M 39/422 is a live mining lease in the Shire of Laverton, Western Australia, held by Murrin Murrin Operations Pty Ltd. Granted on 26 July 1996 for 21 years (renewed), it expires on 25 July 2038. The ground is covered by 59 historical WAMEX reports.
Register summary
- Holder
- Murrin Murrin Operations Pty Ltd
- Local government
- Shire of Laverton
- Application received
- 19 Jan 1996
- Commenced
- 26 July 1996
- Expiry
- 25 July 2038
- Term
- 21 Years (Renewed)
The full record on M 39/422
The register summary says who holds it today. The rest of the record says how they came to, what is attached to it, and whether it is being worked.
- Current holders and their shares, and all 5 changes of holder
- The full record: 31 years of expenditure, 69 conditions and 6 endorsements
- Native title context, combined reporting and rent status
- At-risk and opportunity signals, and expenditure compliance over five years
- Every register dealing (53 on record), with mortgages, caveats and transfers flagged
- Expiry band, and how long the holder has had it
Exploration history on this ground
| Report | Year | Operator | Project | On this ground | Title |
|---|---|---|---|---|---|
| A122796 | 2020 | Gme Resources Limited | Hepi | <1% | Annual Report Hepi Project C173/2005 for the period 1 January 2019 to 31 December 2019 |
| A122834 | 2020 | Murrin Murrin Operations Pty Ltd | Murrin Murrin | 3.2% | Murrin Murrin Nickel Laterite Project - C308/1997 for the period ending 31/12/2019 |
| A119213 | 2019 | Murrin Murrin Operations Pty Ltd | Murrin Murrin | 3.2% | Combined Annual Report for the Murrin Murrin Nickel Laterite Project C308/1997 for the period 1 January 2018 t |
| A119344 | 2019 | Gme Resources Ltd | Hepi | <1% | Hepi Project C173/2005 Annual Report for the period 1 January 2018 to 31 December 2018, M39/00427, M39/00460, |
| A116028 | 2018 | Murrin Murrin Operations Pty Ltd | Murrin Murrin | 3.1% | Combined Annual Report for the Murrin Murrin Project C308/1997 for the period 1 January 2017 to 31 December 20 |
54 more reports
| A116021 | 2018 | Gme Resources Ltd | Hepi | <1% | Annual Report Hepi Project C173/2005 for the period 1 January 2017 to 31 December 2017, M39/00427, M39/00460, |
| A112058 | 2017 | Murrin Murrin Operations Pty Ltd | Murrin Murrin | 3.1% | Combined Annual Report for the Murrin Murrin Project - C308/1997 For the Period 1 January 2016 to 31 December |
| A112161 | 2017 | Gme Resources Ltd | Hepi | <1% | Annual Report Hepi Project C173/2005 for the period 01/01/2016 to 31/12/2016, M39/00427, M39/00460, M39/00717, |
| A108073 | 2016 | Murrin Murrin Operations Pty Ltd | Murrin Murrin | 3.1% | Combined Annual Report, Murrin Murrin Project - C308/1997 for the period 1 January 2015 to 31 December 2015 |
| A108159 | 2016 | Gme Resources Ltd | Hepi | <1% | Hepi Project Annual Report for C173/2005 for the period 1st January 2015 to 31st December 2015, M39/427, M39/4 |
| A104741 | 2015 | Gme Resources Ltd | Hepi | <1% | Hepi Project (C173/2005) Annual Report for the period 1st January 2014 to 31st December 2014, M39/427, M39/460 |
| A104763 | 2015 | Murrin Murrin Operations Pty Ltd | Murrin Murrin | 3.1% | Murrin Murrin Project C308/1997 Combined Annual Report for the period 1 January 2014 to 31 December 2014, M37/ |
| A101236 | 2014 | Hrm Resources Australia Ltd | Paynes Find | <1% | Annual Exploration Report M59 /714 Paynes Find Project for the period ended 31/12/2013 |
| A101336 | 2014 | Minara Resources Ltd | Murrin Murrin | 3.1% | C308/1997 Combined Annual Report, Murrin Murrin Project - C308/1997 for the period 1 January 2013 to 31 Decemb |
| A97047 | 2013 | Murrin Murrin Operations Pty Ltd | Murrin Murrin | 2.8% | Murrin Murrin Project, Annual Report for the period 1st January 2012 to 31st December 2012, M37/630, 933, 1077 |
| A97109 | 2012 | Gme Resources Ltd | Hepi | <1% | C173/2005 Hepi Project Annual Report 2012 for the period 1st January 2012 to 31st December 2012, M39/427, 460, |
| A93017 | 2012 | Gme Resources Ltd | Hepi | <1% | Hepi Project Annual Report 2011, C173/2005 Tenement Numbers: M39/427, M39/460, M39/717, M39/718, M39/758, M39/ |
| A93124 | 2012 | Murrin Murrin Operations Pty Ltd | Murrin Murrin | 2.8% | Combined Annual Report for the Period 1 January 2011 to 31 January 2011, Murrin Murrin Project C308/1997 |
| A89225 | 2011 | Gme Resources Ltd | Hepi | <1% | Hepi Project Annual Report 2010, Report Period: 1st January 2010 to 31st December 2010, C173/2005 M39/427, M39 |
| A89873 | 2011 | Murrin Murrin Operations Pty Ltd | Murrin Murrin | 2.8% | Combined Annual Technical Report for C308/1997 – Murrin Murrin Project, Report Period: 1 January 2010 to 31 De |
| A85679 | 2010 | Gme Resources Ltd | Hepi | <1% | Hepi Project, C173/2005, Annual Report 2009, M39/427, M39/460, M39/717, M39/718, M39/758, M39/819, M39/825, P |
| A86420 | 2009 | Minara Resources Ltd | Murrin Murrin | 2.8% | Murrin Murrin Project Thirteenth Combined Annual Technical Report C308/1997, for the period 1 January 2009 to |
| A80596 | 2008 | Gme Resources Ltd | HEPI | <1% | HEPI PROJECT COMBINED REPORTING GROUP C173/2005 2009 ANNUAL REPORT |
| A77477 | 2008 | Minara Resources Ltd | Murrin Murrin | 2.9% | TR1413 MURRIN MURRIN PROJECT ELEVENTH COMBINED ANNUAL TECHNICAL REPORT C308/1997 FOR THE PERIOD 1st January 20 |
| A78515 | 2008 | Niwest Ltd | Murrin Murrin North | <1% | Annual Technical Report for the Period 30 March 2007 to 29 March 2008, Murrin Murrin North, M39/758 |
| A75235 | 2007 | Niwest Ltd | Murrin Murrin North | <1% | Murrin Murrin North Project M39/758 Annual Technical and Progress Report for the period 30th March 2006 to 29t |
| A74348 | 2007 | Minara Resources Ltd | Murrin Murrin | 2.9% | Murrin Murrin Project, Tenth Combined Annual Report C308/1997, for the Period 1st January 2006 to 31 December |
| A72075 | 2006 | Minara Resources Ltd | Murrin Murrin | 2.9% | Murrin Murrin Project, Eighth Combined Annual Technical Report C308/1997, For the Period 1 January 2005 to 31 |
| A72599 | 2006 | Niwest Ltd | Murrin Murrin North | <1% | Murrin Murrin North Project, M39/758, Annual Report for the Period 30 March 2005 to 29 March 2006, [ [C100/19 |
| A70452 | 2005 | Minara Resources Ltd | Murrin Murrin | 2.9% | Combined annual report for the period 01/01/04 - 31/12/04 Murrin Murrin Project, C308/1997, M37/630, 933, M39/ |
| A67981 | 2004 | Minara Gold Nl | Murrin Murrin | 2.9% | Combined Annual Report for the period 01/01/2003- 31/12/2003 Murrin Murrin Project M37/630, M37/933, M37/299-3 |
| A69453 | 2004 | Gme Resources Ltd | Murrin Murrin North | <1% | Annual technical report for the period 19/01/03 - 18/01/04 Murrin Murrin North Project, C100/1997, P39/3515, P |
| A66097 | 2003 | Anaconda Operations Pty Ltd | Murrin Murrin | 2.9% | Sixth Combined Annual Report for the period 1st January 2002 to 31st December 2002 Murrin Murrin Project C308/ |
| A66184 | 2003 | Niwest Ltd | Murrin Murrin North | <1% | Annual Technical and Progress Report for the period 19th January 2002 to 18th January 2003 Murrin Murrin North |
| A64691 | 2002 | Anaconda Operations Pty Ltd | Murrin Murrin | 2.9% | Murrin Murrin Project Technical Report 1260 Fifth Combined Annual Technical Report Number C308/1997 (Concernin |
| A64094 | 2002 | Anaconda Operations Pty Ltd | Murrin Murrin | 2.9% | Murrin Murrin Project Fifth Combined Annual Technical Report number C308/1997 for the period 1st January 2001 |
| A64616 | 2002 | Niwest Ltd | Murrin Murrin North | <1% | Murrin Murrin North Project P39/3515 to 3522 Annual Technical And Progress Report For The Period 19th January |
| A61877 | 2001 | Anaconda Operations Pty Ltd | Murrin Murrin | 2.9% | Murrin Murrin Project Fourth Combined Annual Technical Report number C308/1997 (Concerning tenements: E39/439, |
| A62351 | 2001 | Niwest Ltd | Murrin Murrin North | <1% | Murrin Murrin North Project P39/3515 to 3522 Annual Technical And Progress Report For The Period 19th January |
| A53861 | 1998 | Anaconda Nickel Ltd | Murrin Murrin | 3.3% | Annual technical report for the period 01/01/97-31/12/97. Murrin Murrin Project. |
| A54875 | 1998 | Gme Resources Nl | Murrin Murrin | <1% | Murrin murrin North Project W.A. 19/01/96 - 18/01/97 P39/3515-3522 |
| A57229 | 1998 | Anaconda Nickel Ltd | Murrin Murrin | 3.3% | Murrin Murrin Project 01/01/98 - 31/12/98 E39/439, M39/71, 299-301 |
| A51352 | 1997 | Anaconda Nickel Nl | Central Bore | 8.2% | Murrin Murrin North Project Annual report Ref:C185/1994 Murrin Murrin North Tenements M39/299 M39/300 M39/301 |
| A50684 | 1996 | Anaconda Nickel Nl | Murrin Murrin | <1% | Murrin Murrin Nickel Cobalt Project Sterilisation Exploration for a Treatments Plant site, Accommodation camps |
| A43575 | 1995 | Anaconda Nickel Nl | Central Bore | 13% | Ancaconda Nickel NL Central Bore Project Annual Report Year ended 31 December 1994 |
| A42089 | 1994 | Terlinga Mining Pty Ltd | Cement Creek | <1% | Annual Report for the period 14/02/93-13/02/94,Cement Creek Project P39/2973 |
| A7966 | 1978 | Australian Selection Pty Ltd | Murrin - Aermotor Well -Central Bore | 4.5% | Murrin -Aermotor Well -Central Bore, Non-statutory Report: Progress Report for the period ending 31st March 19 |
| A5747 | 1975 | Australian Selection Pty Ltd | Murrin | <1% | Murrin Project, Progress report [non-statutory] March 1975, Volumes 1-3, MC39/34 ... 39/4130, TR70/2903, 3564, |
| A6945 | 1973 | Kennecott Exp Aust Pty Ltd | Erlistoun | <1% | Aeromag- Raw Data |
| A3746 | 1972 | Northern Selcast Pty Ltd | Murrin Murrin - Randwick Hill | <1% | Murrin Murrin - Randwick Hill Project, Annual Report for the period ending 31/12/1972, TR70/2903,3564, & 3819H |
| A2715 | 1971 | Australian Selection Pty Ltd | Murrin Murrin - Randwick Hill | <1% | Murrin Murrin - Randwick Hill Project, Annual Report for the period ending 31/12/1971, TR70/2903, 3564 & 3819H |
| A1308 | 1970 | Australian Selection Pty Ltd | Murrin Murrin | 3.2% | Murrin Murrin Project, Annual Report(s) for the years1968, 1969 & 1970,TR70/2903, 3564, 3819H; MC37/34-61; MC3 |
| A1306 | 1967 | Australian Selection Pty Ltd | Murrin Murrin | <1% | Murrin Murrin Project, Annual Report(s) for the years 1965, 1966 & 1967, TR70/2903 & 3564H., |
| A1305 | 1964 | Australian Selection Pty Ltd | Murrin Murrin | <1% | Murrin Murrin Project, Non-statutory Report:Aeromagnetic Surveys, July 1964, TR70/2903 & 3564. |
| A80963 | 1753 | Minara Resources Ltd | MURRIN MURRIN | 3.2% | MURRIN MURRIN PROJECT TWELFTH COMBINED ANNUAL TECHNICAL REPORT C308/1997, FOR THE PERIOD 1 January 2008 to 31 |
| A44933 | 1753 | Terlinga Mining Pty Ltd | Cement Creek | <1% | Cement Creek Project, Annual Report, P39/2973 for the period 14 July 1994-13 July 1995. |
| A48647 | 1753 | Anaconda Nickel Nl | Murrin Murrin | 11% | Anaconda Nickel NL Dome Annual Report Tenements:P39/2825,P39/2828,P39/2829,P39/2830,P39/2990, P39/2991,P39/299 |
| A50446 | 1753 | Mr Hocking Jc | Murrin Murrin | <1% | Annual report for the period ending 18/1/97 Murrin Murrin Project P39/3515-P39/3521 |
| A38751 | 1753 | Inco Australia Ltd | Eastern Goldfields regional mapping | <1% | Eastern Goldfields regional mapping |
What does the exploration record say about this ground?
NextMaps reads the WAMEX reports over M 39/422 into a referenced prospectivity assessment: the geology, the historical programs, the drill intercepts and geochemistry, and the untested gaps, with every claim cited back to its source report. New accounts include a free report (how the reports work). Prefer the raw due diligence? A Tenure Pack bundles the full register record, tenure history and spatial datasets for this ground.
Get the free report Full register record on the mapDo you hold M 39/422? Listing is free. A facilitation fee applies only if the ground ends up with a buyer we introduce.
List this tenementTenure data sourced from the DMPE public registers and SLIP WA (© Government of Western Australia, CC BY 4.0), as at 2026-10-08. Compiled by NextMaps. Verify against primary sources before reliance.