E 37/1592
E 37/1592 is a live exploration licence in the Shire of Leonora, Western Australia, held by Golden Manifesto Pty Ltd (part of Evergold Minerals Limited). Granted on 17 Mar 2026 for 5 years, it expires on 16 Mar 2031. The ground is covered by 71 historical WAMEX reports.
Register summary
- Holder
- Golden Manifesto Pty Ltd
- Part of
- Evergold Minerals Limited (ASX:EG1) as at 2026-06-30
- Local government
- Shire of Leonora
- Application received
- 7 July 2025
- Commenced
- 17 Mar 2026
- Expiry
- 16 Mar 2031
- Term
- 5 Years
The full record on E 37/1592
The register summary says who holds it today. The rest of the record says how they came to, what is attached to it, and whether it is being worked.
- Current holders and their shares (no change of holder on record)
- The full record: 1 year of expenditure, 11 conditions and 14 endorsements
- Native title context, combined reporting and rent status
- At-risk and opportunity signals, and expenditure compliance over five years
- Dealings, mortgages, caveats and transfer history
- Expiry band, and how long the holder has had it
Exploration history on this ground
| Report | Year | Operator | Project | On this ground | Title |
|---|---|---|---|---|---|
| A123220 | 2020 | Round Oak Jaguar Pty Ltd; Round Oak Jaguar Project Pty Ltd | Teutonic Bore Project | <1% | Combined Annual Report 2019 Teutonic Bore Project C/157/2002 for the period 1 January 2019 to 31 December 2019 |
| A125691 | 2020 | St Barbara Limited | Gwalia | <1% | Gwalia Project Combined Reporting Group C55/2004 - Annual Report for the Period 1 October 2019 to 30 September |
| A122153 | 2019 | St Barbara Limited | Gwalia | <1% | Gwalia Project Combined Reporting Group C55/2004 - Annual Report for the Period 1 October 2018 to 30 September |
| A119556 | 2019 | Round Oak Jaguar Project Pty Ltd; Round Oak Jaguar Pty Ltd | Teutonic Bore | <1% | C157/2002 Combined Annual Report for Teutonic Bore Project for the period 1 January 2018 to 31 December 2018 |
| A115994 | 2018 | Independence Group Nl | Teutonic Bore | <1% | Combined Annual Report C157/2002 Teutonic Bore Project for the period from 1st January 2017 to 31st December 2 |
66 more reports
| A118601 | 2018 | St Barbara Limited | Gwalia | <1% | Gwalia Project Combined Reporting Group C55/2004 - Annual Report for the Period 1 October 2017 to 30 September |
| A112037 | 2017 | Independence Group Nl | Teutonic Bore | <1% | Combined Annual Report on C157/2002 Teutonic Bore Project for the period 1 January 2016 to 31 December 2016 |
| A115512 | 2017 | St Barbara Limited | Gwalia | <1% | Gwalia Project Combined Reporting Group C55/2004 - Annual Report for the Period 1 October 2016 to 30 September |
| A108500 | 2016 | Independence Group Nl | Teutonic Bore | 20% | Final Surrender Report on E37/1068, part of Combined Reporting Group C157/2002, Teutonic Bore Project, for the |
| A110551 | 2016 | St Barbara Limited | Gwalia | <1% | Gwalia Project Combined Reporting Group C55/2004 - Annual Report for the Period 1 October 2015 to 30 September |
| A107737 | 2016 | Independence Group Nl | Teutonic Bore | <1% | Combined Annual Report on C157/2002, Teutonic Bore Project, for the period 1 January 2015 to 31 December 2015 |
| A105579 | 2015 | St Barbara Ltd | Leonora | <1% | Annual Mineral Exploration Report - DMP Combined Reporting Group C162/2006 (Leonora) Reporting Period 1 April |
| A105028 | 2015 | Independence Group Nl | Teutonic Bore | 1% | Combined Annual Report on C157/2002, Teutonic Bore Project, for the period 1 January 2014 to 31 December 2014, |
| A107603 | 2015 | St Barbara Limited | Gwalia | <1% | Gwalia Project C55/2004 Combined Annual Report for the Period 1 October 2014 to 30 September 2015 |
| A101281 | 2014 | Independence Group Nl | Teutonic Bore | <1% | Combined Annual Report on C157/2002, Teutonic Bore Project, for the period 1 January 2013 to 31 December 2013, |
| A102258 | 2014 | St Barbara Ltd | Leonora | <1% | Annual Mineral Exploration Report - DMP Combined Reporting Group C162/2006 (Leonora) Reporting Period 1 April |
| A98017 | 2013 | St Barbara Ltd | Leonora | <1% | Leonora Project, Annual Report for the period 1st April 2012 to 31st March 2013, E37/670.......E37/964; M36/41 |
| A97747 | 2013 | Independence Group Nl | Teutonic Bore | <1% | Combined Annual Report on C157/2002, Teutonic Bore Project, for the period 1 January 2012 to 31 December 2012, |
| A98608 | 2013 | Independence Group Nl | Teutonic Bore | <1% | Teutonic Bore Project, Annual Report for the period 1st January 2012 to 31st December 2012, E37/258........E37 |
| A93822 | 2012 | St Barbara Ltd | Leonora | <1% | Leonora C162/2006 Annual Report for the Period 1 April 2011 to 31 March 2012 |
| A93519 | 2012 | Jabiru Metals Ltd | Teutonic Bore | <1% | Teutonic Bore Project Combined Annual Report C157/2002 for the period 1st January 2011 to 31st December 2011 |
| A89147 | 2011 | St Barbara Mines Ltd | Leonora | <1% | Leonora Project, Final Surrender Report for E37/679 |
| A89792 | 2011 | Jabiru Metals Ltd | Teutonic Bore | <1% | Teutonic Bore Project Combined Annual Report C157/2002 for the period 1st January 2010 to 31st December 2010 |
| A90352 | 2011 | St Barbara Ltd | Leonora | <1% | Leonora Project, Annual Report for the period 1st April 2010 to 31st March 2011, Tenements as per Combined Rep |
| A87123 | 2010 | St Barbara Ltd | Leonora | <1% | Annual Report for the Period 1 April 2009 to 31 March 2010, Leonora, C162/2006, E37/235, E37/496, E37/573, E37 |
| A86577 | 2010 | Jabiru Metals Ltd | Teutonic Bore | <1% | Teutonic Bore Project Combined Annual Report C157/2002, For the period 1st January 2009 to 31st December 2009, |
| A81243 | 2009 | Jabiru Metals Ltd | TEUTONIC BORE | <1% | TEUTONIC BORE PROJECT COMBINED ANNUAL REPORT C157/2002 For the period 1st January 2008 to 31st December 2008 |
| A78149 | 2008 | Jabiru Metals Ltd | Teutonic Bore | <1% | COMBINED ANNUAL REPORT, E37/512, E37/258, E37/319, M37/44, M37/515, M37/1132, M37/1153, P37/4326, P37/6794-P37 |
| A78842 | 2008 | St Barbara Ltd | Leonora | <1% | LEONORA PROJECT ANNUAL REPORT FOR THE PERIOD 1 APRIL 2007 - 31 MARCH 2008 GROUP: C162/2006 E37/235, E37/236, E |
| A74304 | 2007 | St Barbara Ltd | Mount Newman | 18% | Mt Newman(Pacmin) Project E37/345, Surrender Report for the Period 7 July 1994 to 20 October 2006, (St Barbara |
| A75283 | 2007 | St Barbara Ltd | Leonora | <1% | Leonora Project, Annual Report for the Period 1 April 2006 - 31 March 2007, C162/2006.(Report No.0051-2007-02) |
| A74695 | 2007 | Jabiru Metals Ltd | Teutonic Bore | <1% | Combined Annual Report Teutonic Bore Project C157/2002 From 18 January 2006 to 17 January 2007 |
| A72388 | 2006 | Jabiru Metals Ltd | Teutonic Bore | <1% | Combined Annual Report E37/258, 512, M37/44,515, 1132, 1153, P37/4326, Teutonic Bore Project, Combined Reporti |
| A72400 | 2006 | St Barbara Mines Ltd | Tarmoola | 2.2% | Tarmoola Regional Project, Annual Report for the Period 1 April 2005 to 31 March 2006, C100/2003, (St Barbara |
| A70505 | 2005 | Jabiru Metals Ltd | Teutonic Bore | <1% | Combined annual report, E37/258, 501, 512, 691, M37/44, P37/4326, and 6235, Teutonic Bore Project, C157/2002, |
| A70723 | 2005 | St Barbara Mines Ltd | Tarmoola Regional | 2.2% | Tarmoola Regional Project, Annual Report for the period 1st April 2004 to 31st March 2005,( C100/2003), E37/23 |
| A68643 | 2004 | Sons Of Gwalia Ltd | Tarmoola | 2% | Annual Report for the period 01/04/2003-31/03/2004 Tarmoola Regional Project (C100/2003) E37/235, E37/345, E3 |
| A68874 | 2004 | Pilbara Mines Ltd | Teutonic Bore | <1% | Exploration Licences E37/258, M37/44, E37/501, E37/691, E37/512, P37/6235, Teutonic Bore Project Combined Annu |
| A65854 | 2003 | Sons Of Gwalia Ltd | Mount Newman | 2.6% | 2001/02 Annual Report for period 01/07/01 to 30/06/02 Group Reporting No C121/1999 Mount Newman/Royal Arthur B |
| A66964 | 2003 | Pilbara Mines Ltd | Teutonic Bore | <1% | Combined Annual Report for the period ending 17 January 2003 C157/2002 (formerly C417/1994): E37/258, M37/44, |
| A67076 | 2003 | Sons Of Gwalia Ltd | MOUNT NEWMAN | 2.6% | MOUNT NEWMAN, Annual report for the period 1 July 2002 to 30 June 2003 C121/1999: M37/459-460,478 E37/235,284, |
| A63877 | 2002 | Sons Of Gwalia Ltd | Royal Arthur Bore | 2.5% | 2000/01 Annual Report Royal Arthur Bore Project Area E37/235, E37/284, E37/345, M37/459, M37/460, M37/478, P37 |
| A64647 | 2002 | Pilbara Mines Ltd | Teutonic Bore (Wendy's Bore) | <1% | Exploration Licece E37/258 & Prospecting Licence P37/4326 Teutonic Bore (Wendy's Bore) Combined Annual Report |
| A61673 | 2001 | Pilbara Mines Ltd | Teutonic Bore | <1% | Digital Data at November 2000 on P37/4326, E37/258,501,512, M37/44,636,705, Teutonic Bore. |
| A62553 | 2001 | Pilbara Mines Ltd | Teutonic Bore (Wendy's Bore) | <1% | Exploration Licence E37/258 & Prospecting P37/4326, Teutonic Bore (Wendy's Bore) Combined Annual Report for th |
| A62612 | 2000 | Pacmin Mining Corporation Ltd | Royal Arthur Bore | 2.5% | 1999/2000 Annual Report Royal Arthur Bore Project Area E37/235, E37/284, E37/345, M37/459, M37/460, M37/478 P3 |
| A57072 | 1999 | Goldfields Exploration Pty Ltd | Teutonic Bore | <1% | Teutonic Bore JV 18/01/97 - 17/01/98 E37/258, 282, 353, 373-375, 501, P37/4326, M37/44, MLA37/515, 636, 705 |
| A53419 | 1998 | Tarmoola Australia Pty Ltd | Mount Newman | 3% | Mount Newman Project, Annual Exploration Report E37/235, 293, 244, 245, M37/458-460, P37/3995, 5010 etc. 30/09 |
| A53496 | 1998 | Tarmoola Australia Pty Ltd | Mount Newman | 18% | Compulsory Partial Surrender Report Tenement E37/345 (Mt Newman Project Group) (1997) |
| A53849 | 1998 | Tarmoola Australia Pty Ltd | Mount Newman | 3% | Mount Newman Project - Annual Exploration Report E37/235, 293, 344, 345, M37/458-460, P37/3995, 5010 etc. 30/0 |
| A55212 | 1998 | Tarmoola Australia Pty Ltd | Mount Newman | 18% | M Newman Project Group, E37/345 4th Year Compulsory Partial Surrender Report 06/1998 |
| A50159 | 1997 | Mt Edon Gold Mines Aust Ltd | Mount Newman | 3% | Mount Newman Project E37/235 E37/293 E37/344 E37/345 M37/458 to M37/460 P37/3995 P37/5010 to P37/5015 P37/5114 |
| A50936 | 1997 | Goldfields Exploration Pty Ltd | Teutonic Bore | <1% | Annual Report Teutonic Bore JV E37/247 E37/258 E37/353 E37/373 to E37/375 P37/4326 M37/44 MLA37/515 Technical |
| A47244 | 1996 | Goldfields Exploration Pty Ltd | Teutonic Bore | <1% | Annual report Teutonic Bore JV E37/247 E37/258 E37/282 E37/353 E37/373 to E37/375 P37/4326 M37/44 MLA37/515 Te |
| A44162 | 1995 | Pancontinental Gold Operations Pty Ltd | Teutonic Bore | <1% | Teutonic Bore Project, Annual Report for the period ending 17th January 1995, E37/247 E37/258 & E37/282; M37/ |
| A46261 | 1995 | Mt Edon Gold Mines Aust Ltd | Mount Newman | 18% | Annual report on the Exploration of the Mount Newman Prospect for the period ending July 6th, 1995 E37/345 Mou |
| A42078 | 1994 | Mim Exploration Pty Ltd | Snowy's Well | <1% | Annual Report for the period 07/06/93-06/06/94 Snowy's Well Project E37/258 P37/4326 |
| A38711 | 1993 | Mim Exploration Pty Ltd | Teutonic Bore/ Snowys Well | <1% | Annual Report for the period 07/06/92-06/06/93 Teutonic Bore/Snowys Well Project E37/258 |
| A10298 | 1981 | Seltrust Mining Corp Pty Ltd | Cutmore East & West | 3% | Cutmore East & West Project, Annual Report for the period 1st January 1979 to 31st December 1980, MC37/4211, 4 |
| A10299 | 1981 | Seltrust Mining Corp Pty Ltd | Teutonic Bore | <1% | Teutonic Bore Project, Non-statutory Report: Report for the period 1st January 1979 to 31st December 1980, MC3 |
| A8787 | 1979 | Carpentaria Exp Co Pty Ltd | Dunk's Well | <1% | Dunk's Well Project, Non-statutory Report: Final Report, July 1979, MC37/4721 & 4722. |
| A19960 | 1979 | Australian Selection Pty Ltd | Cutmore - Teutonic Bore | 3% | Cutmore Claims - Teutonic Bore Area, Progress [non-statutory] report, 1st October 1977 to 31st December 1978, |
| A6576 | 1976 | Carpentaria Exp Co Pty Ltd | Dunk Well | <1% | Dunk Well Project, Non-statutory Report: Final Report, January 1976, MC37/4721-4723 & 4725. |
| A6276 | 1975 | Carpentaria Exp Co Pty Ltd | Dunk's Well | <1% | Dunk's Well Project, Non-statutory Report: Progress Report, September 1975, MC37/4721-4723 & 4725. |
| A5631 | 1974 | Australian Selection Pty Ltd | Cutmore | 3.6% | Cutmore Claims, Progress report [non-statutory], March 1974, MC37/4211-4215, 37/4222-4232 |
| A4008 | 1973 | Newmont Pty Ltd | New Well | <1% | New Well Project, Non-statutory Report:Final Exploration Report, May 1973, MC37/592-597. |
| A5630 | 1973 | Australian Selection Pty Ltd | Cutmore | 3.6% | Cutmore Claims, Progress report [non-statutory], September 1973, MC37/4211-4215, 37/4222-4232 |
| A8959 | 1971 | Culpac Pty Ltd | Mount Stirling- Mount Davis | 1% | Mt Stirling- Mt Davis Project, Non-statutory Report: Exploration of Mt Stirling & Mt Davis Prospects, Mt Marga |
| A8960 | 1971 | Culpac Pty Ltd | Mount Davis - Mount Stirling | 1% | Mt Davis - Mt Stirling Project, Non-statutory Report: Report on Photo -Geological Study, Mt Davis & Mt Stirlin |
| A38751 | 1753 | Inco Australia Ltd | Eastern Goldfields regional mapping | <1% | Eastern Goldfields regional mapping |
| A82836 | 1753 | St Barbara Ltd | Leonora | <1% | LEONORA PROJECT ANNUAL REPORT FOR THE PERIOD 1 APRIL 2008 – 31 MARCH 2009 GROUP: C162/2006 TENEMENTS: E37/235, |
What does the exploration record say about this ground?
NextMaps reads the WAMEX reports over E 37/1592 into a referenced prospectivity assessment: the geology, the historical programs, the drill intercepts and geochemistry, and the untested gaps, with every claim cited back to its source report. New accounts include a free report (how the reports work). Prefer the raw due diligence? A Tenure Pack bundles the full register record, tenure history and spatial datasets for this ground.
Get the free report Full register record on the mapDo you hold E 37/1592? Listing is free. A facilitation fee applies only if the ground ends up with a buyer we introduce.
List this tenementTenure data sourced from the DMPE public registers and SLIP WA (© Government of Western Australia, CC BY 4.0), as at 2026-10-08. Compiled by NextMaps. Verify against primary sources before reliance.