
| A62465 | 2001 | Homestake Gold Of Australia Ltd | Marymia | 2.3% | Project 6490 Marymia Project 6520 Plutonic Project 6523 Plutonic Extended Project 6530 Freshwater M52/148-150, |
| A60012 | 2000 | Homestake Gold Of Australia Ltd | Plutonic/ Marymia | 2.1% | Project 6490,Marymia, Project 6520, Plutonic, Project 6523, Plutonic Extended, Project 6530, Freshwater, M52/1 |
| A60103 | 2000 | Acacia Resources Ltd | Freshwater | 61% | Freshwater Project,Partial Surrender Report for the period 13/01/1992 to 10/01/2000, M52/277-280. [C226/2011] |
| A60176 | 2000 | Homestake Gold Of Australia Ltd | Plutonic - Freshwater - Marymia | 21% | Project 520, Plutonic, Project 523, Plutonic Extended, Project 530, Freshwater, Project 490, Marymia, M52/148- |
| A57727 | 1999 | Homestake Gold Of Australia Ltd | Marymia | <1% | Marymia Exploration - Project 6490 - Technical Report No.812 01/01/98 - 31/12/98 M52/183, 185, 217-220, 226-23 |
| A59117 | 1999 | Haoma Mining Nl | Marymia | 16% | Tenement E52/1153 Marymia Region Annual Report for the period June 1998 to June 1999 |
| A57474 | 1999 | Homestake Gold Of Australia Ltd | Plutonic | 15% | PRojecr 520 - Plutonic. Project 523 - Plutonic Extended. Project 530 - Freshwater. Annual Report 01/01/98-31/1 |
| A57678 | 1999 | Homestake Gold Of Australia Ltd | Plutonic | 15% | Development Drilling Annual Report For the Period 1/01/1998 to 31/12/98, M52/148-150,170,171,222-223,263-264,2 |
| A59118 | 1999 | Haoma Mining Nl | Marymia | 16% | Tenement E52/1153-Marymia Region Partial Relinquishment Report-June 1999 |
| A53884 | 1998 | Plutonic Operations Ltd | Plutonic - Freshwater | 21% | Project 520 - Plutonic, Project 523 - Plutonic Extended, Project 530 - Freshwater. 01/01/1997 - 31/12/1997 M52 |
| A55338 | 1998 | Resolute Ltd | Randall Well | 1.1% | Randall Well Joint Venture M52/253-255, 289-293, 308-309, 351-353, 395, 546-547, 572 01/01/97 - 31/03/97 |
| A55849 | 1998 | Resolute Ltd | Marymia | <1% | Marymia Gold Project - 06/1998 Three Year Proposed Exploration Program E52/634-635, 747, 823-826, 1052 |
| A55893 | 1998 | Haoma Mining Nl | Marymia/Yandal | 16% | Marymia/Yandal, Exploration Licence: 52/1153, 04/06/97 - 03/06/98 |
| A50964 | 1997 | Plutonic Operations Ltd | Plutonic | 21% | Plutonic Operations M52/148 to M52/150 M52/170 M52//171 M52/222 M52/223 M52/305 M52/306 M52/368 to M52/370 P52 |
| A50281 | 1997 | Plutonic Operations Ltd | Plutonic - Freshwater | 21% | Project 520 Plutonic Project 523 Plutonic Extended Project 530 Freshwater M52/148 to M52/150 M 52/170 M52/171 |
| A50981 | 1997 | Plutonic Operations Ltd | Freshwater | 61% | Freshwater Project, Surrender Report M52/282-284 for period 13/01/1992 to 13/02/1997. |
| A51465 | 1997 | Resolute Ltd | Randall Well | <1% | Randall Well Joint Venture E52/920 M52/253 to M52/255 M52/289 to M52/293 M52/308 M52/309 M52/351 to M52/353 M5 |
| A47312 | 1996 | Plutonic Operations Ltd | Plutonic - Freshwater | 21% | Project 520 Plutonic Project and Project 523 Plutonic Extended Project and Project 530 Freshwater M52/148 to M |
| A47535 | 1996 | Resolute Samantha Ltd | Orient Well | <1% | Orient Well Joint Venture E52/614 E52/824 E52/825 E52/826 Annual report December 1995 |
| A47589 | 1996 | Resolute Samantha Ltd | Thaduna | 31% | Thaduna Project, Surrender Report for period September 1993 to March 1996, E52/762. |
| A43761 | 1995 | Plutonic Operations Ltd | Plutonic - Freshwater | 21% | Annual report Project 520: Plutonic M52/148 to M52/150 and Project 523 Plutonic Extended M52/170 and M52/171 M |
| A44223 | 1995 | Resolute Resources Ltd | Orient Well | <1% | Orient Well Joint Venture E52/614 E52/823 E52/824 E52/825 E52/826 Report on Exploration to December 1994 |
| A44226 | 1995 | Resolute Resources Ltd | Randall Well | 1.4% | Randall Well Project M52/253 to M52/255 M52/308 M52/309 M52/395 M52/289 to M52/293 M52/351 to M52/353 E52/320 |
| A45100 | 1995 | Marymia Exploration Nl | Orient Well | <1% | Orient Well Prospect Exploration Licence 52/614 Annual Report on Exploration For the year ended 26th March 199 |
| A41185 | 1994 | Resolute Resources Ltd | Randall Well | 1.4% | (Annual Report for the period 01/93-01/94) Report on Exploration to January 1994 Randall Well Project E52/320 |
| A38354 | 1993 | Stockdale Prospecting Ltd | Peak Hill | 2.3% | Annual report for the period 16/03/92-16/03/93 Peak Hill Project E52/352 |
| A38549 | 1993 | Resolute Resources Ltd | Marymia | 2.3% | Marymia Project, E52/352. Partial Surrender Report for the period 16/03/1989 to 12/03/1993, E52/352. |
| A38043 | 1993 | Resolute Resources Ltd | Randall Well | 1.3% | R Report for the period ending 12/92 Randall Well Project E52/288 E52/320 M52/253-255 M52/289-293 M52/308-309 |
| A38054 | 1993 | Resolute Resources Ltd | Marymia | <1% | Annual report for the period 01/92-12/92 Marymia Project |
| A38270 | 1993 | Marymia Exploration Nl | Orient Well | <1% | Annual Report for the period 27/03/93-26/03/93 Orient Well Project E52/614 |
| A35334 | 1992 | Resolute Resources Ltd | Marymia | 2.3% | PARTIAL SURRENDER REPORT |
| A37926 | 1992 | Plutonic Operations Ltd | Plutonic Extended - Freshwater | 24% | Annual Report for the period 01/01/92-31/12/92 Plutonic Extended Project 523 M52/170-171,222-223,263-264 Fresh |
| A32635 | 1991 | Resolute Resources Ltd | Thadoona Hill | 2.3% | Progress Report - Thadoona Hill E52/352 Period May 1990 - December 1990 |
| A30779 | 1990 | Resolute Resources Ltd | Thadoona Hill | 2.3% | Thadoona Hill Exploration Licence E52/352 Technical Report No:10 May 1990. Resoulte Resources Ltd |
| A32633 | 1990 | Resolute Resources Ltd | Marymia | <1% | Marymia Area WA Interpretation of Aeromagnetic (1990) Data (R Report for 1990; E52/158,320,322,342,352; M52/18 |
| A28050 | 1989 | Resolute Resources Ltd | Marymia | <1% | Marymia Gold Project : Regional review February 1989 E52/288, E52/317, E52/320, E52/322, E52/342 and E52/352 R |
| A7406 | 1977 | Amax Exploration Aust Inc | Beering Unna Tank | 2.1% | Beering Unna Tank Project, Non-statutory Report: Final Report , December 1977, TR70/6405H. |
| A53746 | 1753 | Plutonic Operations Ltd | Plutonic - Freshwater | 21% | Project 520-Plutonic, Project 523-Plutonic Extended, Project 530-Freshwater, Annual Report 01/01/97 - 31/12/97 |
| A38046 | 1753 | Resolute Resources Ltd | Randall Well | 1.7% | R Report for the period ending 07/92 Randall Well Project E52/288 E52/320 M52/253-255 M52/289-293 |
| A40525 | 1753 | Plutonic Operations Ltd | Plutonic - Barramundi - Freshwater - Gol | 21% | Annual Report for the Period 01/01/93 - 31/12/93 Plutonic/Barramundi/Freshwater/Goldfish/Perch/Redfin/Trout Pr |
| A47550 | 1753 | Marymia Exploration Nl | Orient/ Marymia | <1% | Annual report for Exploration Licence E52/614 Orient Well for the period 27th March 1995 to 26th March 1996 |
| A51329 | 1753 | Resolute Ltd | Orient Well | <1% | Orient Well Joint Venture E52/1018 E52/614 E52/823 to E52/826 Annual report 1st January 1996 to 31st December |
Tenure detail Free account
- Current holders & shares
- Holder change history
- Expenditure history
- Conditions & endorsements
- Native title context
- Combined reporting
- Rent status
Tenement intelligence Premium
- Time to expiry
- 23 months · 16 July 2028
- At-risk & opportunity signals
- Expenditure compliance
- 5-year track record
- Spend trend & exploration intensity
- Expiry band
- Ownership age
- Dealings, mortgages & caveats
- Transfer history
What does the exploration record say about this ground?
NextMaps reads every WAMEX report over E 52/4199 into a referenced prospectivity assessment: the geology, the historical programs, the drill intercepts and geochemistry, and the untested gaps — every claim cited back to its source report. New accounts include a free prospectivity report. Prefer the raw due diligence? The Tenure Pack bundles the full register record, tenure history and spatial datasets for this ground.
Open on the map — full register record About AI reports About Tenure PacksDo you hold E 52/4199? Listing is free. A facilitation fee applies only if you sell to a buyer we introduce.
List this tenementTenure data sourced from the DMPE public registers and SLIP WA (© Government of Western Australia, CC BY 4.0), as at 2026-08-21. Compiled by NextMaps. Verify against primary sources before reliance.