E 25/535
Register summary
- Holder
- Crown Gold (Wa) Pty Ltd
- Local government
- City of Kalgoorlie-Boulder
- Application received
- 21 Oct 2015
- Commenced
- 4 May 2016
- Expiry
- 3 May 2028
- Term
- 5 Years (Extended)
Exploration history on this ground
| Report | Year | Operator | Project | On this ground | Title |
|---|---|---|---|---|---|
| A137007 | 2023 | Black Cat (Kal East) Pty Ltd | Slate Dam | <1% | Partial Surrender Report for the Slate Dam Project E25/558 For the Period 11 August 2017 to 10 August 2023 |
| A122610 | 2020 | Silver Lake (Integra) Pty Limited | Mount Monger Peters Dam JV | <1% | Final Surrender Report for Mount Monger Peters Dam JV (C135/2007) E26/153 and E26/154 for the period 6 May 20 |
| A124158 | 2020 | Aruma Resources Limited | SLATE DAM | <1% | Annual Report for C112/2017 Slate Dam Project for the period ending 02/04/2020 |
| A122553 | 2020 | Wanaka Exploration Pty Ltd | Wanaka | <1% | Final Surrender Wanaka E25/00570 for the period 5 July 2018 to 3 December 2019 |
| A125576 | 2020 | Silver Lake Resources Limited | Mount Monger | <1% | Surrender Report for E26/146 (Mt Monger) for the period 23 September 2010 to 22 September 2020 |
116 more reports
| A123215 | 2020 | Mining Investments Australia Pty Ltd | Majestic | <1% | Annual Mineral Exploration Report for Combined Reporting Group No. C49/2019, Majestic Project, for the Period |
| A124734 | 2020 | Resource Holdings Pty Ltd | CURTIN | 94% | Annual Report for C69/2016 "CURTIN" - E25/535 for the period 4 May 2019 to 3 May 2020 |
| A121773 | 2019 | Silver Lake Resources Limited | Mount Monger | <1% | Combined Annual Report on Mt Monger Project - C72/2004 for the period 1 July 2018 to 30 June 2019 |
| A118724 | 2019 | Silver Lake (Integra) Pty Limited | Mount Monger Peters Dam | <1% | Combined Annual Report on Mt Monger Peters Dam Project - C135/2007 for the period 1 November 2017 to 31 Octobe |
| A120183 | 2019 | Mining Investments Australia Pty Ltd | Majestic | <1% | Annual Mineral Exploration Report for Tenement E25/484 as part of the Majestic Project for the Period 9th Apri |
| A120476 | 2019 | Aruma Resources Limited | Slate Dam | <1% | Annual Report for C112/2017 "Slate Dam" for the period 3 April 2018 to 2 April 2019, E25/00553, E25/00556, E25 |
| A120651 | 2019 | Resource Holdings Pty Ltd | CURTIN | 94% | ANNUAL REPORT for C69/2016 "CURTIN" - E25/535 For the period 4 May 2018 to 3 May 2019 |
| A121481 | 2019 | Silver Lake (Integra) Pty Limited | Peters Dam JV | <1% | Final Surrender Report for P26/3819, P26/3820 and P26/3821, Peters Dam JV for the period 15 June 2011 to 14 Ju |
| A116882 | 2018 | Anglogold Ashanti Australia Limited | Glandore South | <1% | Glandore South Project (P26/4238) Annual Report to the Department of Mines, Industry Regulation and Safety for |
| A117305 | 2018 | Resource Holdings Pty Ltd | Curtin | 94% | Annual Report for C69/2016 Curtin Project E25/535 for the period 04/05/2017 - 03/05/2018 |
| A117326 | 2018 | Aruma Resources Limited | Slate Dam | <1% | Annual Report for C112/2017 Slate Dam Project for the period 3 April 2017 to 2 April 2018, E25/00553, E25/0055 |
| A118055 | 2018 | Silver Lake Resources Limited | Mount Monger | <1% | Combined Annual Report on Mount Monger Project C72/2004 for 1 July 2017 to 30 June 2018 |
| A110667 | 2017 | Rubicon Resources Limited; Silver Lake (Integra) Pty Limited | Peters Dam | <1% | Combined Annual Report on Mount Monger Peters Dam Project – C135/2007 for period 1 November 2015 to 31 October |
| A111921 | 2017 | Pioneer Resources Limited | Dingo West | <1% | Annual report for the Dingo West Project, E25/523, for the period 5 November 2015 to 4 November 2016 |
| A114450 | 2017 | Pioneer Resources Limited | Juglah Dome | 24% | Annual Report for the Juglah Dome Project, E25/381, for the period 21 May 2016 to 20 May 2017 |
| A114613 | 2017 | Resource Holdings Pty Ltd | Majestic East | 94% | Majestic East E25/00535 Annual Report for the year ended 3rd May 2017 |
| A114883 | 2017 | Silver Lake Resources Limited | Mount Monger | <1% | Combined Annual Report on Mt Monger Project C72/2004 for the period 1 July 2016 to 30 June 2017 |
| A115389 | 2017 | Silver Lake Resources Limited | Mount Monger Peters Dam | <1% | Combined Annual Report on Mt Monger Peters Dam Project - C135/2007 for the period 1 November 2016 to 31 Octobe |
| A107879 | 2016 | Silver Lake (Integra) Pty Limited | Peters Dam | <1% | Combined Annual Report on Mt Monger Peters Dam JV Project – C135/2007 for period 1 November 2014 to 31 October |
| A109400 | 2016 | Pioneer Resources Limited | Juglah Dome | 24% | Annual Report for the Juglah Dome Project E25/381 for the period 21 May 2015 to 20 May 2016 |
| A109816 | 2016 | Silver Lake Resources Limited | Mount Monger | <1% | Mount Monger Project Combined Annual Report on Mt Monger Project C72/2004 for 1 July 2015 to 30 June 2016 |
| A110590 | 2016 | Silver Lake Resources Limited | Mount Monger | <1% | Surrender Report for Mt Monger Tenements P 26/3426, P 26/3427, P 26/3428, P 26/3429, P 26/3430, P 26/3432, P 2 |
| A104632 | 2015 | Silver Lake Resources Limited | Mount Monger - Peters Dam | <1% | Combined Annual Report on Mt Monger Peters Dam Project – C135/2007 for period 1 November 2013 to 31 October 20 |
| A106108 | 2015 | Pioneer Resources Limited | Juglah Dome | 19% | Annual report for the Juglah Dome Project, C27/2012 (E25/381 & E25/496), East Coolgardie Mineral Field, for th |
| A106365 | 2015 | Pioneer Resources Limited | Juglah Dome | 24% | Partial Surrender Report for the Juglah Dome Project, E25/381, East Coolgardie Mineral Field, for the period 2 |
| A107152 | 2015 | Silver Lake Resources Limited | Mt Monger | <1% | ANNUAL REPORT For the Period 1 July 2014 to 30 June 2015 MT MONGER Combined Annual Report on Mt Monger Project |
| A107196 | 2015 | Macphersons Resources Ltd | Trojan West | <1% | Trojan West Exploration Licence 25/504 Final Surrender Report for the Period 10 July 2014 to 07 July 2015 |
| A105860 | 2015 | Silver Lake (Integra) Pty Limited | Mount Monger | 23% | Surrender Report on E25/208 for period 1 August 2006 to 7 April 2015 |
| A103698 | 2014 | Silverlake Resources Ltd | Mount Monger | <1% | Combined Annual Report on Mt Monger Project – C72/2004 for period 1 July 2013 to 30 June 2014 |
| A102911 | 2014 | Silver Lake Resources Limited | Mount Monger South | <1% | Mount Monger South Project, Annual Report for the period 01/05/2013 to 30/04/2014, E25/332; M25/117; M26/148.. |
| A102932 | 2014 | Silver Lake Resources Limited | Greater Monger | 9.7% | Greater Monger Project, Annual Report for the period 01/05/2013 to 30/04/2014, E25/208; M25/350; P25/1897-1905 |
| A103117 | 2014 | Pioneer Resources Ltd | Juglah Dome | 24% | Annual report for the Juglah Dome Project, C27/2012 (E25/381), East Coolgardie Mineral Field, for the period 2 |
| A96422 | 2013 | Integra Mining Ltd | Mount Monger Peters Dam | <1% | Combined Annual Report on Mt Monger Peters Dam Project – C135/2007 for period 1 November 2011 to 31 October 20 |
| A97157 | 2013 | Pioneer Resources Ltd | Juglah Dome | <1% | Final Surrender Report for the Juglah Dome Project, E25/452, East Coolgardie Mineral Field, for the period 3 M |
| A98315 | 2013 | Silver Lake Resources Ltd | Mount Monger South | <1% | Mount Monger South Project, Annual Report for the period 1st May 2012 to 30th April 2013, E25/332; M25/117; M2 |
| A98746 | 2013 | Silver Lake Resources Ltd | Greater Monger | 9.7% | Combined Annual Report on Greater Monger Project – C108/2001 for period 1 May 2012 to 30 April 2013, E25/208.. |
| A98944 | 2013 | Pioneer Resources Ltd | Juglah Dome | 7.6% | Annual report for the Juglah Dome Project, C27/2012 (E25/381 & E25/452), East Coolgardie Mineral Field, for th |
| A99363 | 2013 | Monteray Mining Group Ltd | Triple 3 | 33% | Triple 3 Project, Annual Report for the period 21/06/2012 to 20/06/2013, E25/333. |
| A99585 | 2013 | Ironstone Resources Ltd | Juglah Rocks | <1% | Combined Annual Report on Exploration at Juglah Rocks Tenements, E25/421, E25/435 and E25/453. 18th October, 2 |
| A99783 | 2013 | Silver Lake Resources Pty Ltd | Mount Monger | <1% | Annual Report for Mount Monger Project C72/2004 E26/146.....P26/3874 for the period 1 July 2012 to 30 June 201 |
| A98822 | 2013 | Integra Mining Ltd | Randalls | <1% | Integra Mining Magnetotelluric Survey 30/11/2012 |
| A94670 | 2012 | Monteray Mining Group Ltd | Triple 3 | 33% | Partial Surrender Report for the period 21st June 2007 to 20th June 2012 Triple 3 Project, E25/333, Block P254 |
| A94705 | 2012 | Pioneer Resources Ltd | Juglah Dome | 7.6% | Combined Annual report for the Juglah Dome Project, C27/2012 (E25/381 & E25/452), East Coolgardie Mineral Fiel |
| A93706 | 2012 | Classic Minerals Ltd | Juglah (3) | <1% | Juglah (3) Project E25/453 Annual Report for the period 31 January 2011 - 30 January 2012 |
| A94987 | 2012 | Monteray Mining Group Ltd | Triple 3 | 33% | Annual Report for the period 21st June 2011 to 20th June 2012 E25/333, Triple 3 Project |
| A95421 | 2012 | Classic Minerals Ltd | Juglah | <1% | Juglah 1.2.3. Project, Annual Report for the period 18/10/2011 to 17/10/2012, E25/421, 435 & 453. {C291/2011] |
| A95757 | 2012 | Silver Lake Resources Pty Ltd | Mount Monger | <1% | Mount Monger Project, Annual Report for the period 1st July 2011 to 30th June 2012, Combined Reporting Group: |
| A90579 | 2011 | Integra Mining Ltd | Greater Monger | 9.7% | Combined Annual Report on Greater Monger Project – C108/2001 for period 1 May 2010 to 30 April 2011 |
| A90917 | 2011 | Pioneer Resources Ltd | Juglah Dome | 24% | Juglah Dome E25/381 Annual Technical Report For the Period 21st May 2010 to 20th May 2011 |
| A91421 | 2011 | Monteray Mining Group Ltd | Tripple 3 | 33% | Tripple 3 Project E25/333 Annual Report for the period 20 June 2010 to 19 June 2011 |
| A91552 | 2011 | Silver Lake Resources Pty Ltd | Mount Monger | <1% | Mount Monger Project, Annual Report for the period 01/07/2010 to 30/06/2011, C72/2004. |
| A92264 | 2011 | Integra Mining Ltd | Mount Monger | <1% | Mount Monger Project, Annual Report for period 1st November 2010 to 31st October 2011, E15/869; E25/307, 313, |
| A94097 | 2011 | Integra Mining Ltd | Greater Monger | 9.7% | Combined Annual Report on Greater Monger Project – C108/2001 for period 1 May 2011 to 30 April 2012, E25/208, |
| A87247 | 2010 | Integra Mining Ltd | Greater Monger | 9.9% | Combined Annual Report on Greater Monger Project – C108/2001 for period 1 May 2009 to 30 April 2010 |
| A87303 | 2010 | Pioneer Resources Ltd | Juglah Dome | 24% | Exploration Licence 25/381 Juglah Dome Annual Technical Report For the Period 21th May 2009 to 20th May 2010 |
| A87892 | 2010 | Silver Lake Resources Pty Ltd | Mount Monger | <1% | Mount Monger Project, Annual Report for the period 01/07/2009 to 20/06/2010 , C72/2004. |
| A88628 | 2010 | Integra Mining Ltd | Wattle Dam | <1% | Combined Annual Report on Wattle Dam Project – C132/2007 for period 1 October 2009 to 30 September 2010 |
| A88848 | 2010 | Integra Mining Ltd | Mount Monger | <1% | Mt Monger Project, Annual Report for the period 1st November 2009 to 31st October 2010, C135/2007. |
| A87591 | 2010 | Integra Mining Ltd | Greater Monger | 23% | Partial Surrender Report on E25/208 for period 1 August 2006 to 30 July 2010 |
| A87703 | 2010 | Integra Mining Ltd | Wattle Dam | <1% | Surrender Report on E25/298 for period 10 August 2005 to 9 August 2010 |
| A88343 | 2010 | Integra Mining Ltd | Mount Monger | <1% | Mt Monger Project, Final Surrender Report for the period 7th September 2006 to 6th September 2010, P25/1842-18 |
| A82327 | 2009 | Integra Mining Ltd | Greater Monger | 9.9% | Combined Annual Report on Greater Monger Project – C108/2001 for period 1 May 2008 to 30 April 2009 |
| A84317 | 2009 | Rubicon Resources Ltd | Wattle Dam | <1% | Partial Surrender report for the period 10th August 2005 to 6th August 2009, Wattle Dam Project E25/298 (C132/ |
| A84788 | 2009 | Silver Lake Resources Pty Ltd | Mount Monger | <1% | Mt Monger Project, Annual Report for the period 01/07/2008 to 30/06/2009, C72/2004. |
| A85250 | 2009 | Integra Mining Ltd | Wattle Dam | <1% | Combined Annual Report on Wattle Dam Project – C132/2007, Tenement Numbers: E25/298, E25/303, E25/319, C132/20 |
| A85375 | 2009 | Integra Mining Ltd | Mount Monger | <1% | Combined Annual Report on Mt Monger Project – C135/2007 for period 1 November 2008 to 31 October 2009, Report |
| A84525 | 2009 | Integra Mining Ltd | Greater Monger | 23% | Partial Surrender Report on E25/208 for period 1 August 2006 to 28 July 2009 |
| A78163 | 2008 | Newcrest Mining Ltd | Mount Monger | 9.9% | Mt Monger (JV) Project, Annual Report for the period ending 30 April 2008, C108/2001. |
| A80032 | 2008 | Silver Lake Resources Pty Ltd | Mount Monger | <1% | Mount Monger Project, Annual Report for the period 01/07/2007 to 30/06/2008, C72/2004. |
| A80489 | 2008 | Rubicon Resources Ltd | WATTLE DAM | <1% | Annual report for the period 1st October 2007 to 30th September 2008, Wattle Dam Project, C132/2007 |
| A80491 | 2008 | Rubicon Resources Ltd | MOUNT MONGER | <1% | Annual Report for the period 1st November 2007 to 31st October 2008, Mt Monger Project, C135/2007, Tenement Nu |
| A79540 | 2008 | Rubicon Resources Ltd | Wattle Dam | <1% | WATTLE DAM E25/298 East Coolgardie Mineral Field PARTIAL SURRENDER REPORT 10th Aug 2005 to 6 Aug 2008 |
| A76734 | 2007 | Rubicon Resources Ltd | Wattle Dam | <1% | WATTLE DAM E25/222, E25/241, E25/271, ..............P25/1830, P25/1831, East Coolgardie Mineral Field ANNUAL R |
| A75185 | 2007 | Newcrest Mining Ltd | Mount Monger | 3.2% | Mt Monger (JV) Project, Annual Report for the period ending 30th April 2004, E25/197,E25/203,E25/208........ |
| A76853 | 2007 | Rubicon Resources Ltd | Mount Monger | <1% | MT MONGER East Coolgardie & Coolgardie Mineral Fields ANNUAL REPORT C135/2007 1st Nov 2006 to 31st Oct 2007 |
| A74296 | 2006 | Heron Resources Ltd | Yindarlgooda | <1% | Yindarlgooda Project, Annual Combined Report C69/2006, 01 November 2005 to 31 October 2006, (Kurnalpi). |
| A72436 | 2006 | Newcrest Mining Ltd | Mount Monger / Jews/ Credo | <1% | Monger JV Annual Technical Report, Period Ending 30 April 2006, Combined Reporting No. C108/2001, (Newcrest Re |
| A70694 | 2005 | Alcaston Mining Nl | North Monger | <1% | North Monger Project, P25/1390, P25/1391........P26/2064.........M26/437 and M26/440, Annual Report for the pe |
| A70671 | 2005 | Newcrest Operations Ltd | Mount Monger | <1% | Monger JV Annual Report to the Dept of Industry and Resources for the period 01/05/2004 to 30/04/2005. DOIR Gr |
| A68758 | 2004 | Newcrest Mining Ltd | Mount Monger | 3.2% | Mt Monger (JV) Project, Annual Report for the period 01/05/2003 to 30/04/2004 , C108/2001. |
| A69074 | 2004 | Newcrest Mining Ltd | Mount Monger | 64% | Mt Monger (JV) Project, Partial Surrender Report for the period ending 30/03/2000 to 09/09/2004, E25/202. [C10 |
| A65889 | 2003 | South Kal Mines Pty Ltd | Transline | <1% | Combined Annual Report for the period 12th June 2001 to 11th June 2002 Transline JV Gold Project C16/2001: E25 |
| A66731 | 2003 | Placer Dome Asia Pacific Ltd | Greater Monger | 64% | Greater Monger Project, Partial Surrender Report for the period 30/03/2000 to 24/12/2002, E25/202. |
| A66939 | 2003 | Placer Dome Asia Pacific Ltd | Greater Monger | 8.9% | Annual Report for the period 01/05/2002 to 30/04/2003 C108/2001: E25/202 M25/117 M26/148,197,248-249,357,364,3 |
| A65401 | 2002 | Auriongold Exploration Pty Ltd | Greater Monger | 9% | Greater Monger Project Annual Report 01/05/2001 - 30/04/2002 C108/2001 Tenement/s P25/1503-1506, 1509/1509, 15 |
| A63729 | 2001 | New Hampton Goldfields Nl | Transline | <1% | Transline JV Gold Project Combined Annual Report for the period 12 June 2000 to 11 June 2001 on Reporting Grou |
| A62328 | 2001 | Croesus Mining Nl | Twin Tanks | 6.1% | Twin Tanks Project Annual Report For The Period 23 February 2000 to 22 February 2001 On The Tenement E25/199. |
| A53443 | 1998 | Titan Resources Nl | Horseshoe Dam | 19% | E25/101 Partial Surrender Report, Reporting Period :8 February 1992 to 13 January 1998 ( Horseshoe Dam Projec |
| A53594 | 1998 | Titan Resources Nl | Horseshoe Dam | 19% | E25/101 Partial Surrender Report, Reporting Period :8th February 1994 to 7th February 1998 |
| A54262 | 1998 | Amx Resources Nl | North Monger | <1% | Surrender Report on North Monger Tenements P25/1457-59, 1465-66, P26/2708, 2752-53. (Period: From Date of Gran |
| A55381 | 1998 | Minair Exploration Pty Ltd | Majestic | <1% | Prospecting Licence P25/1333 Majestic Project Annual Report reporting period from 10/06/1997 to 09/06/1998. |
| A51059 | 1997 | Titan Resources Nl | Horseshoe Dam | 19% | Horseshoe Dam Project : Annual Report ( M9086-All Tenements) Horseshoe Dam E25/101, Horseshoe Infill P25/1307- |
| A51132 | 1997 | Hampton Hill Mining Nl | Mount Monger | <1% | Mount Monger Project, 1996 Surrender Report P26/2176, 2534-2536, May 1997. |
| A52456 | 1997 | Amx Resources Nl | North Monger | <1% | Report on North Monger Tenements: M26/59, 278, 437, 440, 01/08/96 - 31/08/96 |
| A47769 | 1996 | Titan Resources Nl | Horseshoe Dam | 19% | Horseshoe Dam Project, Annual Report for reporting period 21st March 1995 to 20th March 1996, E25/101 (Horsesh |
| A47817 | 1996 | Hampton Hill Mining Nl | Easter Gift | <1% | Combined Annual Technical Report for the period 31/03/95 to 31/03/96 Mt Monger Tenements P26/2176 P26/2324 P26 |
| A43847 | 1995 | Hampton Hill Mining Nl | Mount Monger | <1% | Combined annual technical report for the period 1/1/94 to 31/12/94 Mount Monger tenements P26/2176, 2324, 2534 |
| A44279 | 1995 | Titan Resources Nl | Horseshoe Dam | 19% | Horseshoe Dam Project, E25/101&P25/1307-P25/1310 inclusive, for the period 8th February 1994 to 7th February ( |
| A46502 | 1995 | Westchester Pty Ltd | Majestic | <1% | Majestic Project, Annual Report Prospecting Licences P25/1332 & 1333 for the period 10/06/1994 to 09/06/1995. |
| A37902 | 1993 | Nugold Hill Mines Nl | Mount Monger | <1% | Mount Monger Project, Annual technical report. PL25/1153 and 1154. for the period 6/3/92 - 5/3/93. |
| A35001 | 1992 | Mt Kersey Mining Nl | Curtin | 11% | Curtin Project, Annual Report for the period 22nd January 1991 to 21st January 1992, E25/68 & 69. |
| A33929 | 1991 | Western Mining Corporation Ltd | Yindarlgooda Dome | <1% | Yindarlgooda Dome Project, Final Surrender Report for the period 9th August 1983 to 3rd May 1991, E25/2-5, M25 |
| A21791 | 1987 | Western Mining Corporation Ltd | Yindarlgooda Dome | <1% | Yindarlgooda Dome Project, Annual Report for the period 9th August 1986 to 8th August 1987, E25/2-5. |
| A18898 | 1986 | Western Mining Corporation Ltd | Yindarlgooda Dome | <1% | Annual report on Yindarlgooda Dome, E25/2, 3, 4, 5, For the period 9 August 1985 to 8 August 1986 |
| A18899 | 1986 | Western Mining Corporation Ltd | Yindarlgooda Dome | <1% | Terminal (partial surrender) report on the relinquished portion of the Yindarlgooda Dome, E25/2-5, To 9 August |
| A16203 | 1985 | Western Mining Corporation Ltd | Yindarlgooda Dome | <1% | Yindarlgooda Dome Project, Annual Report for the period 9th August 1984 to 8th August 1985, E25/2-5. |
| A14265 | 1984 | Western Mining Corporation Ltd | Yindarlgooda Dome | <1% | Yindarlgooda Dome Project, Annual Report for the period 9th August 1983 to 8th August 1984, E25/2-5. |
| A21792 | 1983 | Western Mining Corporation Ltd | Yindarlgooda Dome | <1% | Yindarlgooda Dome gold/copper-zinc exploration |
| A4697 | 1974 | Great Boulder Mines Ltd | Cowarna Rocks | <1% | Cowarna Rocks Project, Non-statutory Report: Cowarna I. P. Survey : Lines 158N-164N, 156N-192N ( No 3 Sill)., |
| A4492 | 1972 | Great Boulder Mines Ltd | Cowarna Rocks | <1% | Cowarna Rocks Project, Non-statutory Report: Summary Report, December 1972. |
| A2305 | 1971 | Union Miniere Dev & Mining Corp Ltd | Majestic Dyke | 5.7% | Majestic Dyke Project, Non-statutory Report:Final Report for the period ending 29/10/1971, MC25/405-414. |
| A4696 | 1971 | Great Boulder Mines Ltd | Cowarna Rocks | <1% | Cowarna Rocks Project, Non-statutory Report: ( No 1 Sill), Percussion Logs & Drill Hole Sections, 1970/1971. |
| A4698 | 1971 | Great Boulder Mines Ltd | Cowarna Rocks | <1% | Cowarna Rocks Project, Non-statutory Report: I. P. Lines 60N-92N & 128N-174N, to January 1971. |
| A4693 | 1970 | Great Boulder Mines Ltd | Cowarna Rocks | <1% | Cowarna Rocks Project, Non-statutory Report: No 3 Sill, Drill Holes & Logs, November 1970, |
| A4695 | 1970 | Great Boulder Mines Ltd | Cowarna Rocks | <1% | Cowarna Rocks Project, Non-statutory Report: Drill Holes & Logs, ( No 2 Sill) for the year ending 31/12/1970. |
| A38751 | 1753 | Inco Australia Ltd | Eastern Goldfields regional mapping | <1% | Eastern Goldfields regional mapping |
Tenure detail Free account
- Current holders & shares
- Holder change history
- Expenditure history
- Conditions & endorsements
- Native title context
- Combined reporting
- Rent status
Tenement intelligence Premium
- Time to expiry
- 20 months · 3 May 2028
- At-risk & opportunity signals
- Expenditure compliance
- 5-year track record
- Spend trend & exploration intensity
- Expiry band
- Ownership age
- Dealings, mortgages & caveats
- Transfer history
What does the exploration record say about this ground?
NextMaps reads every WAMEX report over E 25/535 into a referenced prospectivity assessment: the geology, the historical programs, the drill intercepts and geochemistry, and the untested gaps — every claim cited back to its source report. New accounts include a free prospectivity report. Prefer the raw due diligence? The Tenure Pack bundles the full register record, tenure history and spatial datasets for this ground.
Open on the map — full register record About AI reports About Tenure PacksDo you hold E 25/535? Listing is free. A facilitation fee applies only if you sell to a buyer we introduce.
List this tenementTenure data sourced from the DMPE public registers and SLIP WA (© Government of Western Australia, CC BY 4.0), as at 2026-08-21. Compiled by NextMaps. Verify against primary sources before reliance.