M 16/106
M 16/106 is a live mining lease in the Shire of Coolgardie, Western Australia, held by Paddington Gold Pty Limited. Granted on 15 Feb 1989 for 21 years (renewed), it expires on 14 Feb 2031. The ground is covered by 105 historical WAMEX reports.
Register summary
- Holder
- Paddington Gold Pty Limited
- Local government
- Shire of Coolgardie
- Application received
- 27 June 1988
- Commenced
- 15 Feb 1989
- Expiry
- 14 Feb 2031
- Term
- 21 Years (Renewed)
The full record on M 16/106
The register summary says who holds it today. The rest of the record says how they came to, what is attached to it, and whether it is being worked.
- Current holders and their shares, and all 6 changes of holder
- The full record: 38 years of expenditure and 40 conditions
- Native title context, combined reporting and rent status
- At-risk and opportunity signals, and expenditure compliance over five years
- Every register dealing (40 on record), with mortgages, caveats and transfers flagged
- Expiry band, and how long the holder has had it
Exploration history on this ground
| Report | Year | Operator | Project | On this ground | Title |
|---|---|---|---|---|---|
| A137710 | 2023 | Zuleika Gold Limited | North Road | <1% | North Road Project Final Surrender Report 2023, P16/2882eriod ending 30/11/2023. |
| A125596 | 2020 | Torian Resources Limited | North Road | <1% | Annual Report for North Road Gold Project C19/2016 for period ending 28/2/2020 |
| A123515 | 2020 | Northern Star (Kanowna) Pty Limited | Carbine Zuleika | <1% | Carbine Zuleika Annual Technical Report, C154/2009, 5 March 2019 to 4 March 2020 |
| A122620 | 2020 | Torian Resources Ltd | North Road | <1% | North Road Project C29/2016 Annual Report for the period 25 August 2018 to 24 August 2019, P16/02874, P16/0287 |
| A122980 | 2020 | Torian Resources Ltd | Zuleika North | <1% | Zuleika North Project C 28/2016 Annual Report 2019 |
100 more reports
| A123488 | 2020 | Torian Resources Ltd | North Road Project C 29/2016 | <1% | North Road Project C 29/2016 Annual Report 2017 |
| A124749 | 2020 | Paddington Gold Pty Limited | Carbine | 7.6% | Carbine Project Mineral Exploration Report C188/2008 for the period 1 July 2019 to 30 June 2020 |
| A121669 | 2019 | Torian Resources Ltd | Zuleika | <1% | Zuleika Project P 16/2874 Annual Report For the Period 25 August 2017 to 24 August 2018 |
| A121670 | 2019 | Torian Resources Ltd | Zuleika | <1% | Zuleika Project P 16/2875 Annual Report for the period 25 August 2017 to 24 August 2018 |
| A121671 | 2019 | Torian Resources Ltd | Zuleika | <1% | Zuleika Project P 16/2876 Annual Report for the period 25 August 2017 to 24 August 2018 |
| A119902 | 2019 | Northern Star (Kanowna) Pty Limited | Carbine Zuleika | <1% | Carbine Zuleika C154/2009 Annual Technical Report for the period 5 March 2018 to 4 March 2019 |
| A120901 | 2019 | Paddington Gold Pty Limited | Carbine | 6.6% | Carbine Project C188/2008 Mineral Eploration Report for the period 1 July 2018 to 30 June 2019 |
| A121655 | 2019 | Torian Resources Ltd | Zuleika | <1% | Zuleika Project P 16/2945 Annual Report for the period 27 January 2017 to 26 January 2018 |
| A121679 | 2019 | Torian Resources Ltd | Zuleika | <1% | Zuleika Project P 16/2877 Annual Report For the Period 25 August 2017 to 24 August 2018 |
| A121728 | 2019 | Torian Resources Ltd | Zuleika | <1% | Zuleika Project P 16/2882 Annual Report for the period 1 December 2017 to 30 November 2018 |
| A116303 | 2018 | Evolution Mining (Mungari) Pty Ltd | Kintore - Kunanulling | <1% | Annual Report Kintore - Kunanulling C3/2017 For the Period 1 January 2017 to 31 December 2017 |
| A117294 | 2018 | Evolution Mining (Mungari) Pty Ltd | Kratos | <1% | Final Surrender Report Kratos Project C3/2017 for the period 17 June 2010 to 16 June 2018, P16/02554, P16/0255 |
| A117516 | 2018 | Paddington Gold Pty Ltd | Carbine | 6.6% | Carbine Project Mineral Eploration Report, C188/2008, 01 July 2017 - 30 June 2018 |
| A118064 | 2018 | Torian Resources Limited | Zuleika North | <1% | Zuleika North Project C28/2016 Annual Report for the period 01/12/2016 - 30/11/2017 |
| A118224 | 2018 | Torian Resources Limited | Zuleika North | <1% | Zuleika North Project C28/2016 Annual Report for the period 1 December 2017 to 30 November 2018 |
| A118262 | 2018 | Torian Resources Limited | North Road | <1% | North Road Project C29/2016 Annual Report for the period 25 August 2017 to 24 August 2018, P16/02874, P16/0287 |
| A116702 | 2018 | Northern Star (Kanowna) Pty Limited | Carbine Zuleika | <1% | Carbine Zuleika Project Annual Technical Report C154/2009 for the period 05/03/2017 - 04/03/2018 |
| A112431 | 2017 | Evolution Mining (Mungari) Pty Ltd; Hayes Mining Pty Ltd | Kintore - Kunanalling | <1% | Annual Report on the Kintore - Kunanalling Project, C3/2017, for the period 1 January 2016 to 31 December 2016 |
| A112715 | 2017 | Northern Star (Kanowna) Pty Limited | Carbine Zuleika | <1% | Carbine Zuleika C154/2009 Annual Report for the period 05/03/2016 to 04/03/2017 |
| A114436 | 2017 | Paddington Gold Pty Ltd | Carbine | 6.6% | Carbine Project Annual Mineral Exploration Report C188/2008 for the period 1 July 2016 to 30 June 2017 |
| A107992 | 2016 | Phoenix Gold Limited | Kunanalling | <1% | Kunanalling Project Annual Mineral Exploration Report C153/2006 For the period 1st January 2015 to 31st Decemb |
| A109048 | 2016 | Northern Star (Kanowna) Pty Limited | Carbine East | <1% | Carbine East JV Surrender Report C154/2009 for the period 5 March 2008 to 4 March 2016, P 16/02482, P 16/02483 |
| A109807 | 2016 | Torian Resources Limited | North Road | <1% | North Road Project C29/2016 Annual Report For the Period 25 August 2015 to 24 August 2016, P16/02874, P16/0287 |
| A108638 | 2016 | Northern Star (Kanowna) Pty Limited | Carbine East | <1% | C154/2009 Carbine East Annual Technical Report for the period 05/03/2015 to 04/03/2016, M16/00411, P16/02508, |
| A109701 | 2016 | Paddington Gold Pty Ltd | Carbine | 6.5% | Carbine Project C188/2008 Mineral Exploration Report for the period 1 July 2015 to 30 June 2016 |
| A104845 | 2015 | Phoenix Gold Limited | Kunanalling | <1% | Kunanalling Project, Annual Report for the period 01/01/2014 to 31/12/2014, C153/2006. |
| A105538 | 2015 | Northern Star (Kanowna) Limited | Carbine East | <1% | Carbine East C154/2009 Annual Technical Report for the period 5 March 2014 to 4 March 2015, M16/00005.....P 2 |
| A106587 | 2015 | Paddington Gold Pty Ltd | Carbine | 6.5% | Carbine Project Mineral Exploration Report C188/2008 Reporting Period: 1 July 2014 to 30 June 2015 |
| A101201 | 2014 | Phoenix Gold Limited | Kunanalling | <1% | Kunanalling Project, Annual Report, Reporting Group: C153/2006, For the period 1st Januray 2013 to 31st Decem |
| A101979 | 2014 | Northern Star Resources Ltd | North Zuleika | <1% | NORTH ZULEIKA PROJECT 8529 ANNUAL REPORT TECHNICAL REPORT No: Department of Mines and Petroleum Period 9 March |
| A101980 | 2014 | Northern Star Resources Ltd | Carbine East | <1% | Carbine East Project C154/2009 Annual Report 2014 for the period 5th March 2013 – 4th March 2014, P16/2482, P1 |
| A103166 | 2014 | Paddington Gold Pty Ltd | Carbine | 5.8% | Carbine Project Mineral Exploration Report C188/2008 Reporting Period: 1 July 2013 to 30 June 2014, M16/23, M1 |
| A96993 | 2013 | Phoenix Gold Limited | Kunanalling | <1% | Kunanalling Project, Annual Report for the period 1st January 2012 to 31st December 2012, M15/696; M16/15..... |
| A97179 | 2013 | Strategic Projects Mining Pty Ltd | Stackhole Dam | <1% | Stackhole Dam Project Annual Report C22/2012 Period: 1 July 2011 – 30 June 2012 M16/164, M16/229, M16/257, M16 |
| A97659 | 2013 | Barrick (Australia Pacific) Ltd | Carbine East | <1% | Carbine East P16/2482- 2491, P24/4184-4186 Annual Report for the period 5 March 2012 – 4 March 2013 |
| A99397 | 2013 | Strategic Projects Mining Pty Ltd | Stackhole Dam | <1% | Stackhole Dam Project Annual Report C22/2012 Period: 1 July 2012 – 30 June 2013 M16/164, M16/229, M16/257, M16 |
| A97589 | 2013 | Barrick (Kanowna) Ltd | North Zuleika | <1% | PROJECT 8529 NORTH ZULEIKA M16/188, M16/239, M16/27, M16/411, M16/5 P16/2508 ANNUAL REPORT Period 9 March 2012 |
| A98824 | 2013 | Paddington Gold Pty Ltd | Carbine | 8% | Carbine Project Mineral Exploration Report C188/2008 Reporting Period: 1 July 2012 to 30 June 2013, M16/23, M1 |
| A94764 | 2012 | Paddington Gold Pty Ltd | Carbine | 8% | Carbine Project, Mineral Exploration Report, C188/2008, Reporting Period: 1 July 2011 to 30 June 2012 |
| A92835 | 2012 | Phoenix Gold Limited | Kunanulling | <1% | Kunanulling Project, Annual Report for the period 1st January 2011 to 31st December 2011, M15/696; M16/15..... |
| A93429 | 2012 | Barrick (Australia Pacific) Ltd | Carbine East | <1% | Carbine East P16/2482- 2491, P24/4184-4186 Annual Report for the period 5 March 2011 – 4 March 2012, C154/2009 |
| A93430 | 2012 | Barrick (Australia Pacific) Ltd | North Zuleika | <1% | Project 8529 North Zuleika Annual Report for the period 9 March 2011 – 8 March 2012, M16/188, M16/239, M16/27, |
| A91144 | 2011 | Paddington Gold Pty Ltd | Carbine | 5.4% | Carbine Project Mineral Exploration Report C188/2008, Reporting Period: 1 July 2010 to 30 June 2011 |
| A89370 | 2011 | Phoenix Gold Limited | Castle Hill | <1% | Annual Technical Report for Period 1/1/10 to 31/12/10, Castle Hill, Combined Reporting Number C99/1994 Mining |
| A90020 | 2011 | Barrick (Kanowna) Ltd | North Zuleika | <1% | North Zuleika Project, Annual Report for the period 9th March 2010 to 8th March 2011, M16/188, M16/239, M16/27 |
| A90022 | 2011 | Barrick (Kanowna) Ltd | Carbine East | <1% | Carbine East Project, Annual Report for the period 5th March 2010 to 4th March 2011, P16/2482-2491, P24/4184-4 |
| A86740 | 2010 | Barrick Gold Of Australia Ltd | North Zuleika | <1% | Project 8529, North Zuleika, M16/188, M16/239, M16/27, M16/411, M16/44, M16/45, P16/2508, Annual Report, Perio |
| A86635 | 2010 | Barrick (Australia Pacific) Ltd | Carbine East | <1% | Carbine East P16/2482- 2491, P24/4184-4186, Annual Report, Period 5 March 2009 – 4 March 2010 |
| A87601 | 2010 | Paddington Gold Pty Ltd | Carbine | 7% | Carbine Project Mineral Exploration Report C188/2008 Reporting Period: 1July 2009 to 30 June 2010 |
| A82319 | 2009 | Barrick Gold Of Australia Ltd | NORTH ZULEIKA | <1% | PROJECT 8529 NORTH ZULEIKA C303/1997 M16/188, M16/239, M16/27, M16/411, M16/44, M16/45, P16/2508, ANNUAL REPOR |
| A82811 | 2009 | Barrick Gold Of Australia Ltd | CARBINE EAST | <1% | CARBINE EAST PROJECT P16/2482- 2491, P24/4184-4186, ANNUAL REPORT Period 5 March 2008 – 4 March 2009 |
| A84715 | 2009 | Paddington Gold Pty Ltd | Carbine | 6.8% | Carbine Mineral Exploration Report, Period 1 July 2008 to 30 June 2009, Tenements: M16/23, M16/48, M16/58, M16 |
| A77188 | 2008 | Monarch Gold Mining Company Ltd | Davyhurst | <1% | DAVYHURST PROJECT Reporting Group C189/2007 Report Type: Annual Technical Report Report Period: 2 November 200 |
| A78277 | 2008 | Barrick Gold Of Australia Ltd | North Zuleika | 7.8% | ANNUAL REPORT Period 9 March 2007 - 8 March 2008 TECHNICAL REPORT No. 1267 C303/1997 PROJECT 8518, 8529, 8536, |
| A74832 | 2007 | Barrick Gold Of Australia Ltd | North Zuleika | 7.8% | North Zuleika Project C303/1997 Annual Report, Period 9 March 2006 - 8 March 2007 Report No.1223 (Kalgoorlie) |
| A74388 | 2007 | Monarch Gold Mining Company Ltd | Carbine | 1.2% | Carbine Project M16/86, 143, 150, 164, 212, 244, P16/1439, 1512, 1570-73, 1816, 1915-16, 2178-82, 2006 Annual |
| A71993 | 2006 | Siberia Mining Corporation Ltd | Carbine | 1.3% | Carbine Project, Annual Technical Report 01/01/2005 to 31/12/2005, Combined Reporting No. C109/2005, Kalgoorli |
| A72335 | 2006 | Placer Dome Asia Pacific Ltd | North Zuleika | 7.8% | North Zuleika Project, Annual Report, 9 March 2005 to 8 March 2006, Combined Reporting No. C303/1997, (PDAP Re |
| A70065 | 2005 | Siberia Mining Corporation Ltd | Red Dam | <1% | Annual technical report for the period 11/01/04 - 10/01/05 Red Dam Project, M16/143, Kalgoorlie |
| A70234 | 2005 | Siberia Mining Corporation Ltd | Carbine | <1% | Carbine Project, P16/1439, Annual technical report, 11/02/04 - 10/02/05 Kalgoorlie |
| A70420 | 2005 | Placer Dome Asia Pacific Ltd | North Zuleika | 7.8% | North Zuleika Project, Annual Report 9 March 2004 to 8 Marc h 2005 C303/1997 M16/23...M16/411, P16/1373...P24/ |
| A70758 | 2005 | Siberia Mining Corporation Ltd | Red Dam (Carbine) | <1% | Red Dam Project M16/164 Annual technical report 14/05/04 - 13/05/05 (Kalgoorlie). |
| A71206 | 2005 | Siberia Mining Corporation Ltd | Matt Dam (Little Crest Dam) | 6.4% | Matt Dam Project M16/150, Annual Technical Report 03/08/04-02/08/05, (Kalgoorlie). |
| A68508 | 2004 | Placer Dome Asia Pacific Ltd | Carbine/Zuleika | 4.8% | Carbine/Zuleika Project Annual Report 09/03/2003 to 08/03/20 04 C303/1997 M16/27...M16/411, P16/1439...P24/335 |
| A68695 | 2004 | Placer Dome Asia Pacific Ltd | Carbine East | <1% | Carbine East Project,Final Report, Work completed 31/12/1999 to 31/03/2004 (C67/2000), P24/3674 to P24/3676 an |
| A66622 | 2003 | Placer Dome Asia Pacific Ltd | Carbine | <1% | Carbine East Project, Annual Report 01/04/2002-31/03/2003 C67/2000:( P24/2674-76, P16/2029-37). |
| A66658 | 2003 | Placer Dome Asia Pacific Ltd | Carbine | 4.7% | Carbine/ Zuleika Project, Annual Report 09/03/2002 - 08/03/2003 C303/1997: M16/27, 44-5, 48, 58, 86, 106, 143, |
| A64844 | 2002 | Auriongold Exploration Pty Ltd | Carbine East | <1% | Annual Report 01/04/2001 - 31/03/2002 C67/2000 Tenement/s P16/2029-2037, P24/3674-3676 Project Number 1547. |
| A65102 | 2002 | Auriongold Exploration Pty Ltd | Carbine Zuleika | 4.7% | Annual Report Reporting Period 09/03/2000 - 08/03/2002 Combined Reporting NO C303/1997. Tenement/s M16/23, 27, |
| A62415 | 2001 | Goldfields Exploration Pty Ltd | Carbine East | <1% | Carbine East JV 28 March 2000-31 March 2001 Combined Report Number C67/2000 Tenements P16/2029 to P16/2037 and |
| A61372 | 2000 | Centaur Mining & Exploration Ltd | Carbine Zuleika | 5.5% | Mining Leases M16/23,27,44,45,58,86,106,143,150,156,164,188, 212, Prospecting Licences P16/1353-1356,1373,1439 |
| A61943 | 1999 | Centaur Mining & Exploration Ltd | Mount Pleasant | 2.2% | Mount Pleasant Project, Non-statutory Report: Resources Report June 1999. |
| A59105 | 1999 | Centaur Mining & Exploration Ltd | Carbine Zuleika | 5.7% | C303/1997 - Carbine - Zuleika, Joint Annual Report For the Period 9/03/1998 to 8/03/1999 (M16/23, M16/27, M16/ |
| A54403 | 1998 | Darkdale Pty Ltd | Carbine | <1% | Carbine Project, Annual Report P16/1703-1712, P24/3310-3312 01/02/97 - 31/01/98 |
| A55230 | 1998 | Centaur Mining & Exploration Ltd | Carbine Zuleika | 5.7% | C303/1997 - Carbine/Zuleika Joint Annual Report 09/03/97 - 08/03/98 Mining Licence: M16/23, 27, 44-45, 48, 58, |
| A50768 | 1997 | Darkdale Pty Ltd | Carbine | <1% | Carbine Project Annual report PL16/1703 - 1712, PL24/3310 - 3312 01 February 1996 to 31 January 1997 |
| A48542 | 1996 | Newcrest Mining Ltd | Breakaway Dam | 12% | Newcrest Report No. WORA 104 OB No. 352 Ora Banda Gold Mine Breakaway Dam Project M16/58 M16/106 M16/143 M16/1 |
| A47255 | 1996 | Newcrest Mining Ltd | Carbine | <1% | Report No. WORA 100 OB No.349 Carbine Project Exploration Report on Leases M16/27 M16/188 P16/1353 to P16/1356 |
| A43654 | 1995 | Orion Resources Nl | Carbine | <1% | Annual Technical Report for Carbine Project Ora Banda W.A. (February 1995) |
| A43860 | 1995 | Newcrest Mining Ltd | Carbine | <1% | Report No. WORA 78 OB NO. 329 Ora Banda Gold Mine Carbine Project Exploration Report on Leases M16/27 M16/188 |
| A44946 | 1995 | Newcrest Mining Ltd | Breakaway Dam | 12% | Newcrest Mining Report No. WORA 85 OB No. 334 Ora Banda Gold Mine Breakaway Dam Project Exploration Report on |
| A41999 | 1994 | Newcrest Mining Ltd | Breakaway Dam | 12% | Breakaway Dam Project Exploration Report on Leases M6/58, M16/106,M16/143,M16/150,M16/164, P16/1439, P6/1570-1 |
| A42058 | 1994 | Newcrest Mining Ltd | Carbine | <1% | Annual Report for the period 01/01/92-31/12/93 Carbine Project M16/27,188 P16/1353-1356 |
| A39998 | 1993 | Newcrest Mining Ltd | Breakaway Dam | 12% | Breakaway Dam Project Exploration Report on Leases M16/58, M16/106, M16/143, M16/150, M16/164, P16/1439, P16/1 |
| A37331 | 1992 | Newcrest Mining Ltd | Carbine | <1% | Annual Report for the Period 01/10/90 - 01/06/92 Carbine Project GML16/1292, M16/42, P16/1353-1358, P24/2657- |
| A37470 | 1992 | Newcrest Mining Ltd | Breakaway Dam | 12% | Annual report for the period 05/91 to 05/92 Breakaway Dam Project M16/58, M16/106, M16/143, M16/150, M16/164, |
| A32916 | 1991 | Poseidon Ltd | Matt Dam | 6.4% | Matt Dam Project M16/150 Annual Report 1990 Kalgoorlie 1:250000 Sheet SH 51-9 |
| A32917 | 1991 | Poseidon Ltd | Little Crest Dam | <1% | Little Crest Dam Project Annual Report 1990 P16/657, P16/658, P16/1042, P16/1043 and M16/143 Poseidon Explorat |
| A32946 | 1991 | Poseidon Ltd | Twelve Mile Dam | 65% | Twelve Mile Dam Project Annual report 1990 M16/58 P16/645- 649 Kalgoorlie 1:250,000 Sheet SH51-9 Report No: 91 |
| A31512 | 1990 | Poseidon Ltd | Twelve Mile Dam | 65% | Twelve Mile Dam Project,1989-1990 Annual Report (RAB Drilling Completion Report) , July 1990, M16/58, 106; P16 |
| A31267 | 1990 | Poseidon Ltd | Little Crest Dam | <1% | Annual report 1989 Little Crest Dam project P16/538 to P16/539, P16/488 to P16/490, P16/492, P16/493, P16/1402 |
| A31268 | 1990 | Poseidon Ltd | Twelve Mile Dam | 65% | Annual report 1989 Twelve Mile Dam project M16/58, M16/106 and P16/645 to P16/649. Poseidon Limited Report 10/ |
| A25820 | 1988 | Poseidon Ltd | Twelve Mile dam | 51% | Twelve Mile dam project, Coolgardie mineral field, Western Australia, Annual report June 1987 - June 1988 and |
| A21090 | 1987 | Poseidon Minerals Ltd | Twelve Mile Dam | 100% | Twelve Mile Dam Project Coolgardie Mineral Field Western Australia Annual report June 1986 to June 1987 and Au |
| A18003 | 1986 | Freeport Of Australia Inc | Twelve Mile Dam | 100% | Twelve Mile Dam Project Prospecting Licences P16/126 P16/128 P16/266 to P16/270 (incl) P16/334 to P16/336 (inc |
| A15801 | 1985 | Freeport Of Australia Inc | Twelve Mile Dam | 100% | Twelve Mile Dam project Annual report 22/06/84-21/6/85 prospecting licences P16/126,P16/128,P16/334,P16/335,P1 |
| A3022 | 1972 | Carpentaria Exp Co Pty Ltd | Carbine | 18% | Carbine Project, Non-statutory Report: Final Report, March 1972, MC16/45-56, & 280-282. |
| A51014 | 1753 | Centaur Mining & Exploration Ltd | Carbine | <1% | Mining Lease M16/58 Carbine Annual report for the period 9th March 1996 to 10 March 1997 Centaur Mining and Ex |
| A38751 | 1753 | Inco Australia Ltd | Eastern Goldfields regional mapping | <1% | Eastern Goldfields regional mapping |
| A50373 | 1753 | Centaur Mining & Exploration Ltd | Ora Banda South | 6% | Prospecting Licences P16/1353 to P16/1356 P16/1374 P16/1439 P16/1512 P16/1570 to P16/1573 and Mining Leases M1 |
What does the exploration record say about this ground?
NextMaps reads the WAMEX reports over M 16/106 into a referenced prospectivity assessment: the geology, the historical programs, the drill intercepts and geochemistry, and the untested gaps, with every claim cited back to its source report. New accounts include a free report (how the reports work). Prefer the raw due diligence? A Tenure Pack bundles the full register record, tenure history and spatial datasets for this ground.
Get the free report Full register record on the mapDo you hold M 16/106? Listing is free. A facilitation fee applies only if the ground ends up with a buyer we introduce.