L 16/104
L 16/104 is a live miscellaneous licence in the Shire of Coolgardie, Western Australia, held by Kundana Gold Pty Limited (part of Evolution Mining Limited). Granted on 28 Mar 2013 for 21 years, it expires on 27 Mar 2034. The ground is covered by 129 historical WAMEX reports.
Register summary
- Holder
- Kundana Gold Pty Limited
- Part of
- Evolution Mining Limited (ASX:EVN) as at 2025-06-30
- Local government
- Shire of Coolgardie
- Application received
- 21 Sept 2012
- Commenced
- 28 Mar 2013
- Expiry
- 27 Mar 2034
- Term
- 21 Years
The full record on L 16/104
The register summary says who holds it today. The rest of the record says how they came to, what is attached to it, and whether it is being worked.
- Current holders and their shares, and the one change of holder on record
- The full record: 68 conditions and 13 endorsements
- Native title context, combined reporting and rent status
- At-risk and opportunity signals, and expenditure compliance over five years
- Every register dealing (15 on record), with mortgages, caveats and transfers flagged
- Expiry band, and how long the holder has had it
Exploration history on this ground
| Report | Year | Operator | Project | On this ground | Title |
|---|---|---|---|---|---|
| A153915 | 2026 | Evolution Mining (Mungari) Pty Ltd | Kunanalling | 3.2% | Kunanalling Final Surrender Report - P15/6659 for the period ending 23/02/2026 |
| A134318 | 2023 | Evolution Mining (Mungari) Pty Ltd | Kunanalling | <1% | Partial Surrender Report - E15/1499 Kunanalling for the period ending 05/02/2023. |
| A126062 | 2021 | Evolution Mining (Mungari) Pty Ltd | Mungari | 2.9% | Final Surrender Report for Mungari P15/6037 for the period 19 December 2016 to 18 December 2020 |
| A122799 | 2020 | Northern Star (Kanowna) Pty Limited | Kundana | <1% | Kundana Annual Report C102/2004 for the period 1 January 2019 to 31 December 2019 |
| A123026 | 2020 | Evolution Mining (Mungari) Pty Ltd | Mungari | <1% | Annual Report C1/2017 Mungari Project for the period 1 January 2019 to 31 December 2019 |
124 more reports
| A124739 | 2020 | Rand Exploration N.L.; Tribune Resources Limited | Seven Mile Hill | <1% | Seven Mile Hill Project C125/2013 Annual Report for the period 2 August 2019 to 1 August 2020 |
| A119241 | 2019 | Northern Star (Kanowna) Pty Limited | Kundana | <1% | Kundana C102/2004 Annual Technical Report for the period 1 January 2018 to 31 December 2018 |
| A119550 | 2019 | Evolution Mining (Mungari) Pty Ltd | Mungari | <1% | Annual Report - Group C1/2017 - Mungari Project For the Period 1 January 2018 to 31 December 2018 |
| A121257 | 2019 | Rand Mining Nl; Tribune Resources N.L. | Seven Mile Hill | <1% | 7 Mile Hill Project Annual Report C125/2013 for the period 2 August 2018 to 1 August 2019 |
| A116058 | 2018 | Northern Star (Kanowna) Pty Limited | Kundana | <1% | Kundana C102/2004 Annual Technical Report for the period 1 January 2017 to 31 December 2017 |
| A116230 | 2018 | Evolution Mining (Mungari) Pty Ltd | Mungari | <1% | Annual Report Mungari Project C1/2017 For the Period 1 January 2017 to 31 December 2017 |
| A118314 | 2018 | Northern Star Resources Ltd | Black Flag Group | 1.9% | Black Flag Group EIS Drilling – Final Report (R#15) |
| A117992 | 2018 | Tribune Resources Limited | Seven Mile Hill | <1% | Seven Mile Hill Project C125/2013 Annual Report for the period 02/08/2017 - 01/08/2018, M15/01233, M15/01234, |
| A112440 | 2017 | Cerep Pty Ltd; Evolution Mining (Mungari) Pty Ltd; Hayes Min | Mungari | <1% | Annual Report for Mungari Project, C1/2017, for the period 1 October 2015 to 31 December 2016, P16/02244 ....E |
| A112160 | 2017 | Northern Star (Kanowna) Pty Limited | Kundana | <1% | Kundana Project C102/2004 Annual Technical Report for the period 1 January 2016 to 31 December 2016, E24/00152 |
| A115204 | 2017 | Tribune Resources Limited | Seven Mile Hill | <1% | Seven Mile Hill Project C125/2013 Annual Report For the Period 2 August 2016 to 1 August 2017, M15/01233, M15/ |
| A108735 | 2016 | Evolution Mining (Mungari) Pty Ltd | Mungari | <1% | Mungari Project C145/2013 Annual Report to the Department of Mines and Petroleum for the period 01/01/2015 to |
| A110438 | 2016 | Tribune Resources Limited | Seven Mile Hill | <1% | Seven Mile Hill Project C125/2013 Annual Report for the period 2 August 2015 to 1 August 2016, M15/01233, M15 |
| A108144 | 2016 | Northern Star (Kanowna) Pty Limited | Kundana | <1% | Kundana Annual Technical Report for the Period 1 January 2015 to 31 December 2015 C102/2004 |
| A108975 | 2016 | Evolution Mining (Mungari) Pty Ltd | Mungari | <1% | E15/965 MUNGARI PROJECT Partial Surrender Report for the period 10/02/2010 to 09/02/2016 |
| A104917 | 2015 | Northern Star Resources Ltd | Kundana | <1% | Kundana Project C102/2004 Annual Report for the period 1 January 2014 – 31 December 2014, E24/152....P26/3574 |
| A105026 | 2015 | La Mancha Resources Australia Pty Ltd | Mungari | <1% | MUNGARI PROJECT ANNUAL REPORT to the Department of Mines and Petroleum for the period 01/01/2014 to 31/12/2014 |
| A107060 | 2015 | Ekjv Management Pty Ltd | Eastern Zuleika Shear Definition Program | 1.9% | Eastern Zuleika Shear Definition Programme - EIS Final Report (R#10) |
| A107233 | 2015 | Rand Exploration Nl; Tribune Resources Nl | Seven Mile Hill | <1% | Annual Technical Exploration report for the period 1st October 2014 – 30th September 2015, Seven Mile Hill |
| A101174 | 2014 | La Mancha Resources Australia Pty Ltd | Mungari | <1% | Mungari Project C145/2013 Annual Report for the period 01/01/2013 to 31/12/2013, E15/960......P15/5265-5267 |
| A101284 | 2014 | Barrick (Australia Pacific) Ltd | Kundana | <1% | Project 8100 Kundana Project 8101 Kundana Project 8103 East Kundana Project 8104 West Kundana Annual Report P |
| A101627 | 2014 | Tribune Resources Nl | 7 Mile Hill | <1% | 7 Mile Hill Project M15/1743 Annual Report for the period 01/01/2013 to 31/12/2013 |
| A103905 | 2014 | Tribune Resources Ltd | 7 Mile Hill | <1% | 7 Mile Hill Project M15/1233, 1234, 1291, 1388, 1394, 1409 M15/1743, M26/563, P26/3617, P15/5182-4 Annual Repo |
| A101666 | 2014 | Cazaly Resources Ltd | Binduli | <1% | Annual Report Binduli Combined Reporting Group C10/2013 for the period 19th December 2012 to the 18th December |
| A96888 | 2013 | Barrick (Australia Pacific) Ltd | Kundana | <1% | PROJECT 8100 KUNDANA PROJECT 8101 KUNDANA PROJECT 8103 EAST KUNDANA PROJECT 8104 WEST KUNDANA Annual Report P |
| A100149 | 2013 | La Mancha Resources Australia Pty Ltd | Mungari West Kurrawang | <1% | Mungari West Kurrawang C41/2007 Annual Report to the Department of Mines and Petroleum for the period 15/03/12 |
| A99436 | 2013 | Tribune Resources Ltd | 7 Mile Hill | <1% | 7 Mile Hill Project, Annual Report for the period 26/07/2012 to 30/09/2013, M15/1233-1234, 1291, 1388, 1394 & |
| A99538 | 2013 | La Mancha Resources Australia Pty Ltd | Mungari East | 1.1% | Mungari East Joint Venture Combined Annual Report for the period 6 September 2012 to 5 September 2013, M15/688 |
| A92352 | 2012 | La Mancha Resources Australia Pty Ltd | Park Dam South | <1% | Park Dam South E15/256 Annual Report to the Department of Mines and Petroleum for the period 19/09/10 to 18/09 |
| A92483 | 2012 | La Mancha Resources Australia Pty Ltd | Mungari East | 1.1% | Mungari East Joint Venture Combined Annual Report for the period 6 September 2010 to 5 September 2011, M15/688 |
| A93042 | 2012 | Barrick Gold Of Australia Ltd | Kundana | <1% | ANNUAL REPORT Period 1 January 2011 – 31 December 2011 C102/2004 |
| A95993 | 2012 | La Mancha Resources Australia Pty Ltd | Mungari East | 1.1% | Mungari East Project, Annual Report for the period 6th September 2010 to 5th September 2011, M15/688-689, 1287 |
| A94095 | 2012 | La Mancha Resources Australia Pty Ltd | Mungari West - Kurrawang | <1% | Mungari West-Kurrawang Project Annual Report to the Department of Mines and Petroleum for the period 15/03/11 |
| A90700 | 2011 | La Mancha Resources Australia Pty Ltd | Mungari West Kurrawang | <1% | Mungari West Kurrawang Project, Annual Report to the Department of Mines and Petroleum for the period 15/03/10 |
| A85972 | 2010 | Barrick Gold Of Australia Ltd | Kundana | <1% | PROJECT 8100 KUNDANA PROJECT 8101 KUNDANA PROJECT 8103 EAST KUNDANA PROJECT 8104 WEST KUNDANA E15/256, E15/634 |
| A88490 | 2010 | La Mancha Resources Australia Pty Ltd | MUNGARI EAST JOINT VENTURE | 1.1% | MUNGARI EAST JOINT VENTURE COMBINED ANNUAL REPORT FOR THE PERIOD 6 SEPTEMBER 2009 TO 5 SEPTEMBER 2010 Tenemen |
| A81372 | 2009 | Barrick Gold Of Australia Ltd | KUNDANA | <1% | ANNUAL REPORT Period 1 January 2008 – 31 December 2008 C102/2004, PROJECT 8100 KUNDANA, PROJECT 8101 KUNDANA, |
| A82352 | 2009 | La Mancha Resources Australia Pty Ltd | MUNGARI WEST AND KURRAWANG | <1% | MUNGARI WEST AND KURRAWANG PROJECTS, ANNUAL REPORT FOR THE PERIOD 15 MARCH 2008 TO 14 MARCH 2009, Tenement(s): |
| A84896 | 2009 | La Mancha Resources Australia Pty Ltd | Mungari East | 1.1% | MUNGARI EAST JOINT VENTURE COMBINED ANNUAL REPORT FOR THE PERIOD 6 SEPTEMBER 2008 TO 5 SEPTEMBER 2009 Tenement |
| A77536 | 2008 | Barrick Gold Of Australia Ltd | Kundana | <1% | ANNUAL REPORT Period 1 January 2007 - 31 December 2007 KUNDANA PROJECT C102/2004 TECHNICAL REPORT No. 1253 |
| A80021 | 2008 | La Mancha Resources Australia Pty Ltd | Mungari East | 1.1% | MUNGARI EAST JOINT VENTURE, COMBINED ANNUAL REPORT FOR THE PERIOD 6 SEPTEMBER 2007 TO 5 SEPTEMBER 2008 |
| A74407 | 2007 | Barrick Gold Of Australia Ltd | Kundana | <1% | Kundana Project C102/2004 Annual Report 1 January 2006 to 31 December 2006 Technical Report No.1214 (Kalgoorli |
| A76375 | 2007 | La Mancha Resources Australia Pty Ltd | Mungari | 1.1% | Mungari East Joint Venture Combined Annual Report For the Period 6 September 2006 to 5 September 2007 C317/199 |
| A72089 | 2006 | Placer Dome Asia Pacific Ltd | Kundana | <1% | Kundana Project, Annual Report 1 January 2005 to 31 December 2005 C102/2004, (PDAP Report No. WA06.012, Kalgoo |
| A72342 | 2006 | Rand Mining Nl | Seven Mile Hill | 2.1% | Surrender Report E15/669, (Seven Mile Hill Project, Surrendered 19/01/06, Kalgoorlie). |
| A72344 | 2006 | Rand Mining Nl | Seven Mile Hill | 1% | Seven Mile Hill Project, Annual Report E15/384,M15/851, Combined Reporting No. C156/1995, 01/01/05 to 31/12/05 |
| A72349 | 2006 | Mines & Resources Australia Pty Ltd | Mungari West (White Foil) | <1% | Mungari West Joint Venture Project, Annual Report for the Period 28 February 2005 to 27 February 2006, M15/829 |
| A73580 | 2006 | Mines & Resources Australia Pty Ltd | Mungari East | 1.1% | Mungari East Joint Venture M15/688-689,836-837,1188,1287, P15/4676-4677, Combined Annual Report C317/1993 for |
| A70352 | 2005 | Placer Dome Asia Pacific Ltd | Kundana | <1% | Kundana Project, Annual report 1 January 2004 to 31 December 2004, C102/2004, E15/256, 634, E16/113, E26/43, M |
| A70355 | 2005 | Rand Mining Nl | Seven Mile Hill | <1% | Annual report for the period 01/01/04 - 31/12/04 Seven Mile Hill Project, C156/1995, E15/234, 378, 384, 385, E |
| A71009 | 2005 | Placer Dome Asia Pacific Ltd | Kundana | <1% | Sub-Audio magnetic survey, Kundana, Placer Dome Asia Pacific Western Australia, Post-activity report (M15/993, |
| A71458 | 2005 | Mines & Resources Australia Pty Ltd | Mungari East | 1.1% | Mungari East Joint Venture Project, Combined annual report for the period from 6 September 2004 to 5 September |
| A68143 | 2004 | Rand Mining Nl | Seven Mile Hill | <1% | Seven Mile Hill (JV) Project, Annual Report Exploration Licences E15/234, 378, 384-385, & 560; Mining Leases M |
| A68216 | 2004 | Placer Dome Asia Pacific Ltd | Kundana GEM | <1% | Kundana Gem Project ,Annual Report P16/1531-1532,P16/1754-1755, E16/113, M15/993, M16/181-182, M16/213-214, M1 |
| A68571 | 2004 | Mines & Resources Australia Pty Ltd | Park Dam North | <1% | Park Dam North Project, Annual report for the period 22 March 2003 to 21 March 2004 (E15/525) |
| A69463 | 2004 | Placer Dome Asia Pacific Ltd | South Park Dam | <1% | South Park Dam Project, Annual report 17/09/03 to 18/09/04, E15/256 |
| A69590 | 2004 | Mines & Resources Australia Pty Ltd | MUNGARI EAST JOINT VENTURE | 1.1% | Mungari East Joint Venture Project, Combined Annual Report for the period 6 September 2003 to 5 September 200 |
| A66114 | 2003 | Tribune Resources Nl | Seven Mile Hill | <1% | Annual Report for period ending 31 December 2002 Seven Mile Hill Project C156/1995: E15/234, 378, 384-385, M15 |
| A66329 | 2003 | Placer Dome Asia Pacific Ltd | Kundana (GEM) | <1% | Kundana (GEM) Project, Annual Report, 01/01/2002-31/12/2002,C22/1999: P16/1531-32, 1754-55, E16/113, M15/993, |
| A66594 | 2003 | Mines & Resources Australia Pty Ltd | Park Dam North | <1% | Park Dam North Project Annual Report for the Period 19 September 2001 to 22 March 2003, Report No PE 03/13, |
| A67584 | 2003 | Mines & Resources Australia Pty Ltd | Mungari East | 1.8% | Mungari East Joint Venture Project, Combined Annual Report for the period 6 September 2002 to 5 September 200 |
| A67644 | 2003 | Mines & Resources Australia Pty Ltd | Park Dam | <1% | Annual Report for the period 19/09/2002-18/09/2003 Park Dam South Project E15/256 |
| A64283 | 2002 | Continental Resource Management Pty Ltd | Seven Mile Hill | <1% | Annual Report for the period ending 31 December 2001 exploration licences 15/234, 378 & 384-385, mining leases |
| A64443 | 2002 | Goldfields Exploration Pty Ltd | Kundana | <1% | Kundana Project Annual Report 2001. Reporting Period: 01/01/2001 - 31/12/2001. Tenements E16/113, M16/181-82, |
| A65732 | 2002 | Mines & Resources Australia Pty Ltd | Park Dam | <1% | Park Dam Project (South) Annual Report For The Period 19 September 2001 To 18 September 2002 PE 02/10. Tenemen |
| A65755 | 2002 | Mines & Resources Australia Pty Ltd | Mungari East | 1.8% | Mungari East Joint Venture Project Combined Annual Report For The Period From 6 September 2001 To 5 September |
| A82878 | 2002 | Placer (Granny Smith) Pty Ltd | Kalgoorlie | <1% | Kalgoorlie High Resolution Gravity Surveys. |
| A62264 | 2001 | Goldfields Exploration Pty Ltd | Kundana | <1% | Kundana Project Annual Report 2000 reporting period 01/01/2000 - 31/12/2000 tenements E15/247, E16/113, M16/18 |
| A62399 | 2001 | Tribune Resources Nl | Seven Mile Hill | <1% | Seven Mile Hill Project Exploration Licences 15/234, 378 And 384-385 Mining Leases 15/850, 851 Annual Report - |
| A63591 | 2001 | Mines & Resources Australia Pty Ltd | Mungari East | 1.8% | Mungari East Joint Venture Project Combined Annual Report for the period from 6 September 2000 to 5 September |
| A63727 | 2001 | Mines & Resources Australia Pty Ltd | Park Dam | <1% | Park Dam Project Annual Report for the period 19 September 2000 to 18 September 2001 tenements E15/256, E15/52 |
| A60028 | 2000 | Tribune Resources Nl | Seven Mile Hill | <1% | Seven Mile Hill Project, Exploration Licences E15/234,378, 384,385, Annual Report - M8083/1, 01/01/1999 to 31/ |
| A60227 | 2000 | Gilt-Edged Mining Nl | Kundana | <1% | Kundana Project Western Australia Technical Report E15/247, E16/113,M16/181,M16/182,M16/213-214,M16/218,P16/15 |
| A60309 | 2000 | Mines & Resources Australia Pty Ltd | Mungari West (White Foil) gold explorati | <1% | Mungari West Project Annual Report for the period 28/02/1999 to 27/02/2000 PE00/15 Tenements E15/197,E15/339,M |
| A61313 | 2000 | Mines & Resources Australia Pty Ltd | Mungari East | 1.8% | Mungari East Joint Venture Project Combined Annual Report for the Period 6 September 1999 to 5 September 2000. |
| A61355 | 2000 | Mines & Resources Australia Pty Ltd | Park Dam | <1% | Park Dam project, Annual report for the Period 19 September 1999 to 18 September 2000. |
| A56998 | 1999 | Gilt-Edged Mining Nl | East Kundana | <1% | East Kundana Project W.A. 02/12/97-03/12/98 Technical Report:E15/247, 113, M16/181-182, P16/1523-1530, P16/15 |
| A58042 | 1999 | Mines & Resources Australia Pty Ltd | Mungari West | <1% | Mungari West Joint Venture Project Annual Report For the Per iod For the Period 28/02/1998 to 27/02/1999, E15/ |
| A58046 | 1999 | Tribune Resources Nl | Seven Mile Hill | <1% | Seven Mile Hill Project E15/234,378,384-385 For the Period 01/01/1998 to 31/12/1998 |
| A59236 | 1999 | Mines & Resources Australia Pty Ltd | Mungari East | 1.1% | Mungari East Joint Venture Project, Combined Annual Report for the Period 6 September 1998 to 5 September 1999 |
| A59376 | 1999 | Mines & Resources Australia Pty Ltd | Park Dam | <1% | Park Dam Joint Venture Project, Combined Annual Report for the Period 19 September 1998 to 18 September 1999, |
| A53234 | 1998 | Tribune Resources Nl | Seven Mile Hill | <1% | Seven Mile Hill Project, Annual Report M8083/1 01/01/97 - 31/12/97 Exploration Licence: 15/234, 378, 384-385, |
| A53481 | 1998 | Gilt-Edged Mining Nl | East Kundana | <1% | East Kundana Project, Annual Report for theperiod 02/12/1996 to 03/12/1997, E15/247; E16/113; M16/181-182; P1 |
| A55413 | 1998 | Mines & Resources Australia Pty Ltd | Park Dam | <1% | Park Dam Project Annual Report On Exploration Licence:15/256 19/09/1997 - 18/09/1998 PE98/26 |
| A56875 | 1998 | Fargo Investments Pty Ltd | Coolgardie | 8.9% | P15/4018 Coolgardie Project Annual Report Reporting Period from 28/10/1997 to 27/10/1998. |
| A56893 | 1998 | Mines & Resources Australia Pty Ltd | Mungari East | <1% | Mungari East Joint Venture Project 06/09/97 - 05/09/98 PE 98/22 E15/193-194, M15/688-689, 691, MLA15/836- |
| A52771 | 1997 | Mines & Resources Australia Pty Ltd | Park Dam | <1% | Park Dam Project Annual report on Exploration Licence 15/256 for the period 19/09/96-18/09/97 PE97/17 Tenemen |
| A53096 | 1997 | Mines & Resources Australia Pty Ltd | Mungari East | <1% | Mungari East Joint Venture Project. Combined Annual Report 06/09/96 - 05/09/97. PE 97/19 E15/193, 194, M15/68 |
| A49378 | 1996 | Mines & Resources Australia Pty Ltd | Mungari | <1% | Mungari East Joint Venture Project Annual report on Tenement E15/193 E15/194 M15/688 M15/689 and M15/691 for t |
| A49822 | 1996 | Tribune Resources Nl | Kundana East | <1% | Exploration Licences E15/247 E15/16/113 Prospecting Licences P16/1339 P16/1375 P16/1523 to P16/1530 P16/1560 t |
| A46710 | 1996 | Tribune Resources Nl | Seven Mile Hill | <1% | Seven Mile Hill Project Exploration Licences E15/234 and E15/378 and E15/385 Mining Lease Applications MLA15/8 |
| A49480 | 1996 | Mines & Resources Australia Pty Ltd | Park Dam | <1% | Park Dam project Annual report on Exploration Licence E15/256 for the period 19 September 1995 to 18 September |
| A49855 | 1996 | Tribune Resources Nl | Seven Mile Hill | <1% | Seven Mile Hill Project Exploration Licences E15/234 E15/378 and E15/385 Mining Lease Applications MLA15/850 a |
| A44454 | 1995 | Rand Mining Nl | Kurrawang | <1% | Kurrawang Project, Exploration Licence E15/234 Annual report - M8083 14/06/94 - 13/06/95. |
| A46147 | 1995 | Tribune Resources Nl | Kurrawang | <1% | Partial Surrender Report for the period 14/06/91-13/06/95 Kurrawang Project E15/234 |
| A45719 | 1995 | Mines & Resources Australia Pty Ltd | Mungari | <1% | Mungari East Joint Venture Project Annual Report on Tenements E15/193, E15/194,E15/340 & M15/688 to M15/691 6 |
| A45853 | 1995 | Mines & Resources Australia Pty Ltd | Park Dam | <1% | Park Dam Project Annual Report on Exploration Licence 15/256 For the period 19 September 1994 to 18 September |
| A46229 | 1995 | Tribune Resources Nl | Kundana East | <1% | Exploration Licence E15/247 Prospecting Licences P16/1339 P16/1375 P16/1523 to P16/1530 P16/1560 to P16/1568 a |
| A41425 | 1994 | Tern Minerals Nl | Kurrawang | <1% | Kurrawang Project, Annual Report for the period 14/06/1993 to 14/06/1994, E15/234. |
| A41942 | 1994 | Mt Manning Resources Ltd | Kurrawang | <1% | Kurrawang Project, PARTIAL SURRENDER REPORT for the perieod 14/06/1991 to 07/06/1994, e15/234. |
| A42570 | 1994 | Afmeco Pty Ltd | Mungari | <1% | Mungari Joint Venture Project Annual report on Tenements EL15/193 EL15/194 E15/340 and ML15/688 to ML45/691 fo |
| A42653 | 1994 | Afmeco Pty Ltd | Park Dam | <1% | Park Dam project Annual report on Exploration Licence E15/256 for the period 19 September 1993 to 18 September |
| A43188 | 1994 | Tribune Resources Nl | East Kundana | <1% | East Kundana Project,Annual Report, Prospecting Licences 16/1339,16/1375,16/1523-30,16/1560-68 and 24/2981-2; |
| A38668 | 1993 | Altus Corporation Pty Ltd | Kundana | <1% | Annual report for the period 01/88-12/92 Kundana Project M16/65 M16/70-71 M16/116-117 P16/1339 |
| A39784 | 1993 | Afmeco Pty Ltd | Mungari | <1% | Annual report for the period 06/09/92-05/09/93 Mungari JV Project E15/193 & E15/194 |
| A38571 | 1993 | Tern Minerals Nl | Kurrawong | <1% | Kurrawong Project, Annual Report for the period 14/06/1991 to 13/06/1993, E15/234. |
| A39261 | 1993 | Afmeco Pty Ltd | Park Dam | <1% | Annual Report for the period 19/09/92-18/09/93 Park Dam Project E15/256 |
| A39357 | 1993 | Tern Minerals Nl | Kundana East | 1% | Annual Report for the period 09/92-09/93 Kundana/Sth Kundana Project P16/1523-1530 P24/2981-2982 |
| A40058 | 1993 | Tern Minerals Nl | Kundana | <1% | Report on Activities Kundana Project P16/1339 P16/1375 P16/1523-1530 P16/1560-1568 P24/2981-2982 Year Ended De |
| A37009 | 1992 | Afmeco Pty Ltd | Park Dam | <1% | Park Dam project Annual report on Exploration Licence 15/256 for the period 19 September 1991 - 18 September 1 |
| A37069 | 1992 | Afmeco Pty Ltd | Mungari | <1% | Annual Report on Exploration Licences E15/193 and E15/194 Mungari Joint Venture Project for the Period 06/09/9 |
| A31177 | 1990 | Acm Gold Ltd | Binduli | <1% | Annual report for the Binduli Project for the year to 06/03/90 L15/91, L15/105, M26/112, M26/115 |
| A27706 | 1989 | Pioneer Minerals Aust Ltd | Mungari | <1% | Mungari, Report on Exploration, 1988, EL15/68. |
| A28484 | 1989 | Pioneer Minerals Aust Ltd | Mungari | <1% | Mungari, Partial Surrender Report, E15/68, period 03/02/86 to 02/02/89. |
| A30971 | 1989 | Pioneer Minerals Aust Ltd | Mungari | <1% | Mungari (JV) Project, Non-statutory Report: Report on RAB Drillling , November 1989, E15/68. |
| A21957 | 1987 | Noranda Australia Ltd | Mungari | <1% | Mungari Project, Non-statutory Report: Reconnaissance RAB Drilling , August-September 1987, E15/68. |
| A20626 | 1987 | Noranda Australia Ltd | Mungari | <1% | Mungari, Soil geochemistry [non-statutory report], April 1987, E15/68 |
| A20529 | 1986 | Noranda Australia Ltd | Mungari | <1% | Mungari Joint Venture, Report on preliminary geological mapping [non-statutory], December 17-22 1985, E15/68 |
| A3974 | 1973 | Amax Exploration Aust Inc | Kundana | <1% | Kundana Project, Final Surrender Report: Final Report & Plates 1-8, MC16/314-317, 326-330, 909-910; MC15/2423 |
| A22737 | 1753 | Defiance Mining Nl | Binduli | <1% | Report on Exploration at Binduli, Western Australia Mar 1987 to Feb 1988 (E15/152, GML26/7040, GML26/7136, GM |
| A38751 | 1753 | Inco Australia Ltd | Eastern Goldfields regional mapping | <1% | Eastern Goldfields regional mapping |
| A82877 | 1753 | Placer Dome Asia Pacific Ltd | Kundana | <1% | Ground Geophysics Survey |
| A89376 | 1753 | Barrick Gold Of Australia Ltd | Kundana | <1% | Kundana Project, ANNUAL REPORT, Period 1 January 2010 – 31 December 2010, C102/2004, E15/256, E15/634, E16/113 |
| A82882 | 1753 | Placer Dome Asia Pacific Ltd | Kundana Detailed | <1% | Ground Geophysics Survey |
What does the exploration record say about this ground?
NextMaps reads the WAMEX reports over L 16/104 into a referenced prospectivity assessment: the geology, the historical programs, the drill intercepts and geochemistry, and the untested gaps, with every claim cited back to its source report. New accounts include a free report (how the reports work). Prefer the raw due diligence? A Tenure Pack bundles the full register record, tenure history and spatial datasets for this ground.