M 16/545
M 16/545 is a live mining lease in the Shire of Coolgardie, Western Australia, held by Evolution Mining (Mungari) Pty Ltd (part of Evolution Mining Limited). Granted on 25 Oct 2016 for 21 years, it expires on 24 Oct 2037. The ground is covered by 182 historical WAMEX reports.
Register summary
- Holder
- Evolution Mining (Mungari) Pty Ltd
- Part of
- Evolution Mining Limited (ASX:EVN) as at 2025-06-30
- Local government
- Shire of Coolgardie
- Application received
- 4 Mar 2016
- Commenced
- 25 Oct 2016
- Expiry
- 24 Oct 2037
- Term
- 21 Years
The full record on M 16/545
The register summary says who holds it today. The rest of the record says how they came to, what is attached to it, and whether it is being worked.
- Current holders and their shares (no change of holder on record)
- The full record: 10 years of expenditure, 6 conditions and 12 endorsements
- Native title context, combined reporting and rent status
- At-risk and opportunity signals, and expenditure compliance over five years
- Every register dealing (3 on record), with mortgages, caveats and transfers flagged
- Expiry band, and how long the holder has had it
Exploration history on this ground
| Report | Year | Operator | Project | On this ground | Title |
|---|---|---|---|---|---|
| A150075 | 2025 | Evolution Mining (Mungari) Pty Ltd | Kunanalling | <1% | Final Surrender Report - P16/3018 Kunanalling for the period ending 20/07/2025. |
| A138086 | 2024 | Zuleika Gold Limited | Castle East | <1% | Zuleika Project Annual Report 2023, Castle East, C218/2021 for the period ending 02/11/2023. |
| A142835 | 2024 | Zuleika Gold Limited | Castle East - Zuleika | <1% | Zuleika Project Annual Report Castle East P16/2944 for the period ending 17/03/2024 |
| A145127 | 2024 | Zuleika Gold Limited | Castle East | <1% | Castle East Final Surrender Report 2024, P16/2943, for the period ending 21/11/2024 |
| A145479 | 2024 | Zuleika Gold Limited | Castle East | <1% | Zuleika Project Final Surrender Report 2023, Castle East, P16/2944 |
177 more reports
| A145531 | 2024 | Zuleika Gold Limited | Castle East | <1% | Zuleika Project Final Surrender Report Castle East P16/2960 for the period ending 31/10/2024 |
| A145703 | 2024 | Zuleika Gold Limited | Castle East | <1% | Zuleika Project Final Surrender Report Castle East P16_3275 for the period 16 September 2022 to 4 November 202 |
| A135137 | 2023 | Zuleika Gold Limited | Castle East | <1% | Zuleika Project Annual Report 2022, Castle East, P16/2944 for the period ending 17/03/2023. |
| A133582 | 2023 | Zuleika Gold Limited | Castle East | <1% | Zuleika Project Annual Report 2022, Castle East, C218/2021 for the period ending 02/11/2022. |
| A130465 | 2022 | Zuleika Gold Limited | Castle East | <1% | Zuleika Project Annual Report 2021, Castle East, P16/2944 for the period ending 17/03/2022. |
| A129678 | 2022 | Zuleika Gold Limited | Castle East | <1% | Zuleika Project Annual Report 2021, Castle East, C218/2021 for the period ending 02/11/2021 |
| A126294 | 2021 | Zuleika Gold Limited | Zuleika | <1% | Zuleika Project Annual Report 2020, Castle East, P16/2960, for the period ending 17/01/2021 |
| A126847 | 2021 | Zuleika Gold Limited | Castle East | <1% | Zuleika Project Annual Report 2020, Castle East, P16/2944 for the period 18 March 2020 to 17 March 2021 |
| A125867 | 2021 | Dampier Gold Limited | Zuleika | <1% | Zuleika Project Annual Report 2020, Castle East, P16/2943 for the period ending 21/11/2020 |
| A123163 | 2020 | Evolution Mining (Mungari) Pty Ltd | Kintore-Kunanalling | 5.2% | Annual Report - C3/2017 - Kintore/Kunanalling - 1 January 2019 to 31 December 2019 |
| A123721 | 2020 | Torian Resources Ltd | Zuleika | <1% | Zuleika Project P 16/2960 Annual Report for the period ending 17/1/2020 |
| A122766 | 2020 | Torian Resources Ltd | Zuleika | <1% | Zuleika Project P16/2943 Annual Report for the period ending 21/11/2019 |
| A123016 | 2020 | Torian Resources Ltd | Zuleika | <1% | Zuleika Project P 16/2960 Annual Report for the period ending 17/01/2019 |
| A123513 | 2020 | Evolution Mining (Mungari) Pty Ltd | Kunanalling | <1% | Final Surrender Report P16/2669 and P16/2670, Kunanalling, 6 October 2011 to 5 October 2019 |
| A123605 | 2020 | Torian Resources Ltd | Zuleika | <1% | Zuleika Project P 16/2944 Annual Report for the period ending 16/3/2019 |
| A121619 | 2019 | Torian Resources Ltd | Zuleika | <1% | Zuleika Project P 16/2943 Annual Report for the period 22 November 2017 to 21 November 2018 |
| A119174 | 2019 | Evolution Mining (Mungari) Pty Ltd | Ardenne | <1% | Final Surrender Report Ardenne Project C03/2017, P16/2610, P16/2611, P16/2612 and P16/2613 for the period 10 J |
| A119550 | 2019 | Evolution Mining (Mungari) Pty Ltd | Mungari | <1% | Annual Report - Group C1/2017 - Mungari Project For the Period 1 January 2018 to 31 December 2018 |
| A119552 | 2019 | Evolution Mining (Mungari) Pty Ltd | Kintore - Kunanalling | 5% | Group Annual Technical Report - Kintore Kunanalling - C3/2017 For the Period 1 January 2018 to 31 December 201 |
| A119926 | 2019 | Evolution Mining (Mungari) Pty Ltd | Kunanalling | <1% | Surrender Report P16/2862 Kunanalling Project for the period 4 February 2015 to 3 February 2019 |
| A121632 | 2019 | Torian Resources Ltd | Zuleika | <1% | Zuleika Project P16/2960 Annual Report For the Period 18 January 2017 to 17 January 2018 |
| A121662 | 2019 | Torian Resources Ltd | Zuleika | <1% | Zuleika Project P 16/2622 Final Report for the period 15/03/2017-16/02/2018. |
| A115817 | 2018 | Evolution Mining (Mungari) Pty Ltd; Evolution Mining (Phoeni | Kintore - Kunanalling | <1% | Final Surrender Report for P16/2586 and P16/2797 [C3/2017] for the period 4 January 2010 to 3 January 2018 |
| A116230 | 2018 | Evolution Mining (Mungari) Pty Ltd | Mungari | <1% | Annual Report Mungari Project C1/2017 For the Period 1 January 2017 to 31 December 2017 |
| A116303 | 2018 | Evolution Mining (Mungari) Pty Ltd | Kintore - Kunanulling | 3.8% | Annual Report Kintore - Kunanulling C3/2017 For the Period 1 January 2017 to 31 December 2017 |
| A117294 | 2018 | Evolution Mining (Mungari) Pty Ltd | Kratos | <1% | Final Surrender Report Kratos Project C3/2017 for the period 17 June 2010 to 16 June 2018, P16/02554, P16/0255 |
| A117941 | 2018 | Evolution Mining (Mungari) Pty Ltd | Kunanalling | <1% | Final Surrender Report P16/2583 Kunanalling Project for the period 8 July 2010 to 7 July 2018 |
| A118276 | 2018 | Torian Resources Limited | Zuleika | <1% | Zuleika P16/2943 Annual Report for the period 22 November 2016 to 21 November 2017 |
| A112431 | 2017 | Evolution Mining (Mungari) Pty Ltd; Hayes Mining Pty Ltd | Kintore - Kunanalling | 3.6% | Annual Report on the Kintore - Kunanalling Project, C3/2017, for the period 1 January 2016 to 31 December 2016 |
| A112440 | 2017 | Cerep Pty Ltd; Evolution Mining (Mungari) Pty Ltd; Hayes Min | Mungari | <1% | Annual Report for Mungari Project, C1/2017, for the period 1 October 2015 to 31 December 2016, P16/02244 ....E |
| A113875 | 2017 | Torian Resources Limited | Balgarrie | <1% | Balgarrie Project C52/2011 Annual Report For the Period 15 March 2016 to 14 March 2017, P16/02621, P16/02622, |
| A107992 | 2016 | Phoenix Gold Limited | Kunanalling | <1% | Kunanalling Project Annual Mineral Exploration Report C153/2006 For the period 1st January 2015 to 31st Decemb |
| A109675 | 2016 | Torian Resources Limited | Stackhole Dam Project | <1% | Stackhole Dam Project Annual Report, 1 July 2015 to 30 June 2016 |
| A110055 | 2016 | Evolution Mining (Mungari) Pty Ltd | Kintore | 14% | Annual Report for the period 1st July 2015 to 30th June 2016, Kintore, Kintore East, Carbine, Broads Dam, Star |
| A108698 | 2016 | Cascade Resources Ltd | Balgarrie | <1% | Balgarrie Project C52/2011, P16/02621, P16/02622, P16/02623 Annual Report for the period 15/03/2015 to 14/03/2 |
| A107223 | 2015 | Torian Resources Ltd | Stackhole Dam | <1% | Stackhole Dam Project Annual Report C22/2012 Period: 1 July 2014 – 30 June 2015 M16/229, M16/491,P16/2479-81 |
| A107613 | 2015 | Phoenix Gold Limited | Broads Dam | <1% | Broad Dam Project C194/2010 Combined Mineral Exploration Report for the period 1st October 2014 to 30th Septem |
| A104845 | 2015 | Phoenix Gold Limited | Kunanalling | <1% | Kunanalling Project, Annual Report for the period 01/01/2014 to 31/12/2014, C153/2006. |
| A106632 | 2015 | La Mancha Resources Australia Pty Ltd | Kintore | 12% | Annual Report for the period 1st July 2014 to 30th June 2015,C144/2014 Kintore, Kintore East, Carbine, Broads |
| A101201 | 2014 | Phoenix Gold Limited | Kunanalling | <1% | Kunanalling Project, Annual Report, Reporting Group: C153/2006, For the period 1st Januray 2013 to 31st Decem |
| A103786 | 2014 | Strategic Projects Mining Pty Ltd | Stackhole Dam | <1% | Stackhole Dam Project Annual Report C22/2012 Period: 1 July 2013 – 30 June 2014 M16/229,M16/491,P16/2479-81 |
| A103169 | 2014 | La Mancha Resources Australia Pty Ltd | Kintore | 12% | Annual Report for the period 1st July 2013 to 30th June 2014, Kintore, Kintore East, Carbine, Broads Dam, Star |
| A103681 | 2014 | Phoenix Gold Limited | Broads Dam | <1% | Broad Dam Project C194/2010 Annual Mineral Exploration Report for Period 1/10/13 to 30/09/14 |
| A96993 | 2013 | Phoenix Gold Limited | Kunanalling | <1% | Kunanalling Project, Annual Report for the period 1st January 2012 to 31st December 2012, M15/696; M16/15..... |
| A97179 | 2013 | Strategic Projects Mining Pty Ltd | Stackhole Dam | <1% | Stackhole Dam Project Annual Report C22/2012 Period: 1 July 2011 – 30 June 2012 M16/164, M16/229, M16/257, M16 |
| A97967 | 2013 | La Mancha Resources Australia Pty Ltd | Kintore | 21% | Kintore Project, Annual Report for the period 06/03/2012 to 05/03/2013, P16/2358-2374, 2586, 2589-2591, 2642-2 |
| A98139 | 2013 | Phoenix Gold Limited | Red Dam | 8.9% | Red Dam Project, Annual Report for the period 19th April 2012 to 18th April 2013, M16/344. |
| A98371 | 2013 | Western Resources Pty Ltd | Balgarrie | <1% | Annual Report for the period 15 March 2012 to 14 March 2013, Balgarrie Project, Combined Reporting Group C52/2 |
| A99397 | 2013 | Strategic Projects Mining Pty Ltd | Stackhole Dam | <1% | Stackhole Dam Project Annual Report C22/2012 Period: 1 July 2012 – 30 June 2013 M16/164, M16/229, M16/257, M16 |
| A100441 | 2013 | Phoenix Gold Limited | Broads Dam | <1% | Mineral Exploration Report for Period 1/10/12 to 30/09/13 Broads Dam Project |
| A92835 | 2012 | Phoenix Gold Limited | Kunanulling | <1% | Kunanulling Project, Annual Report for the period 1st January 2011 to 31st December 2011, M15/696; M16/15..... |
| A93643 | 2012 | Siburan Resources Limited | Balgarrie | <1% | Annual report Balgarrie Project Exploration Licence P16/2621, P16/2622 & P16/2623 C52/2011 Period 15 March 201 |
| A94030 | 2012 | Carbine Resources Ltd | Red Dam | 8.9% | Red Dam Project M16/344 Annual Technical Report 2011 - 2012 |
| A94167 | 2012 | La Mancha Resources Australia Pty Ltd | Kintore | 21% | Annual Report for the period 6 March 2011 to 5 March 2012, Kintore, Kintore East and Carbine Projects, P16/235 |
| A91144 | 2011 | Paddington Gold Pty Ltd | Carbine | <1% | Carbine Project Mineral Exploration Report C188/2008, Reporting Period: 1 July 2010 to 30 June 2011 |
| A89370 | 2011 | Phoenix Gold Limited | Castle Hill | <1% | Annual Technical Report for Period 1/1/10 to 31/12/10, Castle Hill, Combined Reporting Number C99/1994 Mining |
| A90210 | 2011 | Siburan Resources Limited | Balgarrie | <1% | Balgarrie Project, Annual Report for the period 15th March 2010 to 14th March 2011, P16/2621, P16/ 2622 & P16/ |
| A90864 | 2011 | Carbine Resources Ltd | Red Dam | 8.9% | Red Dam Project M16/344, Annual Technical Report 2010 - 2011 |
| A90701 | 2011 | La Mancha Resources Australia Pty Ltd | Broads Dam | 32% | Broads Dam Project Annual Report to the Department of Mines and Petroleum for the period 14/04/2010 to 13/04/2 |
| A90752 | 2011 | La Mancha Resources Australia Pty Ltd | Kintore East - Carbine | 19% | Annual Report for the period 6 March 2010 to 5 March 2011, Kintore, Kintore East and Carbine Projects C187/200 |
| A86987 | 2010 | La Mancha Resources Australia Pty Ltd | Red Dam - Broads Dam | 32% | Red Dam and Broads Dam Projects Annual Report for the Period 14th June 2009 to 13th June 2010 |
| A86988 | 2010 | La Mancha Resources Australia Pty Ltd | Kintore East | 75% | Kintore East Project Annual Report for the period 14th June 2009 to 13th June 2010 |
| A87961 | 2010 | Carbine Resources Ltd | Red Dam | 8.9% | Red Dam Project M16/344, Annual Technical Report. |
| A87109 | 2010 | La Mancha Resources Australia Pty Ltd | Kintore | 52% | Kintore Annual Report for the period 06/03/2009 to 05/03/2010, P16/2358 and 2369-2374, C187/2009 |
| A87601 | 2010 | Paddington Gold Pty Ltd | Carbine | <1% | Carbine Project Mineral Exploration Report C188/2008 Reporting Period: 1July 2009 to 30 June 2010 |
| A81462 | 2009 | Cazaly Resources Ltd | KUNANALLING | <1% | Combined Annual Report KUNANALLING PROJECT, For the Period 1 January 2008 to 31 December 2008. Exploration |
| A82595 | 2009 | La Mancha Resources Australia Pty Ltd | KINTORE, RED DAM AND BROADS DAM | 27% | KINTORE, RED DAM AND BROADS DAM PROJECTS ANNUAL REPORT FOR THE PERIOD 14th JUNE 2008 TO 13th JUNE 2009, C Numb |
| A82596 | 2009 | La Mancha Resources Australia Pty Ltd | KINTORE EAST | 75% | KINTORE EAST PROJECT ANNUAL REPORT FOR THE PERIOD 14th JUNE 2008 TO 13th JUNE 2009, C Number 38/2009 |
| A82774 | 2009 | Carbine Resources Ltd | Red Dam | 8.9% | Red Dam Project M16/344 Annual Technical Report |
| A84715 | 2009 | Paddington Gold Pty Ltd | Carbine | <1% | Carbine Mineral Exploration Report, Period 1 July 2008 to 30 June 2009, Tenements: M16/23, M16/48, M16/58, M16 |
| A81511 | 2009 | Cazaly Resources Ltd | CASTLE HILL | <1% | Combined Annual Report CASTLE HILL PROJECT For the Period 1 January 2008 to 31 December 2008 |
| A77188 | 2008 | Monarch Gold Mining Company Ltd | Davyhurst | <1% | DAVYHURST PROJECT Reporting Group C189/2007 Report Type: Annual Technical Report Report Period: 2 November 200 |
| A77532 | 2008 | Cazaly Resources Ltd | Kunanalling | <1% | Combined Annual Report KUNANALLING PROJECT C153/2006 For the Period 1 January 2007 to 31 December 2007 |
| A77599 | 2008 | Cazaly Resources Ltd | CASTLE HILL | <1% | Combined Annual Report CASTLE HILL PROJECT C99/1994 For the Period 1 January 2007 to 31 December 2007 |
| A78111 | 2008 | Carbine Resources Ltd | Red Dam | 8.9% | Red Dam Project M16/344 Annual Technical Report RD_2007A |
| A74443 | 2007 | Cazaly Resources Ltd | Kunanalling | <1% | Combined Annual Report, Kunanalling Project, For the Period 1 January 2006 to 31 December 2006. (C87/2004) |
| A75021 | 2007 | Cazaly Resources Ltd | Castle Hill | <1% | Combined Annual Report, Castle Hill Project, For the Period 1 January 2006 to 31 December 2006. (C99/1994 - M1 |
| A75605 | 2007 | Cazaly Resources Ltd | Castle Hill | <1% | Annual Environmental Report, Castle Hill Project For the period 1 January 2006 to 31 December 2006 Tenements: |
| A74388 | 2007 | Monarch Gold Mining Company Ltd | Carbine | <1% | Carbine Project M16/86, 143, 150, 164, 212, 244, P16/1439, 1512, 1570-73, 1816, 1915-16, 2178-82, 2006 Annual |
| A73237 | 2006 | Cazaly Resources Ltd | Kunanalling | <1% | Combined Annual Report for the Period 7 July 2005 to 6 July 2006, Kunanalling Project P16/2197-2198,2224-2231, |
| A73350 | 2006 | Cazaly Resources Ltd | Castle Hill | <1% | Combined Annual Report, Castle Hill Project P16/2253-2259, P16/2265-2266, For the Period 7 July 2005 to 6 July |
| A71993 | 2006 | Siberia Mining Corporation Ltd | Carbine | <1% | Carbine Project, Annual Technical Report 01/01/2005 to 31/12/2005, Combined Reporting No. C109/2005, Kalgoorli |
| A74655 | 2006 | Siberia Mining Corporation Ltd | Carbine | 7% | Carbine Project , Annual Report for the period 01/01/2006 to 31/12/2006, P16/1577-1578 (C78/2006) |
| A70065 | 2005 | Siberia Mining Corporation Ltd | Red Dam | <1% | Annual technical report for the period 11/01/04 - 10/01/05 Red Dam Project, M16/143, Kalgoorlie |
| A70171 | 2005 | Siberia Mining Corporation Ltd | Carbine | 5.3% | Annual technical report for the period 27/01/04 - 26/01/05 Carbine Project, P16/1916, Kalgoorlie |
| A70385 | 2005 | Siberia Mining Corporation Ltd | Carbine | <1% | Carbine Project, P16/1573, Annual technical report for the period 09/03/04 - 08/03/05 Kalgoorlie |
| A70386 | 2005 | Siberia Mining Corporation Ltd | Carbine | 4.2% | Carbine Project, P16/1572, Annual technical report 09/03/04 - 08/03/05 Kalgoorlie |
| A70402 | 2005 | Cazaly Resources Ltd | Kunanalling | <1% | Combined annual report for the period 01/01/04 - 31/12/04 Kunanalling Project, C87/2004, E16/302, M15/692..... |
| A70709 | 2005 | Siberia Mining Corporation Ltd | Red Dam | 7% | Carbine Project - Red Dam P16/1577-1578, Annual technical report 6/04/04 - 5/04/05 (C226/1996, Kalgoorlie). |
| A68396 | 2004 | Cazaly Resources Ltd | Kunanalling | <1% | Annual report for the period 01/01/2003-31/12/2003 Kunanalling Project (C36/1999), M16/0015, M16/0017, M16/003 |
| A68508 | 2004 | Placer Dome Asia Pacific Ltd | Carbine/Zuleika | <1% | Carbine/Zuleika Project Annual Report 09/03/2003 to 08/03/20 04 C303/1997 M16/27...M16/411, P16/1439...P24/335 |
| A68748 | 2004 | Allied Gold Ltd | Red Dam | 7% | Red Dam Project, P16/1577, P16/1578, Annual Report 06/04/2003-05/04. Allied Rept No 2004/1 |
| A69018 | 2004 | Placer Dome Asia Pacific Ltd | Carbine Zuleika | <1% | Carbine Zuleika Project, Surrender report 06/06/2000-05/06/2004, P16/2008-09 |
| A66164 | 2003 | Placer Dome Asia Pacific Ltd | Kunanalling | <1% | Annual Report 01/01/2002 - 31/12/2002 Kunanalling Project C36/1999: M16/15, 17, 33, 36, 47, 52, 99, 139-40, 17 |
| A66658 | 2003 | Placer Dome Asia Pacific Ltd | Carbine | <1% | Carbine/ Zuleika Project, Annual Report 09/03/2002 - 08/03/2003 C303/1997: M16/27, 44-5, 48, 58, 86, 106, 143, |
| A66665 | 2003 | Allied Mining And Processing Ltd | Red Dam | 7% | Red Dam Project, P16/1577 & P16/1578,Annual Report 6 April 2002 - 5 April 2003. C226/1996: Allied Mining Techn |
| A64425 | 2002 | Goldfields Exploration Pty Ltd | Kunanalling | <1% | Annual Report. Kunanalling Project. Tenements M16/139-40, M16/15, M16/17, M16/178, M16/217, M16/236, M16/306, |
| A65102 | 2002 | Auriongold Exploration Pty Ltd | Carbine Zuleika | <1% | Annual Report Reporting Period 09/03/2000 - 08/03/2002 Combined Reporting NO C303/1997. Tenement/s M16/23, 27, |
| A59890 | 2000 | Amx Resources Nl | Kunanalling | <1% | Annual Report on Kunanalling Gold Project Progress Report on Exploration carried out on Tenements GML16/1253,M |
| A60037 | 2000 | Mines & Resources Australia Pty Ltd | Croesus Joint Venture | <1% | Combined Annual Technical Report for the Period 08/12/1998 to 07/12/1999 PE00/10 Tenements P16/1385,1484-1487, |
| A60282 | 2000 | Mines & Resources Australia Pty Ltd | Kintore | <1% | Kintore Project, Annual Report for the Period 07/03/1999 to 06/03/2000, PE00/14, P16/1297,1298.Combined Report |
| A60310 | 2000 | Mines & Resources Australia Pty Ltd | Kintore East | 73% | Kintore East Joint Venture Project Annual Report for the Period 10/03/1999 to 09/03/2000 PE00/12 Tenements P16 |
| A60612 | 2000 | Homestake Gold Of Australia Ltd | Red Dam | 7% | Project 6564, Red Dam Project, P16/1577,1578, Annual Report, 6 April 1999 to 5 April 2000, Technical Report No |
| A61372 | 2000 | Centaur Mining & Exploration Ltd | Carbine Zuleika | <1% | Mining Leases M16/23,27,44,45,58,86,106,143,150,156,164,188, 212, Prospecting Licences P16/1353-1356,1373,1439 |
| A62574 | 2000 | Homestake Gold Of Australia Ltd | Red Dam | 7% | Project 6564 Red Dam Project P16/1577 & P16/1578 Annual Report 6 April 2000 - 5 April 2001. Technical Report N |
| A57321 | 1999 | Mines & Resources Australia Pty Ltd | Croesus | <1% | Croesus Joint Venture - PE99/1 08/12/97 - 07/12/98 P16/1385, 1484-1487, 1569, 1607-1614, M16/199, 200 |
| A58177 | 1999 | Mines & Resources Australia Pty Ltd | Kintore East | 73% | Kintore East joint venture project. Annual technical report on P16/1416-1420. 10/03/98-09/03/99. |
| A58280 | 1999 | Homestake Gold Of Australia Ltd | Red Dam | 7% | Red Dam Project - P16/1577, 1578 Annual Report 06/04/98 - 05/04/99 |
| A58486 | 1999 | Delta Gold Ltd | Kintore | <1% | Delta Gold NL - Kintore JV Annual Report 01/1998 - 01/1999 PL16/1297-1298 |
| A59105 | 1999 | Centaur Mining & Exploration Ltd | Carbine Zuleika | <1% | C303/1997 - Carbine - Zuleika, Joint Annual Report For the Period 9/03/1998 to 8/03/1999 (M16/23, M16/27, M16/ |
| A53901 | 1998 | Croesus Mining Nl | Croesus JV | <1% | Combined Annual Technical Report for the period 08/12/96- 07/12/97 Tenements P16/1385,1484-1487, 1569, 1607-16 |
| A54598 | 1998 | Mines & Resources Australia Pty Ltd | Kintore East Joint Venture | 73% | Kintore East Joint Venture Project Prospecting Licence: 16/1416-1420 10/03/97 - 09/03/98 |
| A54686 | 1998 | Mines & Resources Australia Pty Ltd | Red Dam | 46% | Red Dam Project, P16/1454 to P16/1459 and P16/1914 10/03/97 to 09/03/98 Mines and Resources Australia Pty Ltd |
| A54789 | 1998 | Plutonic Operations Ltd | Plutonic | 7% | Plutonic Project 564 - Red Dam Project, P16/1577-1578 Annual Report, 06/04/1997 to 05/04/1998 |
| A54951 | 1998 | Delta Gold Ltd | Kintore | <1% | Annual Technical Report Kintore Project Between 07/03/97 to 06/03/98 Tenements P16/1297 & P16/1298 MLA16/232 |
| A55230 | 1998 | Centaur Mining & Exploration Ltd | Carbine Zuleika | <1% | C303/1997 - Carbine/Zuleika Joint Annual Report 09/03/97 - 08/03/98 Mining Licence: M16/23, 27, 44-45, 48, 58, |
| A50240 | 1997 | Mines & Resources Australia Pty Ltd | Croesus | <1% | Croesus Joint Venture Project Combined Annual Technical report for Prospecting Licences P16/1385 P16/1484 to P |
| A51281 | 1997 | Plutonic Operations Ltd | Red Dam | 5.2% | Project 564 Red Dam Project P16/1578 and P16/1579 Final Surrender Report 06/04/93 to 05/04/97 WA Technical Rep |
| A51296 | 1997 | Delta Gold Ltd | Grants Patch West - Balgarri - Kintore E | <1% | ANNUAL TECHNICAL REPORT KINTORE PROJECT BETWEEN 7 March, 1996 to 6 March, 1997 |
| A50807 | 1997 | Mines & Resources Australia Pty Ltd | Kintore East | 73% | Kintore East Project Annual Technical Report on Prospecting Licences P16/1416 to P16/1420 for the period 10th |
| A50811 | 1997 | Mines & Resources Australia Pty Ltd | Red Dam | 46% | Red Dam Project Combined Annual report for Prospecting Licences P15/1454 to P16/1459 for the period 10 March 1 |
| A51241 | 1997 | Plutonic Operations Ltd | Red Dam | 6.5% | Project 564 Red Dam Project P16/1577 P16/1578 and P16/1579 Annual report 06/04/96 to 05/04/97 WA Technical Rep |
| A47860 | 1996 | Mines & Resources Australia Pty Ltd | Kintore East | 73% | Kintore East Project Annual Technical Report on Prospecting Licences P16/1416 to P16/1420 for the period 10th |
| A47898 | 1996 | Plutonic Operations Ltd | Red Dam | 6.5% | Project 564 Red Dam Project P16/1577 to P16/1579 Annual report 06/04/95 to 05/04/96 Plutonic Operations Limite |
| A48220 | 1996 | Delta Gold Ltd | Kintore | <1% | Annual Technical Report for the Kintore Project between 7th March, 1995 to 6th March, 1996 (P16/1297, P16/1298 |
| A48542 | 1996 | Newcrest Mining Ltd | Breakaway Dam | <1% | Newcrest Report No. WORA 104 OB No. 352 Ora Banda Gold Mine Breakaway Dam Project M16/58 M16/106 M16/143 M16/1 |
| A49964 | 1996 | Amx Resources Nl | Kunanalling | 21% | Annual report for Kunanalling Project Period 1 November 1995 to 31 October 1996 Mining Leases M16/139 M16/140 |
| A46904 | 1996 | Mines & Resources Australia Pty Ltd | Croesus Joint Venture | <1% | Croesus Joint Venture Project Combined Annual report for Prospecting Licences P16/1385 P16/1484 to P16/1487 P1 |
| A47900 | 1996 | Mines & Resources Australia Pty Ltd | Red Dam | 46% | Red Dam Project Combined Annual Technical Report for Prospecting Licences P16/1454 to P16/1459 for the period |
| A43430 | 1995 | Mines & Resources Australia Pty Ltd | Croesus | <1% | Croesus Joint Venture Project Combined Annual Technical Report for Prospecting Licences P16/1608 to P16/1614 P |
| A44289 | 1995 | Mines & Resources Australia Pty Ltd | Red Dam | 46% | Red Dam Project Combined Annual Techincal Report for Prospecting Licences 16/1454 -16/1459 For the period 10 M |
| A44290 | 1995 | Mines & Resources Australia Pty Ltd | Kintore East | 73% | Annual Technical Report on Prospecting Licences P16/1416 to P16/1420 for the period 10 March 1994 to 9 March 1 |
| A44307 | 1995 | Mines & Resources Australia Pty Ltd | Kintore | <1% | Annual Report on Prospecting Licences P16/1297 & P16/1298 for the period 7 March 1994 to 6 March 1995, Kintore |
| A44946 | 1995 | Newcrest Mining Ltd | Breakaway Dam | <1% | Newcrest Mining Report No. WORA 85 OB No. 334 Ora Banda Gold Mine Breakaway Dam Project Exploration Report on |
| A45223 | 1995 | Coolgardie Gold Nl | Kintore | <1% | Surrender Report for the period 17/07/94-16/07/95 Kintore Project P16/1371 P16/1372 |
| A41043 | 1994 | Resource Service Group Pty Ltd | Kintore | <1% | Annual report on Prospecting Licences P16/1297 P16/1298 Kintore Project for the period 07/03/93 to 06/03/94 |
| A41044 | 1994 | Resource Service Group Pty Ltd | Kintore East | 73% | Combined Annual Technical Report for the 12 months to 9/03/1994 Kintore East Project P16/1416 to 1420 |
| A41999 | 1994 | Newcrest Mining Ltd | Breakaway Dam | <1% | Breakaway Dam Project Exploration Report on Leases M6/58, M16/106,M16/143,M16/150,M16/164, P16/1439, P6/1570-1 |
| A42236 | 1994 | Plutonic Operations Ltd | Red Dam | 5% | Annual report for the period 06/04/93 to 05/04/94 Project 564 Red Dam Project P16/1577 to P16/1580 Plutonic Op |
| A40277 | 1994 | Afmeco Pty Ltd | Croesus - Macaroni - Crest Shear | <1% | Annual Report for the period 08/12/92-07/12/93 Croesus JV(Macaroni & Crest Shear Area) Project P16/1152-1154,1 |
| A40685 | 1994 | Afmeco Pty Ltd | Red Dam | 46% | Annual report for the period 10/03/93-09/03/94 Red Dam Project P16/1454-1459 |
| A41976 | 1994 | Coolgardie Gold Nl | Kintore | <1% | Annual report for the period 17/07/93-16/07/94, Kintore Project, P16/1371 P16/1372 |
| A38140 | 1993 | Afmeco Pty Ltd | Kintore East | 73% | Annual report for the period 10/03/92-09/03/93 Kintore East JV Project P16/1416-1420 |
| A39125 | 1993 | Coolgardie Gold Nl | Kintore | <1% | Annual report for the period 17/07/92-16/07/93 Kintore Project P16/1371 P16/1372 |
| A39747 | 1993 | Afmeco Pty Ltd | Croesus | <1% | Surrender report for the period 20/01/93-16/08/93 Croesus JV Project M16/190 M16/192 |
| A38160 | 1993 | Afmeco Pty Ltd | Red Dam | 46% | Annual report for the period 10/03/92-09/03/93 Red Dam Project P16/1454-1459 |
| A39998 | 1993 | Newcrest Mining Ltd | Breakaway Dam | <1% | Breakaway Dam Project Exploration Report on Leases M16/58, M16/106, M16/143, M16/150, M16/164, P16/1439, P16/1 |
| A36414 | 1992 | Afmeco Pty Ltd | Red Dam | 46% | Surrender Report for the period to 03/92 Red Dam Project M16/121,162 |
| A35699 | 1992 | Afmeco Pty Ltd | Kintore East | 74% | Final Report on tenements for the period 01/08/91 - 10/03/92 Kintore East Joint Venture Project M16/172 and M1 |
| A35818 | 1992 | Afmeco Pty Ltd | Kintore | <1% | Annual Report on Prospecting Licences P16/1297 and 1298 Kintore Project for the Period 07/03/91 - 06/03/92 |
| A36848 | 1992 | Coolgardie Gold Nl | Kintore | <1% | Annual Report for the period 17/07/91-16/07/92 Kintore Project P16/1371 P16/1372 |
| A37470 | 1992 | Newcrest Mining Ltd | Breakaway Dam | <1% | Annual report for the period 05/91 to 05/92 Breakaway Dam Project M16/58, M16/106, M16/143, M16/150, M16/164, |
| A32470 | 1991 | Mt Martin Gold Mines Nl | Red Dam/Seven Dwarfs | 5% | Annual report for the period 17/03/90 to 17/03/91 For Mining Lease M16/132 Seven Dwarfs East Coolgardie Minera |
| A32917 | 1991 | Poseidon Ltd | Little Crest Dam | <1% | Little Crest Dam Project Annual Report 1990 P16/657, P16/658, P16/1042, P16/1043 and M16/143 Poseidon Explorat |
| A31267 | 1990 | Poseidon Ltd | Little Crest Dam | <1% | Annual report 1989 Little Crest Dam project P16/538 to P16/539, P16/488 to P16/490, P16/492, P16/493, P16/1402 |
| A29841 | 1989 | Pioneer Minerals Aust Ltd | Red Dam | 2.9% | Project 564: Red Dam. Report on Rotary Airblast Drilling July 1989 Prospecting licence P16/463 Pioneer Mineral |
| A27605 | 1989 | Pioneer Minerals Aust Ltd | Red Dam | 1.4% | Project 564: Red Dam Report on RAB drilling Sept 1988 P16/454 to P16/463 and P16/535 to P16/537 Pioneer Minera |
| A28611 | 1989 | Pioneer Minerals Aust Ltd | Red Dam | 2.9% | Project 564: Red Dam; Report on Rotary Airblast Drilling March 1989 P16/463 WA Technical Report No 231 (R Rep |
| A30974 | 1989 | Pioneer Minerals Aust Ltd | Red Dam | 2.9% | Project 564: Red Dam, Report on Rotary Airblast Drilling, March 1989. Prospecting licence 16/463 (Kalgoorlie, |
| A31366 | 1989 | Barrack Exploration Pty Ltd | Kintore | 46% | R Report for the period 11/89 Kintore Project P16/399-402,618-619 M16/121 |
| A23949 | 1988 | Coolgardie Mining Associates Nl | Dunnsville - Jaurdi Hill | 1.4% | Jaurdi - Dunnsville Group, Final report for year ended 31 April 1988, P/16/308, P16/438-439, P16/477-480, P16/ |
| A18302 | 1986 | Noranda Australia Ltd | West Black Flag | 1.4% | Project 564 : Red Dam Preliminary Reconnaissance Mapping field work December 13 to 15, 19858 W.A. Technical Re |
| A18303 | 1986 | Noranda Australia Ltd | West Black Flag | 1.4% | Project 564: Red Dam Report on Soil Geochemistry April to June 1986 P16/454 to P16/463 P16/535 to P16/537 Nora |
| A6607 | 1976 | Western Mining Corporation Ltd | Ora Banda- Kunanalling- Broad Arrow | 3.6% | Ora Banda- Kunanalling- Broad Arrow Project, Annual Report for the period 01/05/1973 to 29/06/1976, TR70/5012 |
| A1814 | 1971 | Western Mining Corporation Ltd | Kunanalling | 4.8% | Kunanalling Project, Annual Report for theyear ending 30th June 1971, MC16/118-119, 124-185, & 190-205. |
| A105 | 1970 | Western Mining Corporation Ltd | Ora Banda- Kunanalling | 1.4% | Ora Banda- Kunanalling Project, Non-statutory Report: Annual Tenements & Temporary Reserve Reports Data File, |
| A106 | 1970 | Western Mining Corporation Ltd | Ora Banda - Kunanalling | 1.4% | Ora Banda - Kunanalling Project, Non-statutory Report: Kalgoorlie Regional & Geological Plans (8), circa July |
| A107 | 1970 | Western Mining Corporation Ltd | Ora Banda - Kunanalling | 1.4% | Ora Banda - Kunanalling Project, Non-statutory Report: Annual Tenements & Temporary Reserve Report ,Data File |
| A112 | 1970 | Western Mining Corporation Ltd | Ora Banda - Kunanalling | 1.4% | Ora Banda - Kunanalling Project, Non-statutory Report:Annual Report, Folder 11, Sample Data Sheets for Kunanal |
| A108 | 1970 | Western Mining Corporation Ltd | Ora Banda/Kunanalling | 1.4% | Annual Tenements and Temporary Reserve Report Data File, Ora Banda - Kunanalling Area. |
| A109 | 1970 | Western Mining Corporation Ltd | Ora Banda - Kunanalling | 1.4% | Ora Banda - Kunanalling Project, Non-statutory Report: Annual Tenements & Temporary Reserve Report,Folder 8,In |
| A110 | 1970 | Western Mining Corporation Ltd | Ora Banda -Kunanalling | 1.4% | Ora Banda -Kunanalling Project, Non-statutory Report:Annual Tenement & Temporary Reserve Report, Folder 9, Vac |
| A111 | 1970 | Western Mining Corporation Ltd | Ora Banda -Kunanalling | 1.4% | Ora Banda -Kunanalling Project, Non-statutory Report:Annual Tenements & Temporary Reserve Report Folder 10,Sam |
| A22686 | 1753 | Noranda Australia Ltd | West Black Flag | 1.4% | Project 564 Red Dam Report on RAB Drilling June - July 1987 and Nov 1987. P16/454 to P16/463 and P16/535 to P1 |
| A38751 | 1753 | Inco Australia Ltd | Eastern Goldfields regional mapping | <1% | Eastern Goldfields regional mapping |
| A50373 | 1753 | Centaur Mining & Exploration Ltd | Ora Banda South | <1% | Prospecting Licences P16/1353 to P16/1356 P16/1374 P16/1439 P16/1512 P16/1570 to P16/1573 and Mining Leases M1 |
| A57775 | 1753 | Amx Resources Nl | Kunanalling | <1% | Report On Kunanalling Gold Project, Progress Report on GML 16/1253,M16/140,160,178,236,306, Period 1/11/97 to |
What does the exploration record say about this ground?
NextMaps reads the WAMEX reports over M 16/545 into a referenced prospectivity assessment: the geology, the historical programs, the drill intercepts and geochemistry, and the untested gaps, with every claim cited back to its source report. New accounts include a free report (how the reports work). Prefer the raw due diligence? A Tenure Pack bundles the full register record, tenure history and spatial datasets for this ground.
Get the free report Full register record on the mapDo you hold M 16/545? Listing is free. A facilitation fee applies only if the ground ends up with a buyer we introduce.
List this tenementTenure data sourced from the DMPE public registers and SLIP WA (© Government of Western Australia, CC BY 4.0), as at 2026-10-08. Compiled by NextMaps. Verify against primary sources before reliance.