L 29/80
L 29/80 is a live miscellaneous licence in the Shire of Menzies, Western Australia, held by Aurenne Mit Pty Ltd. Granted on 18 Nov 2010 for 21 years, it expires on 17 Nov 2031. The ground is covered by 53 historical WAMEX reports.
Register summary
- Holder
- Aurenne Mit Pty Ltd
- Local government
- Shire of Menzies
- Application received
- 11 Feb 2010
- Commenced
- 18 Nov 2010
- Expiry
- 17 Nov 2031
- Term
- 21 Years
The full record on L 29/80
The register summary says who holds it today. The rest of the record says how they came to, what is attached to it, and whether it is being worked.
- Current holders and their shares, and the one change of holder on record
- The full record: 11 conditions and 2 endorsements
- Native title context, combined reporting and rent status
- At-risk and opportunity signals, and expenditure compliance over five years
- Every register dealing (8 on record), with mortgages, caveats and transfers flagged
- Expiry band, and how long the holder has had it
Exploration history on this ground
| Report | Year | Operator | Project | On this ground | Title |
|---|---|---|---|---|---|
| A124712 | 2020 | Alt Resources Limited | Quin Hills | <1% | C143/2005 Quinn Hills Project Combined Annual Report for the period ending 30/06/2020 |
| A124731 | 2020 | Alt Resources Limited | Bottle Creek West | <1% | E29/0901 Final Report period 1 December 2014 to 24th April 2020, Bottle Creek West project. |
| A118845 | 2019 | Alt Resources Limited | Riverina | <1% | Riverina E29/0901 Annual Report for the period 1st December 2017 to 30th November 2018 |
| A120779 | 2019 | Alt Resources Limited | Bottle Creek | <1% | Combined Annual Technical Report Bottle Creek Project C112/2013 for the period 24 June 2018 to 23 June 2019. T |
| A121025 | 2019 | Alt Resources Limited | Quinns | <1% | Combined Annual Technical Report Quinns Project C143/2005 for the period 1 July 2018 to 30 June 2019, E 29/649 |
48 more reports
| A115983 | 2018 | Mgk Resources Pty Ltd; Maincoast Pty Ltd | Quinns | <1% | Quinns Project E29/901 Annual Report for the period 01/12/2016 - 30/11/2017 |
| A117619 | 2018 | Alt Resources Limited | Bottle Creek | <1% | C112/2013 Bottle Creek Project Combined Report period 24 June 2017 to 23 June 2018 |
| A114483 | 2017 | Lehmann, R | Bottlecreek | <1% | Annual Report for the period 24/06/2015 to 23/06/2016, Bottle Creek Project C112/2013, M 29/150 & M 29/151 |
| A109236 | 2016 | Lehmann, R | Bottle Creek | <1% | C112/2013 Annual Report for the period 24/06/2015 to 23/06/2016, Bottle Creek Project, M 29/150 & M 29/151 |
| A109801 | 2016 | Fe Limited | Mount Ida | 1% | Mount Ida E29/806 Final Surrender Report for the period 18/08/2011 to 26/07/2016 |
| A106701 | 2015 | Lehmann, R | Bottle Creek | <1% | Bottle Creek Project Combined Annual Report C112/2013 (M 29\150 & M 29\151) for the period 24/06/2014 – 23/06/ |
| A104676 | 2015 | Jupiter Mines Ltd | Central Yilgarn - Mount Ida - Mount Maso | <1% | Annual Report for the period 28-11-2013 to 27-11-2014 Central Yilgarn Iron Project - Mt Ida and Mt Mason C180/ |
| A107499 | 2015 | Jupiter Mines Ltd | Mount Ida | <1% | Mt Ida Magnetite Project E29/560-I Final Surrender Report for the period 08/09/2006 to 07/09/2015 |
| A101107 | 2014 | Swan Gold Mining Ltd | Mount Ida | <1% | Mineral Exploration Report Mt Ida Project Combined Report C112/2001 For the Period 1/01/2013 – 31/12/2013, E29 |
| A101594 | 2014 | Jupiter Mines Ltd | Central Yilgarn - Mount Ida - Mount Maso | <1% | Central Yilgarn Iron Project C180/2010 (Mt Ida and Mt Mason) Annual Report for the period 28/11/2012 to 27/11/ |
| A101880 | 2014 | Fe Limited; Swan Gold Mining Ltd | Mount Ida | <1% | Mt Ida Project, Final Surrender Report for the period 09/09/2008 to 22/01/2014, E29/561. |
| A102934 | 2014 | Lehmann, R | Bottle Creek | <1% | BOTTLE CREEK PROJECT M 29\150 & M 29\151 NORTH COOLGARDIE MINERAL FIELD Menzies (SH51-05) 1:250,000 Sheet Mt M |
| A103432 | 2014 | Fe Limited | Mount Ida | 1% | Mt Ida Project E29/806 Annual Report for the period 18/08/2013 to 17/08/2014 |
| A99103 | 2013 | Fe Limited | Mount Ida | 1% | Mt Ida Project E29/806 Annual Report for the period 18/08/2012 to 17/08/2013 |
| A96734 | 2013 | Jupiter Mines Ltd | Central Yilgarn - Mount Ida - Mount Maso | <1% | Central Yilgarn Iron Ore Project (CYIP) Mt Ida Magnetite Project and Mt Mason DSO Hematite Project C180/2010, |
| A97708 | 2013 | Swan Gold Mining Ltd | Mount Ida | <1% | Mt Ida Project, Annual Report for the period 01/01/2012 to 31/12/2012, E29/561, 660, 640- 644, 647 & E29/659; |
| A98888 | 2013 | Lehmann, R | Bottle Creek | <1% | Annual report for the period 24/06/2012 to 23/06/2013, Bottle Creek Project, M 29\150 & M 29\151 |
| A93077 | 2012 | Jupiter Mines Ltd | Mount Ida - Mount Mason | <1% | Annual Report for the period 28/11/10 to 27/11/2011, Central Yilgarn Iron Project - Mt Ida and Mt Mason, C180/ |
| A94518 | 2012 | Fe Limited | Mount Ida | 1% | E29/806 Annual Report, Mount Ida Project, Report Period: 18/08/2011 to 17/08/2012 |
| A89261 | 2011 | Swan Gold Mining Ltd | Mount Ida - Menzies | <1% | Mt Ida Project, Menzies, E29/526 FINAL SURRENDER REPORT FOR THE PERIOD 23/05/2006 to 23/11/2010 |
| A89288 | 2010 | Jupiter Mines Ltd | Mount Ida - Mount Mason | <1% | MounT Ida - Mount Mason Annual Report C180/2010, Period 28/11/09 to 27/11/10 |
| A85967 | 2010 | La Mancha Resources Australia Pty Ltd | Mount Ida | <1% | MT IDA PROJECT COMBINED ANNUAL REPORT FOR THE PERIOD 01/01/2009 TO 31/12/2009 Tenements: E29/526, 539, 559, 56 |
| A88536 | 2010 | Jupiter Mines Ltd | Mount Ida | <1% | Mount Ida Project Annual Report E29/560 Period 08/09/09 to 07/09/10 |
| A81393 | 2009 | La Mancha Resources Australia Pty Ltd | MT IDA | <1% | MT IDA PROJECT COMBINED ANNUAL REPORT FOR THE PERIOD 01/01/2008 TO 31/12/2008, Tenements: E29/481, 506, 526, 5 |
| A84191 | 2009 | La Mancha Resources Australia Pty Ltd | Mount Ida | <1% | MT. IDA PROJECT PARTIAL SURRENDER REPORT E29/526 AUGUST 2009 |
| A77445 | 2008 | La Mancha Resources Australia Pty Ltd | Mount Ida | <1% | MT IDA PROJECT COMBINED ANNUAL REPORT FOR THE PERIOD 01/01/2007 TO 31/12/2007 C112/2001 |
| A74385 | 2007 | La Mancha Resources Australia Pty Ltd | Mount Ida | <1% | Mount Ida Project, C112/2001, Combined Annual Report for the Period 01/01/2007 to 31/12/2007 (Menzies) |
| A76309 | 2007 | Jupiter Mines Ltd | Mount Ida | <1% | Annual Exploration Report for Exploration Licence E29/560 Mt. Ida Iron Ore Project The period 8th September 20 |
| A72271 | 2006 | Mines & Resources Australia Pty Ltd | Mount Ida | <1% | Mt Ida Project, Combined Annual Report for the Period 01/01/2005 to 31/12/2005, C112/2001, (Leonora). |
| A70249 | 2005 | International Goldfields Ltd | Mount Ida | <1% | Annual report for the period 01/01/04 - 31/12/04 Mount Ida Project, C112/2001, E29/120, 378, 385, 386, 388, E2 |
| A68646 | 2004 | International Goldfields Ltd | Mount Ida | <1% | Annual Report for the period 01/01/2003-31/12/2003 Mount Ida Project (C112/2001), E29/120, E29/385, E29/386, E |
| A68814 | 2004 | International Goldfields Ltd | Mount Ida | <1% | Partial Surrender Report E29/388 for the period 31/03/2000 t o 30/03/2003 (end of 3rd year) and 31/03/2000 to |
| A66710 | 2003 | Hamill Resources Ltd | Mount Ida | <1% | Annual Report for the period 01/01/2002 to 31/12/2002 Mount Ida Project C112/2001: E29/120, 385-6, 388, 413, 4 |
| A64536 | 2002 | Hamill Resources Ltd | Mount Ida | <1% | Annual Report For The Period 01/01/2001 to 31/12/2001 Mt Ida Project E29/00120, E29/00385, E29/00386, E29/0038 |
| A53483 | 1998 | Delta Gold Ltd | Copperfield | <1% | Annual Technical Report for the Copperfield Project (E29/186) between 9 December 1996 to 8 December 1997 |
| A53546 | 1998 | Newcrest Mining Ltd | Copperfield | <1% | Copperfield Project. Annual Report for the period 28-10-96 to 27-10-97, E29/167. [Corbetts JV] |
| A53606 | 1998 | Newcrest Mining Ltd | Copperfield | <1% | Copperfield Project. Partial Relinquishment Report Covering Exploration Carried out on the Corbetts Joint Ven |
| A55108 | 1998 | Delta Gold Ltd | Copperfield | <1% | Surrender Report , Copperfield Projejct, 9th December 1994 to 28th April 1998. |
| A50508 | 1997 | Delta Gold Ltd | Copperfield | <1% | Copperfield Project, Annual Report for period 09/12/1995 to 08/12/1996, E29/186. |
| A50813 | 1997 | Newcrest Mining Ltd | Copperfield | <1% | Report No. G700/2 Annual Report for the period ending 31/12/1996 Copperfield Project Spotted Dog Joint Venture |
| A47283 | 1996 | Delta Gold Ltd | Copperfield | <1% | Annual Technical Report for the Copperfield Project between 9 December 1994 to 8 December 1995 |
| A49641 | 1996 | Newcrest Mining Ltd | Copperfield | <1% | Annual Report for the Period Ending 27-10-1996, Copperfield Project, Corbetts Joint Venture, E29/167 |
| A46088 | 1995 | Grumpy Investments Pty Ltd | Copperfield | <1% | Final Surrender Report for the period 03/09/1994 to 06/08/1995 ,Copperfield Project, E29/181. |
| A38751 | 1753 | Inco Australia Ltd | Eastern Goldfields regional mapping | <1% | Eastern Goldfields regional mapping |
| A43197 | 1753 | Archaean Gold Nl | Corbetts Bore | <1% | Corbetts Bore Project, Annual Report, 28/10/1993 to 27/10/1994,Exploration Licence 29/167. |
| A46915 | 1753 | Archaean Gold Nl | Corbetts Bore | <1% | Corbetts Bore Project, Menzies Area, WA, Annual Report 28th October 1994 to October 27th, 1995, Exploration Li |
| A79645 | 1753 | Jupiter Mines Ltd | Mount Ida | <1% | MT IDA PROJECT Annual Report E29/560 Period 08/09/07 to 07/09/08 |
| A84480 | 1753 | Jupiter Mines Ltd | MT IDA | <1% | MT IDA PROJECT Annual Report E29/560, Period 08/09/08 to 07/09/09 |
What does the exploration record say about this ground?
NextMaps reads the WAMEX reports over L 29/80 into a referenced prospectivity assessment: the geology, the historical programs, the drill intercepts and geochemistry, and the untested gaps, with every claim cited back to its source report. New accounts include a free report (how the reports work). Prefer the raw due diligence? A Tenure Pack bundles the full register record, tenure history and spatial datasets for this ground.
Get the free report Full register record on the mapDo you hold L 29/80? Listing is free. A facilitation fee applies only if the ground ends up with a buyer we introduce.
List this tenementTenure data sourced from the DMPE public registers and SLIP WA (© Government of Western Australia, CC BY 4.0), as at 2026-10-09. Compiled by NextMaps. Verify against primary sources before reliance.