E 52/4626
E 52/4626 is a pending exploration licence in the Shire of Meekatharra, Western Australia, applied for by Mount Gibson Mining Limited (part of MGX Resources Limited). The application was received on 24 Aug 2026 and is awaiting a decision. The ground is covered by 37 historical WAMEX reports.
Register summary
- Holder
- Mount Gibson Mining Limited
- Part of
- MGX Resources Limited (ASX:MGX) as at 2025-06-30
- Local government
- Shire of Meekatharra
- Application received
- 24 Aug 2026
The full record on E 52/4626
The register summary says who has applied for it. The rest of the record says what is attached to the application and how it is progressing.
- Current holders and their shares (no change of holder on record)
- Expenditure history, conditions and endorsements
- Native title context, combined reporting and rent status
- Expenditure compliance, expiry and ownership signals, once the application is granted
- Dealings, mortgages, caveats and transfer history
Exploration history on this ground
| Report | Year | Operator | Project | On this ground | Title |
|---|---|---|---|---|---|
| A144996 | 2024 | Murchison Ree Pty Ltd | Lyons | 8.1% | Final Surrender Report for E52/4040 Lyons Project for the period 9 May 2023 to 19 July 2024 |
| A135096 | 2023 | Metals Of Australia Pty Ltd | TINO RANGE | <1% | Annual Report E52/3771 TINO RANGE for the period ending 15/03/2023. |
| A127146 | 2021 | Metals Of Australia Pty Ltd | Tino Range | <1% | Annual Report E52/3771 Tino Range Project for the period 16 March 2020 to 15 March 2021 |
| A110767 | 2017 | Abra Mining Pty Limited | Jillawarra | 3.2% | Annual Report for the Jillawarra Project 1 December 2015 to 30 November 2016 |
| A110768 | 2017 | Abra Mining Pty Limited | Jillawarra | 3.8% | Partial Surrender Report for E52/1970 and E52/1971 Jillawarra 10 October 2006 to 7 October 2016 |
32 more reports
| A111843 | 2017 | Abra Mining Pty Limited | Jillawarra | 33% | Final Report for E52/2693 for the period 7 July 2011 to 18 October 2016 |
| A114096 | 2017 | Abra Mining Pty Limited | Jillawarra | 6% | Final Surrender Report for E52/1970 For the Period 10 October 2006 to 10 April 2017 |
| A114006 | 2017 | Cosmopolitan Minerals Ltd | Woodlands | <1% | Annual Report on the Woodlands Project C83/2016, E52/3191, 3250 & 3391 for the period 16 January 2016 to 15 Ja |
| A115435 | 2017 | Abra Mining Pty Ltd | Jillawarra | 1.5% | Jillawarra Project E52/1971 Final Surrender for the period 10/10/2006 - 18/09/2017 |
| A107807 | 2016 | Abra Mining Pty Limited | Jillawarra | 3.8% | Annual Report for the Jillawarra Project C186/2006, E52/01413, E52/01970, E52/01971, E52/01972, E52/02693 for |
| A104582 | 2015 | Abra Mining Pty Ltd | Jillawarra | 3.8% | Jillawarra Project Combined Annual Report GSWA C186/2006 For the period 1 Dec 2013 to 30 Nov 2014, E52/1413, E |
| A105947 | 2015 | Rio Tinto Iron Ore | Upper Gascoyne | 3.1% | Upper Gascoyne C114/2014 Surrender Report for Exploration Licences 09/2037, 09/2038 & 52/2907 for the period 1 |
| A100832 | 2014 | Abra Mining Pty Ltd | Jillawarra | 3.8% | Jillawarra Project, Annual Report for the period 01/12/2012 to 30/11/2013, E52/1413, 1970-1972 & 2693; P52/128 |
| A96446 | 2013 | Abra Mining Pty Ltd | Jillawarra | 3.8% | Jillawarra Project Combined Annual Report GSWA C186/2006 For the period1 Dec 2011 to 30 Nov 2012, E52/1413.... |
| A97373 | 2013 | Encounter Resources Ltd | Staten | <1% | Annual Report and Final Surrender for the period 28 January 2011 to 17 January 2013, Staten Project |
| A100527 | 2013 | Rio Tinto Exploration Pty Ltd | Teano | 94% | Voluntary Surrender Technical Report for the Period 15/03/2013 to 5/12/2013, Exploration Licence 52/2853 |
| A92761 | 2012 | Abra Mining Ltd | Jillawarra | 3.1% | Jillawarra Project Combined Annual Report GSWA C186/2006 For the period 01 Dec 2010 to 30 Nov 2011 |
| A92256 | 2012 | Aurora Minerals Ltd | Capricorn Southeast | 9.3% | SURRENDER REPORT CAPRICORN SOUTHEAST PROJECT BANGEMALL BASIN WESTERN AUSTRALIA COMBINED REPORTING C63/2010 SUR |
| A92825 | 2012 | Aurora Minerals Ltd | Capricorn Southeast | 1.3% | Annual Technical Report; Capricorn Southeast Project; Basngemall Basin, Western Australia, Combined Reporting |
| A93372 | 2012 | Encounter Resources Ltd | Staten | <1% | Staten Project, Annual [& Final Surrender] Report for the period 28th January 2011 to 27th Janaury 2012, E52/2 |
| A90092 | 2011 | Abra Mining Ltd | Jillawarra | 6% | Jillawarra Project, Partial Surrender Report for E 52/1970 for the period 10-Oct-2006 to 22-Fbe-201. (C186/200 |
| A90093 | 2011 | Abra Mining Ltd | Jillawarra Project | 1.5% | JILLAWARRA PROJECT, Partial Surrender Report for E52/1971, FOR THE PERIOD 10-OCT-2006 TO 22-FEB-2011 |
| A89213 | 2011 | Abra Mining Ltd | Jillawarra | 3.1% | Jillawarra Project Combined Annual Report GSWA C186/2006 For the period 1Dec 2009 to 30th Nov 2010 |
| A89788 | 2011 | Aurora Minerals Ltd | Capricorn Southeast | 1.3% | Annual Technical Report; Capricorn Southeast Project; Combined Reporting C63_2010; Year ending Dec 31 2010 |
| A87852 | 2010 | Encounter Resources Ltd | Staten | <1% | Annual and Final Surrender Report for the period 20 August 2009 to 13 August 2010, Staten Project |
| A85494 | 2010 | Abra Mining Ltd | Jillawarra | 3.1% | Jillawarra Project C186/2006 Combined Annual Report for the Jillawarra Project for the period 1/12/2008 - 30/1 |
| A80709 | 2009 | Abra Mining Ltd | Jilllawarra | 3.1% | Jilllawarra Project Combined Annual report C186/2006, For the period 01/12/2007 - 30/11/2008 |
| A77155 | 2008 | Abra Mining Ltd | Jillawarra | 3.1% | Combined Annual Report for the Jillawarra Project (C186/2006 tenements E52/1413, E52/1970, E52/1971 & E52/1972 |
| A74188 | 2007 | Abra Mining Ltd | Jillawarra | 3.1% | Jillararra Project E52/1413,1970-1972, Combined Annual Report C186/2006, (Period 01/12/05 to 30/11/06, Mt Eger |
| A52821 | 1997 | Bhp Minerals Pty Ltd | Glen Ross | 22% | Glen Ross Project, [BHP-Cambrian JV] Annual Report , E52/950, for the year ending 19/09/1997 |
| A47809 | 1996 | Cra Exploration Pty Ltd | Teano Range | 14% | Teano Range Project, Annual Report for year ending 10th March 1996, E52/828 &E52/910.( Teano Range 1 &2 ) |
| A50380 | 1996 | Bhp Minerals Pty Ltd | Glen Ross | 22% | Glen Ross Project, Annual Report ,E52/950, for the period 29/09/1995 to 19/09/1996. |
| A44416 | 1995 | Cra Exploration Pty Ltd | Teano Range 1 & 2 | 14% | Teano Range 1 & 2 Project, Annual Report E52/828 ( Teano Range 1) E52/910 ( Teano Range 2) for the year ending |
| A21559 | 1987 | Alcoa Of Australia Ltd | Bangemall Basin | <1% | Bangemall Basin, [Non-statutory Report: Mapping, circa 1966] |
| A9335 | 1980 | Amoco Minerals Aust Co | Glenn Ross | 3.2% | Glenn Ross Project, Non-statutory Report:Final Report for the period 17th June 1980 to 4th August 1980, TR70/7 |
| A21557 | 1972 | Alcoa Of Australia Ltd | Bangemall Basin | <1% | Bangemall Basin Project, Non-statutory Report: Edmund Area, Plates 1- 5, January 1972, |
| A571 | 1967 | Westfield Minerals Nl | Ashburton-Bangemall | <1% | Ashburton-Bangemall Project, Non-statutory Report:Report for 1966, (Vol 2) Exploration within the Bangemall Gr |
What does the exploration record say about this ground?
NextMaps reads the WAMEX reports over E 52/4626 into a referenced prospectivity assessment: the geology, the historical programs, the drill intercepts and geochemistry, and the untested gaps, with every claim cited back to its source report. New accounts include a free report (how the reports work). Prefer the raw due diligence? A Tenure Pack bundles the full register record, tenure history and spatial datasets for this ground.
Get the free report Full register record on the mapDo you hold E 52/4626? Listing is free. A facilitation fee applies only if the ground ends up with a buyer we introduce.
List this tenementTenure data sourced from the DMPE public registers and SLIP WA (© Government of Western Australia, CC BY 4.0), as at 2026-10-08. Compiled by NextMaps. Verify against primary sources before reliance.