L 15/344
L 15/344 is a live miscellaneous licence in the Shire of Coolgardie, Western Australia, held by Evolution Mining (Phoenix) Pty Ltd (part of Evolution Mining Limited). Granted on 28 Mar 2014 for 21 years, it expires on 27 Mar 2035. The ground is covered by 69 historical WAMEX reports.
Register summary
- Holder
- Evolution Mining (Phoenix) Pty Ltd
- Part of
- Evolution Mining Limited (ASX:EVN) as at 2025-06-30
- Local government
- Shire of Coolgardie
- Application received
- 27 Sept 2013
- Commenced
- 28 Mar 2014
- Expiry
- 27 Mar 2035
- Term
- 21 Years
The full record on L 15/344
The register summary says who holds it today. The rest of the record says how they came to, what is attached to it, and whether it is being worked.
- Current holders and their shares, and all 3 changes of holder
- The full record: 31 conditions and 14 endorsements
- Native title context, combined reporting and rent status
- At-risk and opportunity signals, and expenditure compliance over five years
- Every register dealing (7 on record), with mortgages, caveats and transfers flagged
- Expiry band, and how long the holder has had it
Exploration history on this ground
| Report | Year | Operator | Project | On this ground | Title |
|---|---|---|---|---|---|
| A143439 | 2024 | Beacon Mining Pty Ltd | Jaurdi | 2% | E15/1582 Partial Surrender Report For the Period 27 March 2018 to 7 June 2024 |
| A128799 | 2021 | Evolution Mining (Mungari) Pty Ltd | Kunanalling | <1% | Final Surrender Report P16/2788 and P16/2789 Kunanalling Project for the period 13 May 2013 to 12 May 2021 |
| A122627 | 2020 | Scorpion Mining Pty Ltd | Kunanallilng | <1% | Kunanallilng M16/329 Exploration Report For the Period 13 September 2018 to 12 September 2019 |
| A123445 | 2020 | Beacon Minerals Limited | Jaurdi | 1.3% | Annual Report for the Jaurdi Gold Project C134/2018 for the period ending 26 January 2020 |
| A123845 | 2020 | Beacon Minerals Limited | Jaurdi | 2% | Partial Surrender of Jaurdi E15/1582 for the period ending 9/3/2020 |
64 more reports
| A123163 | 2020 | Evolution Mining (Mungari) Pty Ltd | Kintore-Kunanalling | <1% | Annual Report - C3/2017 - Kintore/Kunanalling - 1 January 2019 to 31 December 2019 |
| A119122 | 2019 | Scorpion Mining Pty Ltd | Kunanallilng | <1% | Kunanallilng M16/329 Annual Exploration Report For the Period 13 September 2017 to 12 September 2018 |
| A119552 | 2019 | Evolution Mining (Mungari) Pty Ltd | Kintore - Kunanalling | <1% | Group Annual Technical Report - Kintore Kunanalling - C3/2017 For the Period 1 January 2018 to 31 December 201 |
| A119727 | 2019 | Beacon Minerals Limited | Jaurdi | 1.3% | Annual Report for the Jaurdi Gold Project C134/2018 For the Period 27 January 2018 to 26 January 2019, E15/015 |
| A121862 | 2019 | Evolution Mining (Mungari) Pty Ltd | Kunanalling | 2.3% | Final Surrender Report Kunanalling P16/2900 for the period 9 September 2015 to 8 September 2019 |
| A116303 | 2018 | Evolution Mining (Mungari) Pty Ltd | Kintore - Kunanulling | <1% | Annual Report Kintore - Kunanulling C3/2017 For the Period 1 January 2017 to 31 December 2017 |
| A117260 | 2018 | Evolution Mining (Phoenix) Pty Limited | Kunanalling | <1% | Final Surrender Report P16/2598, P16/2600, P16/2601, P16/2602, P16/2603, P16/2608 Kunanalling Project C3/2017 |
| A118281 | 2018 | Evolution Mining (Mungari) Pty Ltd | Kunnalling | 2.9% | C3/2017 Final Surrender Report P16/2829-2834 Kunnalling Project for 05/09/2014 - 04/09/2018, P16/02829, P16/02 |
| A115917 | 2018 | Scorpion Mining Pty Ltd | Kunanallilng | <1% | Kunanallilng Project M16/329 2017 Exploration Report for the period 13/09/2016 - 12/09/2017 ver. 2 |
| A112431 | 2017 | Evolution Mining (Mungari) Pty Ltd; Hayes Mining Pty Ltd | Kintore - Kunanalling | <1% | Annual Report on the Kintore - Kunanalling Project, C3/2017, for the period 1 January 2016 to 31 December 2016 |
| A107992 | 2016 | Phoenix Gold Limited | Kunanalling | <1% | Kunanalling Project Annual Mineral Exploration Report C153/2006 For the period 1st January 2015 to 31st Decemb |
| A104845 | 2015 | Phoenix Gold Limited | Kunanalling | <1% | Kunanalling Project, Annual Report for the period 01/01/2014 to 31/12/2014, C153/2006. |
| A101201 | 2014 | Phoenix Gold Limited | Kunanalling | <1% | Kunanalling Project, Annual Report, Reporting Group: C153/2006, For the period 1st Januray 2013 to 31st Decem |
| A102617 | 2014 | Kunanalling | <1% | Kunanalling Project P16/2787- 2789 Mineral Exploration Report for Period 13/6/2013 to 12/6/2014 | |
| A96993 | 2013 | Phoenix Gold Limited | Kunanalling | <1% | Kunanalling Project, Annual Report for the period 1st January 2012 to 31st December 2012, M15/696; M16/15..... |
| A97862 | 2013 | Dolphin Resources Pty Ltd | Kunanulling | 2.4% | Kunanulling Project, Annual Report for the period 7th December 2011 to 6th December 2012, E16/387 & P16/2596. |
| A92528 | 2012 | Bm Geological Services Pty Ltd | Castle Hill | 2.2% | Castle Hill Project, Annual Report for the period 07/12/2010 to 06/12/2011, E16/387; P16/2592-2596. (C32/2011) |
| A92835 | 2012 | Phoenix Gold Limited | Kunanulling | <1% | Kunanulling Project, Annual Report for the period 1st January 2011 to 31st December 2011, M15/696; M16/15..... |
| A89371 | 2011 | Phoenix Gold Limited | Kunanalling | <1% | Kunanalling Annual Technical Report For the period 1st January 2010 to 31st December 2010 |
| A89158 | 2011 | Bm Geological Services Pty Ltd | Castle Hill | 2.2% | CASTLE HILL ANNUAL REPORT 2010, REPORTING PERIOD: 7/12/2009 – 6/12/2010, E16/387, P16/2592, P16/2593, P16/2594 |
| A86386 | 2010 | Cazaly Resources Ltd | Kunanalling | <1% | Combined Annual Report, KUNANALLING PROJECT, For the Period 1 January 2009 to 31 December 2009, C153/2006 |
| A81462 | 2009 | Cazaly Resources Ltd | KUNANALLING | <1% | Combined Annual Report KUNANALLING PROJECT, For the Period 1 January 2008 to 31 December 2008. Exploration |
| A77532 | 2008 | Cazaly Resources Ltd | Kunanalling | <1% | Combined Annual Report KUNANALLING PROJECT C153/2006 For the Period 1 January 2007 to 31 December 2007 |
| A74443 | 2007 | Cazaly Resources Ltd | Kunanalling | <1% | Combined Annual Report, Kunanalling Project, For the Period 1 January 2006 to 31 December 2006. (C87/2004) |
| A72502 | 2006 | Cazaly Resources Ltd | Kunanalling | <1% | Combined Annual Report C87/2004, Kunanalling Project, For the Period 1 January 2005 to 31 December 2005, (Kalg |
| A73032 | 2006 | Cazaly Resources Ltd | Kunanalling | <1% | Combined Annual Report, Kunanalling Project P16/2193-2196, P16/2203-2208,2241-2243,2292, For the Period 30 Mar |
| A67091 | 2003 | Placer Dome Asia Pacific Ltd | Kunanalling | 4.5% | Kunanalling South Project (White Flag West), Annual Report 06/06/2002 to 05/06/2003, C101/2000 P16/2004-2005,2 |
| A67141 | 2003 | Placer Dome Asia Pacific Ltd | Kunanalling South | 16% | Surrender Report for the period 06/06/2000-01/07/2003 Kunanalling South Project P16/2004. |
| A67340 | 2003 | Placer Dome Asia Pacific Ltd | Northlander | <1% | Annual Report for the period 01/08/2002 to 31/07/2003 Northlander Project C410/1994: M15/696 P15/2916,3029,326 |
| A65433 | 2002 | Auriongold Exploration Pty Ltd | Northlander | <1% | Northlander Project Annual Reprt 01/08/2001-31/07/2002 C410/1994 Tenements P15/2916, 3029, 3262-3263, 3363, 33 |
| A61763 | 2001 | Goldfields Exploration Pty Ltd | Star of Fremantle | <1% | Annual Report, Star of Fremantle Project, P15/3037, P16/1410, P16/1411, and P16/1412. For the period 19 Novem |
| A63101 | 2001 | Kundana Gold Pty Ltd | Kunanalling South | 4.5% | Kunanalling South Project Reporting Period: 06/06/2000 - 05/06/2001. Tenements P16/2004, P16/2005, P16/2059. [ |
| A63329 | 2001 | Hampton Hill Mining Nl | Northlander | <1% | Northlander Project. Reporting Period: 1/08/2000-31/07/2001 Tenements M15/696, P15/2916, P15/3263, P15/3363, P |
| A59553 | 2000 | Hampton Hill Mining Nl | Northlander | <1% | Combined Annual Technicl Report, Northlander project, P15/3663,3368,3370-3373,3824,P16/1615-1618,1670-1671, Pe |
| A60023 | 2000 | Reefton Mining Nl | Star of Fremantle | <1% | Annual Report, P16/1410, P16/1411, P16/1412, and P15/3037. For the period 19 November 1998 to 18 November 199 |
| A61117 | 2000 | Goldfields Exploration Pty Ltd | Northlander | <1% | Annual Report Northlander Project M15/696,P15/2916,P15/3029, P15/3262-3263,P15/3363,P15/3368,P15/3370-3373,P15 |
| A59055 | 1999 | Goldfields Exploration Pty Ltd | Northlander | <1% | Annual report Northlander J.V. Project Tenements P15/3363 P15/3368 P15/3370-73 P15/3824 P16/1615-18 P16/1670-1 |
| A54527 | 1998 | Hampton Hill Mining Nl | Northlander | <1% | Northlander Project, Combined Annual Technical Report 01/08/96 - 31/07/97 P15/3363, 3368, 3370-3373, 3824, P16 |
| A54750 | 1998 | Resolute Ltd | Bullabulling | <1% | Bullabulling Project, Exploration LicencesE15/217, 312, 332, 333, 407, 408, 437, 438, 453, 454, 455, 461, 462, |
| A54836 | 1998 | Reefton Mining Nl | Star of Fremantle | <1% | Annual Report, Star of Fremantle Project, for the period 19 November 1996 to 18 November 1997. P15/3037, P16/ |
| A55486 | 1998 | Central Kalgoorlie Gold Mines Nl | Fifteen Mile Dam | 17% | Final and Annual Technical Report Fifteen Mile Dam P15/3980 for the Period 6/5/97 to 5/5/98. |
| A57996 | 1998 | Reefton Mining Nl | Star of Fremantle | <1% | Annual Report, P16/1410, P16/1411, P16/1412, and P15/3037. For the period 19 November 1997 to 18 November 199 |
| A52592 | 1997 | Resolute Ltd | Bullabulling | <1% | Annual Report Bullabulling Project Exploration Licences E15/312,217,332,333,407,408,437,438,453,454,461,462 Mi |
| A49852 | 1997 | Hampton Hill Mining Nl | Northlander | <1% | Combined Annual Technical Report Northlander Project P15/3363 P15/3368 P15/3370 to P15/3373 P16/1615 to P16/16 |
| A48633 | 1996 | Reefton Mining Nl | Star of Fremantle | <1% | Star of Fremantle Project, Surrender Report for period 5th May 1995 to 4th May 1996, P16/1479,1480 & 1499. |
| A45299 | 1995 | Hampton Hill Mining Nl | Northlander | <1% | Annual Report, Northlander Project P15/3363, 3368, 3370-3373, P16/1615-1618, 1670-1671 Period 1/8/94 to 31/7/ |
| A45288 | 1995 | Hampton Hill Mining Nl | Northlander | 20% | Final Surrender Report for the period 07/07/94-06/07/95, Northlander Project, P15/3369,3374. |
| A42119 | 1994 | Hampton Hill Mining Nl | Northlander | 1.7% | Annual Report for the period 08/06/93-08/06/94, Northlander Project, P15/3363,3368-3374 P16/1615-1618,1670-167 |
| A6607 | 1976 | Western Mining Corporation Ltd | Ora Banda- Kunanalling- Broad Arrow | <1% | Ora Banda- Kunanalling- Broad Arrow Project, Annual Report for the period 01/05/1973 to 29/06/1976, TR70/5012 |
| A2860 | 1972 | Western Mining Corporation Ltd | Black Cat | 2.8% | Black Cat Project, Annual Report for the year ending 30th June 1972, MC15/1631-1635, 1640-1646 & 1995-2021. |
| A1814 | 1971 | Western Mining Corporation Ltd | Kunanalling | <1% | Kunanalling Project, Annual Report for theyear ending 30th June 1971, MC16/118-119, 124-185, & 190-205. |
| A105 | 1970 | Western Mining Corporation Ltd | Ora Banda- Kunanalling | <1% | Ora Banda- Kunanalling Project, Non-statutory Report: Annual Tenements & Temporary Reserve Reports Data File, |
| A106 | 1970 | Western Mining Corporation Ltd | Ora Banda - Kunanalling | <1% | Ora Banda - Kunanalling Project, Non-statutory Report: Kalgoorlie Regional & Geological Plans (8), circa July |
| A107 | 1970 | Western Mining Corporation Ltd | Ora Banda - Kunanalling | <1% | Ora Banda - Kunanalling Project, Non-statutory Report: Annual Tenements & Temporary Reserve Report ,Data File |
| A112 | 1970 | Western Mining Corporation Ltd | Ora Banda - Kunanalling | <1% | Ora Banda - Kunanalling Project, Non-statutory Report:Annual Report, Folder 11, Sample Data Sheets for Kunanal |
| A108 | 1970 | Western Mining Corporation Ltd | Ora Banda/Kunanalling | <1% | Annual Tenements and Temporary Reserve Report Data File, Ora Banda - Kunanalling Area. |
| A109 | 1970 | Western Mining Corporation Ltd | Ora Banda - Kunanalling | <1% | Ora Banda - Kunanalling Project, Non-statutory Report: Annual Tenements & Temporary Reserve Report,Folder 8,In |
| A110 | 1970 | Western Mining Corporation Ltd | Ora Banda -Kunanalling | <1% | Ora Banda -Kunanalling Project, Non-statutory Report:Annual Tenement & Temporary Reserve Report, Folder 9, Vac |
| A111 | 1970 | Western Mining Corporation Ltd | Ora Banda -Kunanalling | <1% | Ora Banda -Kunanalling Project, Non-statutory Report:Annual Tenements & Temporary Reserve Report Folder 10,Sam |
| A38751 | 1753 | Inco Australia Ltd | Eastern Goldfields regional mapping | <1% | Eastern Goldfields regional mapping |
| A42393 | 1753 | Keela Wee Exploration Ltd | Star of Fremantle | <1% | Annual Report, Star of Fremantle Project, for the period 19 November 1992 to 18 November 1993. P15/3037, P16/ |
| A44564 | 1753 | Reefton Mining Nl | Star of Fremantle | <1% | Annual Report, Star of Fremantle Project, for the period 19 November 1993 to 18 November 1994. P15/3037, P16/ |
| A47442 | 1753 | Reefton Mining Nl | Star of Fremantle | <1% | Annual report for the period 19/11/94-18/11/95 Star of Fremantle Project P15/3037 P16/1410 P16/1411 P16/1412 |
| A48634 | 1753 | Reefton Mining Nl | Star of Fremantle | <1% | Annual Report, Star of Fremantle Project, for the period 19 November 1995 to 18 November 1996. P15/3037, P16/ |
What does the exploration record say about this ground?
NextMaps reads the WAMEX reports over L 15/344 into a referenced prospectivity assessment: the geology, the historical programs, the drill intercepts and geochemistry, and the untested gaps, with every claim cited back to its source report. New accounts include a free report (how the reports work). Prefer the raw due diligence? A Tenure Pack bundles the full register record, tenure history and spatial datasets for this ground.
Get the free report Full register record on the mapDo you hold L 15/344? Listing is free. A facilitation fee applies only if the ground ends up with a buyer we introduce.
List this tenementTenure data sourced from the DMPE public registers and SLIP WA (© Government of Western Australia, CC BY 4.0), as at 2026-10-08. Compiled by NextMaps. Verify against primary sources before reliance.