L 39/156
Register summary
- Holder
- Murrin Murrin Operations Pty Ltd
- Local government
- Shire of Laverton
- Application received
- 15 Oct 2004
- Commenced
- 29 Mar 2006
- Expiry
- 28 Mar 2027
- Term
- 21 Years
Exploration history on this ground
| Report | Year | Operator | Project | On this ground | Title |
|---|---|---|---|---|---|
| A123165 | 2020 | Murrin Murrin Operations Pty Ltd | Mount Zephyr | <1% | Annual Report Mount Zephyr Calcrete Project - C17/2000 - 1 January 2019 to 31 December 2019 |
| A119546 | 2019 | Murrin Murrin Operations Pty Ltd | Mount Zephyr | <1% | Combined Annual Report Mount Zephyr Calcrete Project C17/2000 for the period 1 January 2018 to 31 December 20 |
| A116258 | 2018 | Murrin Murrin Operations Pty Ltd | Mount Zephyr | <1% | Combined Annual Report for the Mount Zephyr Project - C17/2000 For the Period 1 January 2017 to 31 December 20 |
| A112421 | 2017 | Murrin Murrin Operations Pty Ltd | Mount Zephyr | <1% | Combined Annual Report for the Mount Zephyr Calcrete Project - C17/2000 For the Period 1 January 2016 to 31 De |
| A108254 | 2016 | Murrin Murrin Operations Pty Ltd | Mount Zephyr | <1% | Combined Annual Report for the Mount Zephyr Calcrete Project 1 January 2015 to 31 December 2015, M 39/00446, M |
44 more reports
| A105111 | 2015 | Murrin Murrin Operations Pty Ltd | Mount Zephyr | <1% | Combined Annual Report, Mount Zephyr Project, C17/2000 for the period 1 January 2014 to 31 December 2014 |
| A101678 | 2014 | Murrin Murrin Operations Pty Ltd | Mount Zephyr | <1% | Combined Annual Report For The Period: 1 January 2013 to 31 December 2013 Mount Zephyr Calcrete Project C17/20 |
| A99043 | 2013 | Poseidon Nickel Limited | Windarra | 8.9% | Windarra Nickel Project - Combined Annual Report For the Period 22 April 2012 to 21 April 2013, C79/2006, E38/ |
| A97315 | 2013 | Murrin Murrin Operations Pty Ltd | Mount Zephyr | <1% | Combined Annual Report, Mount Zephyr Project, C17/2000 for the period 1 January 2012 to 31 December 2012, E39/ |
| A92730 | 2012 | Poseidon Nickel Limited | Windarra | 8% | Windarra Project, Final Surrender Report for the period 3rd May 2004 to 23rd November 2011, E39/930. (C79/2006 |
| A93512 | 2012 | Murrin Murrin Operations Pty Ltd | Mount Zephyr | <1% | Combined Annual Report for the Period 1 January 2011 to 31 December 2011, Mt Zephyr Project, C17/2000, E 39/12 |
| A94461 | 2012 | Poseidon Nickel Limited | Windarra | 3.2% | Windarra Nickel Project - Combined Annual Report for the Period 22 April 2011 to 21 April 2012, C79/2006, E38/ |
| A89108 | 2011 | Perto Minerals Ltd | Mount Korong | 3.6% | Mt Korong Project, Partial Surrender Report on Exploration Licence 39/1196. (or the period 4th October 2008 |
| A91181 | 2011 | Poseidon Nickel Limited | Windarra | 3.5% | Windarra Nickel Project - Combined Annual Report for the Period 22 April 2010 to 21 April 2011, C79/2006, E38/ |
| A89851 | 2011 | Murrin Murrin Operations Pty Ltd | Mount Zephyr | <1% | Combined Annual Technical Report for C17/2000, 1 January 2010 to 31 December 2010 |
| A88778 | 2010 | Xserv Pty Ltd | Mount Korong | 3.6% | Mt Korong Project, Annual Report on Exploration Completed Exploration Licence 39/1196, for the period 4th Sep |
| A86528 | 2010 | Regal Resources Ltd | Mount Zephyr | 3.6% | Mt Zephyr Project Annual Technical Report E39/1196 Period Ending 3 September 2009 |
| A86678 | 2010 | Minara Resources Ltd | Mount Zephyr | <1% | Mt Zephyr Project Eleventh Combined Annual Technical Report C17/2000, 1st January 2009 to 31st December 2009, |
| A87137 | 2010 | Poseidon Nickel Limited | Windarra | 3.5% | Windarra Nickel Project - Combined Annual Report for the Period 22 April 2009 to 21 April 2010, CR# C79/2006, |
| A80998 | 2009 | Poseidon Nickel Limited | Windarra Nickel | 8% | Windarra Nickel Project, E39-930 - Partial Surrender Report, 3rd May 2004 to 10th December 2008 |
| A82530 | 2009 | Poseidon Nickel Ltd | Windarra | 3.6% | Windarra Project - Combined Annual Report for the Period 22 April 2008 to 21 April 2009, C79/2006 |
| A77520 | 2008 | Minara Resources Ltd | Mount Zephyr | <1% | TR1414 MT ZEPHYR PROJECT NINTH COMBINED ANNUAL TECHNICAL REPORT C17/2000 |
| A78633 | 2008 | Poseidon Nickel Ltd | Windarra | 3.6% | Windarra Nickel Project - Combined Annual Report for the period 22 April 2007 to 21 April 2008, CR79/2006 |
| A74717 | 2007 | Minara Resources Ltd | Mount Zephyr | <1% | TR1406 Mount Zephyr Project Eighth Combined Annual Technical Report C17/2000 for the Period 1st January 2006 t |
| A75378 | 2007 | Dynasty Metals Australia Ltd | Woodline Well | 8% | EL39/930 Annual Report For the period 3/05/2005 -1/05/2007 Woodline Well Project |
| A75544 | 2007 | Dynasty Metals Australia Ltd | Woodline Well | 8% | Woodline Well Project, Partial Surrender Report for the period 03/05/2005 to 01/05/2007, E39/930. [C79/20006] |
| A75957 | 2007 | Dynasty Metals Australia Ltd | Laverton | 2.8% | LAVERTON PROJECT COMBINED REPORT E38/1450/1586/1587/1622/ 1752, E39/929/930/1325/1326/3272-3274 Annual Technic |
| A72560 | 2006 | Dynasty Metals Australia Ltd | Laverton | 8% | Laverton Project E39/930, Annual Technical Report Period Ending 3 May 2006. |
| A72077 | 2006 | Minara Resources Ltd | Mount Zephyr | <1% | Mt Zephyr Project, Seventh Combined Annual Technical Report C17/2000, E39/482,M39/446,671,672,723, For the Per |
| A70792 | 2005 | Target Minerals Australia Pty Ltd | Laverton | 8% | Laverton (Woodline Well) Project E39/930, Annual technical report for the period ending 2nd May 2005. |
| A70580 | 2005 | Minara Resources Ltd | Mount Zephyr | <1% | Annual technical report for the period 01/01/04 - 31/12/04 Mount Zephyr Project, C17/2000, E39/482, M39/446, M |
| A68340 | 2004 | Minara Resources Ltd | Mt Zephyr | <1% | Combined Annual Report for the period 01/01/2003-31/12/2003 Mount Zephyr (C17/2000), E39/541, E39/482, M39/446 |
| A66299 | 2003 | Anaconda Operations Pty Ltd | Mt Zephyr | <1% | Fourth Combined Annual Technical Report for the period 1st January 2002 to 31st December 2002 Mt Zephyr Projec |
| A65047 | 2002 | Anaconda Operations Pty Ltd | Mt Zephyr | <1% | Mt Zephyr Project Combined Reporting Number C17/2000 Third Annual Technical Report For The Period 1 January 20 |
| A62098 | 2001 | Anaconda Operations Pty Ltd | Mount Zephyr | <1% | Mt Zephyr Project Second Combined Annual Technical Report number C17/2000 for the period 1st January 2000 to 3 |
| A60027 | 2000 | Anaconda Nickel Ltd | Mount Zephyr | <1% | Mt Zephyr Project M39/446,E39/482,E39/541 Combined Reporting Number C17/2000 First Annual Technical Report for |
| A57343 | 1999 | Great Southern Mines Nl | Mount Zephyr | <1% | Partial Surrender Report ,E39/536, Mt Zephyr Project, , January 1999. |
| A57411 | 1999 | Great Southern Mines Nl | Mount Zephyr | <1% | Annual Report E39/536 Mt Zephyr 9 October 1997 to 8 October 1998 |
| A58677 | 1999 | Murrin Murrin Holdings Pty Ltd | Mount Zephyr | <1% | Mt Zephyr Calcrete Project E 39/482 30/05/1998 - 29/05/1999 |
| A59141 | 1999 | Murrin Murrin Holdings Pty Ltd | Mount Zephyr | <1% | Mount Zephyr Calcrete Project E39/482, Partial Surrender Report, 30 May 1996 to 29 May 1999 |
| A55823 | 1998 | Anaconda Nickel Ltd | Mount Zephyr | <1% | Mt Zephyr, Annual Report E39/482, 31/05/97 - 30/05/98 |
| A52275 | 1997 | Voyager Gold Nl | Minara | 20% | Annual report E39/525 Minara Project for the year ending 01/07/1997 |
| A4720 | 1974 | Carpentaria Exp Co Pty Ltd | Woodline Well | 51% | Woodline Well Project, Non-statutory Report:Final Report, March 1974, M39/1549-1551, 1693-1695, 2569-2570, 166 |
| A6945 | 1973 | Kennecott Exp Aust Pty Ltd | Erlistoun | <1% | Aeromag- Raw Data |
| A2637 | 1972 | Amad Nl | Clay Well | 66% | Clay Well Project, Non-statutory Report: Report on Geological Investigation, Clay Well Group, February 1972, M |
| A2638 | 1971 | Amad Nl | Clay Well | 66% | Clay Well Project, Non-statutory Report: Summary Report for the period ending 30th April 1971, MC39/1662-1688 |
| A81627 | 1753 | Minara Resources Ltd | MT ZEPHYR | <1% | MT ZEPHYR PROJECT, TENTH COMBINED ANNUAL TECHNICAL REPORT, C17/2000, Concerning Tenements: Concerning Tenement |
| A38751 | 1753 | Inco Australia Ltd | Eastern Goldfields regional mapping | <1% | Eastern Goldfields regional mapping |
| A51715 | 1753 | Anaconda Nickel Ltd | Murrin Murrin | <1% | Murrin Murrin Nickel Cobalt Project Windarra Calcrete Deposit Annual mineral exploration to the Department of |
Tenure detail Free account
- Current holders & shares
- Holder change history
- Expenditure history
- Conditions & endorsements
- Native title context
- Combined reporting
- Rent status
Tenement intelligence Premium
- Time to expiry
- 7 months · 28 Mar 2027
- At-risk & opportunity signals
- Expenditure compliance
- 5-year track record
- Spend trend & exploration intensity
- Expiry band
- Ownership age
- Dealings, mortgages & caveats
- Transfer history
What does the exploration record say about this ground?
NextMaps reads every WAMEX report over L 39/156 into a referenced prospectivity assessment: the geology, the historical programs, the drill intercepts and geochemistry, and the untested gaps — every claim cited back to its source report. New accounts include a free prospectivity report. Prefer the raw due diligence? The Tenure Pack bundles the full register record, tenure history and spatial datasets for this ground.
Open on the map — full register record About AI reports About Tenure PacksDo you hold L 39/156? Listing is free. A facilitation fee applies only if you sell to a buyer we introduce.
List this tenementTenure data sourced from the DMPE public registers and SLIP WA (© Government of Western Australia, CC BY 4.0), as at 2026-08-21. Compiled by NextMaps. Verify against primary sources before reliance.