L 38/365
L 38/365 is a live miscellaneous licence in the Shire of Laverton, Western Australia, held by Regis Resources Limited. Granted on 23 June 2022 for 21 years, it expires on 22 June 2043. The ground is covered by 175 historical WAMEX reports.
Register summary
- Holder
- Regis Resources Limited
- Local government
- Shire of Laverton
- Application received
- 17 Dec 2021
- Commenced
- 23 June 2022
- Expiry
- 22 June 2043
- Term
- 21 Years
The full record on L 38/365
The register summary says who holds it today. The rest of the record says how they came to, what is attached to it, and whether it is being worked.
- Current holders and their shares (no change of holder on record)
- The full record: 23 conditions and 11 endorsements
- Native title context, combined reporting and rent status
- At-risk and opportunity signals, and expenditure compliance over five years
- Every register dealing (2 on record), with mortgages, caveats and transfers flagged
- Expiry band, and how long the holder has had it
Exploration history on this ground
| Report | Year | Operator | Project | On this ground | Title |
|---|---|---|---|---|---|
| A124986 | 2020 | Stone Resources Australia Limited | E38/1937 | 2% | E38/1937 Final Surrender Report for the period ending 08/07/2020 |
| A125005 | 2020 | Regis Resources Limited | Duketon Central | <1% | Combined Annual Mineral Exploration Report for the Duketon Central Project C95/2016 for the period ending 30/0 |
| A123520 | 2020 | Stone Resources Australia | Brightstar North | 1.7% | C209/2006 COMBINED ANNUAL EXPLORATION REPORT, BRIGHTSTAR NORTH, 1 JANUARY 2019 TO 31 DECEMBER 2019 |
| A123481 | 2020 | Duketon Mining Limited; Regis Resources Limited | Elistoun | <1% | Final Surrender Report E38/2819, Elistoun, 4 March 2014 to 27 February 2020 |
| A124932 | 2020 | Stone Resources Australia Limited | E38/1936 | 1% | E38/1936 Final Surrender Report for the period ending 31 October 2019 |
170 more reports
| A125250 | 2020 | Regis Resources Limited | Duketon Central | 1.2% | Combined Annual Mineral Exploration Report for the Duketon Central Project C47/2016 for the period ending 31/0 |
| A125258 | 2020 | Stone Resources Australia Limited | Brightstar North | 7.6% | E38/2332 Final Surrender Report for the period ending 27/07/2020 |
| A125260 | 2020 | Stone Resources Australia Limited | Brightstar | 7.4% | E38/3233 Final Surrender Report for the period ending 27/07/2020 |
| A119561 | 2019 | Stone Resources Australia Limited | Brightstar North | 1.5% | C209/2006 Combined Annual Exploration Report for the period 1 January 2018 to 31 December 2018 |
| A121211 | 2019 | Regis Resources Limited | Duketon Central | <1% | Annual Report C95/2016 Duketon Central Project for the period 1 July 2018 to 30 June 2019 |
| A121507 | 2019 | Regis Resources Limited; Duketon Mining Limited | Duketon Central | <1% | Duketon Central - Combined Annual Report - C47/2016 for the period 1 August 2018 to 31 July 2019, E38/02976, E |
| A116697 | 2018 | Stone Resources Australia Limited | Brightstar North | 1.3% | Brightstar North C209/2006 Combined Annual Exploration Report for the period 19/05/2017 - 20/05/2018 |
| A117884 | 2018 | Regis Resources Limited | Duketon Central | <1% | Duketon Central C95/2016 Annual Report for the period 1 July 2017 to 30 June 2018 |
| A118049 | 2018 | Duketon Mining Limited | Duketon Central | <1% | Annual Report Duketon Central C47/2016 for the period 01/08/2017 - 31/07/2018 |
| A112656 | 2017 | Duketon Mining Limited | Duketon | <1% | Duketon Project E38/2819 Annual Report For the Period 4 March 2016 to 3 March 2017 |
| A112788 | 2017 | Stone Resources Australia Limited | Brightstar North | 1.3% | Brightstar North C209/2006 Combined Annual Exploration Report for the period 01/01/2016 – 31/12/2016 |
| A114311 | 2017 | Stone Resources Australia Ltd | Laverton | 7.4% | Final Surrender Report for E38/2596 for the period 18/08/2011 - 04/05/2017 |
| A114312 | 2017 | Stone Resources Australia Ltd | Laverton | 12% | E38/2597 Final Surrender Report for the period 18/08/2011 - 04/05/2017 |
| A114932 | 2017 | Regis Resources Limited | Duketon Central | <1% | Duketon Central Project C95-2016 Annual Report for the period 1 July 2016 to 30 June 2017 |
| A115072 | 2017 | Duketon Mining Limited | Duketon Central | <1% | Annual Report Duketon Central C47/2016 for the period 1 August 2016 to 31 July 2017, E38/02976, E38/03083, E38 |
| A108880 | 2016 | Duketon Mining Limited | Duketon | <1% | Duketon E38/2819 Annual Report for the period 04/03/2015 to 03/03/2016 |
| A109758 | 2016 | Regis Resources Limited | Duketon Central | <1% | Annual Report For the Period 1 July 2015 to 30 June 2016 DUKETON CENTRAL PROJECT C61/2003 |
| A108839 | 2016 | Stone Resources Australia Ltd | Brightstar North | 1.5% | C209/2006 Combined Annual Exploration Report for period 01/01/2015 – 31/12/2015 |
| A105227 | 2015 | Stone Resources Australia Ltd | Brightstar North | 1.5% | Combined Annual Exploration Report for C209/2006 from 01/01/2014 to 31/12/2014, E38/1936.....P38/4115 |
| A106601 | 2015 | Regis Resources Limited | Duketon Central | <1% | C61-2003 2015A Duketon Central Project Annual Report for the period 01/07/2014 - 30/06/2015 |
| A105565 | 2015 | Duketon Mining Ltd | Duketon | <1% | Duketon Project E38/2819, Annual Report for the period 04/03/2014 to 03/03/2015 |
| A106314 | 2015 | Duketon Mining Ltd | Duketon West | 1.6% | Surrender Report E38/1535 Duketon West Project for the period 10/06/2008 – 09/06/2015 |
| A102553 | 2014 | Duketon Mining Ltd | Duketon West | 6.5% | Duketon West Project, Surrender Report E38/2255 for the period 06/01/2010 – 17/03/2014. |
| A102988 | 2014 | Regis Resources Ltd | Duketon Central | <1% | Duketon Central Project, Annual Report for the period 01/07/2013 to 30/06/2014, E38/378.........E38/2857; M38/ |
| A104336 | 2014 | Duketon Mining Ltd | Duketon West | <1% | Duketon West Project. Annual Report, Combined Reporting No.: C99/2007, for the period 01/10/2013 – 30/09/2014 |
| A103266 | 2014 | Stone Resources Australia | E38/1937 | 2% | E38/1937 Partial Surrender Report for the period 08/08/2008 to 07/08/2014 |
| A101263 | 2014 | Stone Resources Australia | Brightstar North | 1.4% | Combined Annual Exploration Report for Brightstar North Project C209/2006 from 01/01/2013 to 31/12/2013, E 38/ |
| A97680 | 2013 | Stone Resources Australia | Brightstar North | 1.2% | CR209-2006 COMBINED ANNUAL EXPLORATION REPORT Reporting Period 1/01/2012 – 31/12/2012 |
| A97942 | 2013 | Stone Resources Australia | Brightstar North | 6.4% | Brightstar North Project, Annual Report for the period 05/08/2010 to 04/08/2011, P38/3781. [C209/2006] |
| A97944 | 2013 | Stone Resources Australia | Brightstar North | 39% | Brightstar North Project, Annual Report for the period 05/08/2010 to 04/08/2011, P38/3785 |
| A97947 | 2013 | Stone Resources Australia | Epsilon | 6.4% | Epsilon Project, Annual Report for the period 05/08/2011 to 04/08/2012, P38/3781. |
| A98828 | 2013 | Regis Resources Ltd | Duketon Central | <1% | Annual Combined Group Report for the period 1 July 2012 to 30 June 2013 Duketon Central Project (C61/2003) E38 |
| A99053 | 2013 | Stone Resources Australia | Brightstar North | 39% | Brightstar North P38/3875 Annual Exploration Report Reporting Period 05/08/2012 – 04/08/2013 |
| A99094 | 2013 | Regis Resources Ltd | Duketon Central | 11% | Surrender Report E38/1133 for the period 20 June 2006 to 18 July 2013 |
| A100800 | 2013 | Duketon Mining Ltd | Duketon West | <1% | Duketon West Project, Annual Report for the period 01/10/2012 to 30/09/2013, E38/1535, 1537, 1800, 2177, 2206, |
| A99056 | 2013 | Stone Resources Australia | P38/3871 | 6.4% | P38/3871 Annual Exploration Report 5/08/2012 – 4/08/2013 |
| A94597 | 2012 | Regis Resources Ltd | Duketon Central | <1% | Annual Combined Group Report for the period 1 July 2011 to 30 June 2012 Duketon Central Project C61/2003, E38/ |
| A94953 | 2012 | South Boulder Mines Ltd | Duketon West | 1.6% | Exploration Licence E38/1535 Duketon West Project C99/2007 Partial Surrender Report for the period 10/06/2008 |
| A95409 | 2012 | Stone Resources Australia | Epsilon | 7.4% | Epsilon E38/2596 Annual Exploration Report for the period 18/08/2011 – 17/08/2012 |
| A96070 | 2012 | Independence Group Nl; South Boulder Mines Ltd | Duketon West | <1% | Combined Annual Report C99/2007 “Duketon West” E38/1511, 1535, 1537, 1800, 1979, 2177, 2206, 2255, 2661, M38/1 |
| A95410 | 2012 | Stone Resources Australia | Epsilon | 12% | Epsilon E38/2597 Annual Exploration Report for the period 18/08/2011 – 17/08/2012 |
| A89303 | 2011 | A1 Minerals Ltd | King of Creation | 3.3% | Final Surrender Report E38/1368 (King of Creation Area) Period covered 18/01/2006 -17/01/2011 |
| A91382 | 2011 | South Boulder Mines Ltd | Duketon | 1.6% | Exploration Licence E38/1535, Duketon Project, Partial Surrender Report for the period 10/06/2008 to 9/06/2011 |
| A89810 | 2011 | A1 Minerals Ltd | Bright Star North | 1.3% | Bright Star North Project C209/2006 Combined Annual Report for the period 01/01/2010 to 31/12/2010 |
| A91193 | 2011 | Regis Resources Ltd | Duketon Central | <1% | Annual Combined Group Report for the period 1 July 2010 to 30 June 2011, Duketon Central Project (C61/2003) |
| A92270 | 2011 | South Boulder Mines Ltd | Dukewest | <1% | Combined Annual Report for C99/2007, Duketon West Project, for the Period 1 Oct 2010 to 30 Sept 2011 |
| A93427 | 2011 | A1 Minerals Ltd | Bright Star North | 1.2% | Bright Star North Project Combined Annual report for the period 01/01/2011 to 31/12/2011, C209/2006, E38/1936, |
| A86180 | 2010 | A1 Minerals Ltd | Brightstar North | 1.2% | Bright Star North Project C209/2006 Annual Combined Report for the period 01/01/2009 to 31/12/2009 |
| A87969 | 2010 | Regis Resources Ltd | Duketon | <1% | C61/2003 Duketon Central: Combined Annual Report On Exploration For The Period 1/07/2009 to 30/06/2010 |
| A86523 | 2010 | A1 Minerals Ltd | King of Creation | 3.3% | Partial Surrender Report E38/1368 (King of Creation Area), Period covered 18/01/2006 -17/01/2010 |
| A88530 | 2010 | South Boulder Mines Ltd | Duketon West | <1% | Combined Annual Report for C99/2007, Duketon West Project, for the Period 1 Oct 2009 to 30 Sept 2010 |
| A81678 | 2009 | A1 Minerals Ltd | Bright Star North | 1.2% | Bright Star North Project, Annual Report for th eperuiod 01/01/2008 to 31/12/2008, E38/1368. 1375, 1563, 1618, |
| A81985 | 2009 | A1 Minerals Ltd | King of Creation Area | 3.3% | PARTIAL SURRENDER REPORT E38/1368 (King of Creation Area), Period covered 18/01/2006 -17/01/2009 |
| A84064 | 2009 | Regis Resources Ltd | Duketon Central | 11% | PARTIAL SURRENDER REPORT ON EXPLORATION, FOR THE PERIOD 20/06/2006 TO 19/06/2009, Duketon Central, E38/1133, R |
| A84137 | 2009 | Regis Resources Ltd | DUKETON CENTRAL | <1% | COMBINED ANNUAL REPORT ON EXPLORATION FOR THE PERIOD 1/07/2008 TO 30/06/2009 PROJECT C61/2003 DUKETON CENTRAL |
| A79266 | 2008 | Regis Resources Ltd | DUKETON CENTRAL | <1% | COMBINED ANNUAL REPORT ON EXPLORATION FOR THE PERIOD 1/07/2007 TO 30/06/2008 PROJECT C61/2003 DUKETON |
| A85436 | 2008 | South Boulder Mines Ltd | Duketon West | <1% | Combined Annual Report C99/2007, Duketon West Project, for the period 1st Oct 2008 to 30th Sept 2009, E38/1499 |
| A77711 | 2008 | A1 Minerals Ltd | Brightstar North | <1% | Brightstar North Project Laverton, WA Combined Annual Report 1st January 2007 to 31 December 2007 Project No: |
| A79043 | 2008 | Regis Resources Ltd | CAMEL HUMP | 11% | ANNUAL REPORT ON EXPLORATION FOR THE PERIOD 20/06/2007 TO 19/06/2008 CAMEL HUMP E38/1133 |
| A75748 | 2007 | Regis Resources Nl | Camel Hump | 11% | Annual Report on Exploration for the Period 20/06/2006 to 19/6/2007 Camel Hump E38/1133 Volume 1 of 1 Report N |
| A74176 | 2007 | A1 Minerals Ltd | Brightstar North | <1% | Combined Annual Technical Report, Brightstar North Project C209/2006, For the period 31 January 2006 to 31 Jan |
| A75801 | 2007 | Regis Resources Nl | Duketon Central | <1% | Combined Annual Report On Exploration For The Period 1/7/200 5 to 30/6/2006; C61/2003 Duketon Central: E38/378 |
| A73284 | 2006 | Regis Resources Nl | Duketon Central | <1% | Combined Annual Report on exploration for the period 1/07/2005 to 30/06/2006, Project C61/2003 Duketon Central |
| A73196 | 2006 | A1 Minerals Ltd | King of Creation | <1% | King of Creation Project M38/160, Annual Technical Report for the Period 27 July 2005 to 26 July 2006, (Lavert |
| A69760 | 2005 | Newmont Australia Ltd | Duketon | <1% | Combined annual report for the period 01/07/03 - 30/06/04 Duketon Central Project, C61/2003, E38/378, E38/379, |
| A70955 | 2005 | Newmont Duketon Pty Ltd | Duketon | <1% | Combined annual report on exploration for the period 1/07/2004 to 30/06/2005, Project C61/2003, Duketon Centra |
| A71350 | 2005 | Bronzewing Gold Nl | King of Creation | <1% | King of Creation Project, Mining Lease 38/160, Annual Technical Report for the period 27 July 2004 to 26 July |
| A69449 | 2004 | Bronzewing Gold Nl | King of Creation | <1% | Annual report for the period 27/07/03 - 26/07/04 King of Creation Project, M38/160 |
| A66600 | 2003 | Newmont Australia Ltd | Duketon Belt/Erlistoun | <1% | Combined Annual Report on Exploration for period ended 17/3/2003 Project C16/1996 Erlistoun E38/379, 387, 565, |
| A67379 | 2003 | West Australian Metals Ltd | King of Creation | <1% | King of Creation Project, Annual Report for the period 27th July 2002 to 26th July 2003, M38/160. |
| A64877 | 2002 | Newmont Australia Ltd | Duketon Belt/Erlistoun | <1% | Combined Annual Report On Exploration For Period Ended 17/3/2002 Project C16/1996 Erlistoun E38/379, 386, 387, |
| A65365 | 2002 | West Australian Metals Ltd | King of Creation | <1% | King of Creation Project , Annual Report for the period 27th July, 2001 to 26th July 2002, M38/160. |
| A62652 | 2001 | Johnsons Well Mining Nl | Duketon Belt/Erlistoun | <1% | Exploration Licences: E38/379, 386-7, 404, 565, 649, 651, 653, 843, 1189-92, 1196 Mining Leases: M38/114, 237, |
| A63442 | 2001 | Bronzewing Gold Nl | King of Creation | <1% | King of Creation Project, Annual Report for the period 27th July, 2000 to 26th July 2001,M38/160. |
| A63547 | 2001 | Johnsons Well Mining Nl | Camel Hump | <1% | Exploration Licences: E38/495, 518, 845, 1147, 1148, Mining Lease: M38/262, Prospecting Licences: P38/2660, 27 |
| A63672 | 2001 | Johnsons Well Mining Nl | Duketon Belt/Erlistoun | <1% | Exploration licences: E38/379, 386-387, 404, 565, 649, 651, 653, 789, 843, 1189-1192, 1196. Mining leases: M3 |
| A59621 | 2000 | Sons Of Gwalia Ltd | Amy Clarke | 4.4% | Amy Clarke (JV Project, Partial Surrender Report for the period 16/11/1993 to 02/08/1999, E38/566 |
| A60613 | 2000 | Sons Of Gwalia Ltd | Amy Clarke | 2.9% | Amy Clarke JV, Annual Report for the Period 1/12/1998 to 30/11/1999, E38/496, E38/566, E38/598, P38/2486-9, P3 |
| A61116 | 2000 | Sons Of Gwalia Ltd | Swincer | <1% | Swincer Project, Annual Report for the period 01/01/1999 to 31/12/1999, E38/520, E38/521. |
| A61238 | 2000 | Sons Of Gwalia Ltd | Swincer | <1% | Swincer Project, Surrender Report for the Period 20/08/1993 to 23/06/2000, E38/520. |
| A61848 | 2000 | Johnsons Well Mining Nl | Camel Hump | <1% | Exploration Licences E38/495,518,845, Mining Leases M38/262, Prospecting Licences P38/2660,2718-2724,2737,2949 |
| A61966 | 2000 | Johnsons Well Mining Nl | Duketon Belt/Erlistoun | <1% | C16/1996 - Erlistoun Joint Annual Report for the period 18 March 1999 to 17 March 2000. Gold mining lease: GM |
| A63219 | 2000 | Sons Of Gwalia Ltd | Amy Clarke | 3.1% | Amy Clarke Project, Surrender Report for the period 5 January 1993 to 28 September 2000, E38/496, 566, 598; P |
| A57543 | 1999 | Sons Of Gwalia Ltd | Swincer | <1% | Swincer Project - Partial Surrender Report 20/08/93-09/07/98 E38/520-521 |
| A59200 | 1999 | Johnsons Well Mining Nl | Duketon Belt/Erlistoun | <1% | Joint Annual Report on the Erlistoun Project, E38/379, 386- 387, 404, 565, 649, 651, 653, 789, M38/114, 237, 2 |
| A54261 | 1998 | Sons Of Gwalia Ltd | Amy Clarke | 3% | Amy Clarke JV Project Annual report for the period 01/12/96-30/11/97 Tenements E38/496,566,598 P38/2486-2489,2 |
| A54583 | 1998 | Sons Of Gwalia Ltd | Swincer | <1% | Swincer Project, Annual Report for the period 1 January 1997 - 31 December 1997, E38/520-521, P38/2518-2519. |
| A55359 | 1998 | Sons Of Gwalia Ltd | Baneygo | <1% | Baneygo Project Annual report for the period 01/01/97- 31/12/97 Tenements EL38/545 EL38/547 EL38/665 EL38/667 |
| A55392 | 1998 | Johnsons Well Mining Nl | Duketon Belt/Erlistoun | <1% | Exploration Licences E38/379 E38/386 to E38/387 E38/565 E38/649 E38/651 E38/653 Mining Leases M38/114 M38/237 |
| A55510 | 1998 | Johnsons Well Mining Nl | Camel Hump | <1% | C184/1997 - Camel Hump, Joint Annual Report Exploration Licence:E38/495, 518, 845 26/03/97 - 25/03/98 |
| A55547 | 1998 | Sons Of Gwalia Ltd | Baneygo | 3.2% | Baneygo Project, PL 38/2520, 2521, 2525 Final Surrender Report, 23/03/94 - 18/04/98 |
| A55879 | 1998 | Bronzewing Gold Nl | King of Creation | <1% | King of Creation Project, Annual Report for the period 27//07/1997 to 26/07/1998, M38/160. |
| A56181 | 1998 | Sons Of Gwalia Ltd | Baneygo | 2.4% | Baneygo Project, Partial Surrender Report E38/547 24/09/93 - 09/07/98 |
| A56182 | 1998 | Sons Of Gwalia Ltd | Amy Clarke | 4.4% | Amy Clarke J.V. Project, Partial Surrender Report 16/11/93 - 02/04/98 E38/566. |
| A50479 | 1997 | Sons Of Gwalia Ltd | Swincer | <1% | Swincer Project , Annual Report for the period 1 January 1996 - 31 December 1996, E38/520-521, P38/2518-2519. |
| A50928 | 1997 | Sons Of Gwalia Ltd | Laverton | <1% | Laverton Region Baneygo Project Annual report for the period 1 January 1996 to 31 December 1996 Tenements E38/ |
| A50167 | 1997 | Sons Of Gwalia Ltd | Amy Clarke | 3% | Laverton Region Amy Clarke Joint Venture Project Annual report for the period 1 December 1995 to 30 November 1 |
| A50637 | 1997 | Sons Of Gwalia Ltd | Baneygo | 2.4% | Partial Surrender Report for the period 24 November 1993 - 23 November 1996 |
| A53635 | 1997 | Sons Of Gwalia Ltd | Doris Creek | 1.9% | Laverton Region, Doris Creek, Annual Report E38/542 For the Period 23/08/96 - 24/0897. |
| A48746 | 1996 | Central Kalgoorlie Gold Mines Nl | Doris Creek | 1.9% | Doris Creek Project, Annual Report for period ending 30th June 1996, E38/542. |
| A47730 | 1996 | Metex Resources Nl | Paillard Find | 2.3% | Paillard Find Project, Annual Report for period 1st February 1995 to 31st January 1996, P38/2527-2533. |
| A47739 | 1996 | Sons Of Gwalia Ltd | Laverton | <1% | Laverton Region North Eastern Goldfields Baneygo Project Annual report for the period 1 January 1995 to 31 Dec |
| A47742 | 1996 | Sons Of Gwalia Ltd | Swincer | <1% | Swincer Project ,Annual Report for the period 1 January 1995 - 31 December 1995,E38/520-521, P38/2518-2519. |
| A47872 | 1996 | Johnsons Well Mining Nl | Duketon Belt/Erlistoun | <1% | Gold Mining Lease G38/2882,Exploration Licences E38/379,565, Mining Leases M38/114,262,283,292,303,316-317,341 |
| A49227 | 1996 | Sons Of Gwalia Ltd | Swincer | <1% | Laverton Region Swincer Project Partial Surrender Report for the Period 20th Augusr 1996-19 August 1996 E38/5 |
| A49562 | 1996 | Roehampton Developments Pty Ltd | King of Creation | <1% | King of Creation Project, Annual Report for the period 27/07/1995 to 26/07/1996, M38/160. |
| A43653 | 1995 | Ramsgate Resources Ltd | Erlistoun - Duketon | 1% | Annual Report for the period 7th November 1993 to 6th November 1994, Erlistoun - Duketon Project, E38/384. |
| A45391 | 1995 | Roehampton Developments Pty Ltd | King of Creation | <1% | King of Creation Project, Annual Report for the period 27th July 1994 to 26th July 1995, M38/160. |
| A45519 | 1995 | Sons Of Gwalia Ltd | Laverton | <1% | Laverton Region Northeastern Goldfields Baneygo project Annual report for the period 01 January 1994 to 31 Dec |
| A46412 | 1995 | Johnsons Well Mining Nl | Duketon | <1% | Exploration Licence E38/379 Mining Licences M38/292 M38/303 M38/114 M38/352 M38/262 M38/316 M38/317 M38/341 M3 |
| A43856 | 1995 | Metex Resources Nl | Paillard Find | 2.3% | Paillard Find Project, Annual Report Prospecting Licences P38/2527-2533 for period 20th April 1994 to 31st Jan |
| A45428 | 1995 | Central Kalgoorlie Gold Mines Nl | Doris Creek | 1.9% | Doris Creek Project, Second Annual Report E38/542, August 1995 |
| A47328 | 1995 | Sons Of Gwalia Ltd | Amy Clarke | 3% | Amy Clarke (JV) Project, Annual report for the period 1 December 1994 to 30 November 1995 E38/496 E38/566 E38 |
| A42598 | 1994 | Central Kalgoorlie Gold Mines Nl | Doris Creek | 1.9% | Doris Creek Project, (1st) Annual Report for the period 25th August 1993 to 24th August 1994, E38/542. |
| A43247 | 1994 | Sons Of Gwalia Ltd | Laverton | <1% | Laverton Region North Eastern Goldfields Baneygo Project Interim Report to 23 September 1994 Tenements:E38/545 |
| A40894 | 1994 | Aurora Gold Ltd | Mistake Well | 1% | Mistake Well Project, Partial Surrender Report for the period 26th November 1990 to 25th November 1993, E38/38 |
| A43882 | 1994 | Sons Of Gwalia Ltd | Swincer | <1% | Swincer Project, Annual Report for the period 1 January 1994 - 31 December 1994,E38/520-521, P38/2518-2519. |
| A38735 | 1993 | Ashton Gold Wa Ltd | Hack Well | <1% | Annual Technical Report H475 Hack Well Project E38/85, M38/114, M38/283, M38/292, M38/303, M38/316, M38/317, M |
| A40943 | 1993 | Aurora Gold Ltd | Hack Well | <1% | H475 Hack Well Project Western Australia Annual Technical` Report for the period 01 January 1993 to 31st Decem |
| A35628 | 1992 | Ashton Gold Wa Ltd | Hack Well | <1% | Annual Technical Report Hack Well Project E38/25, M38/114, M38/283, M38/291 to M38/293, M38/302 to M38/307, M3 |
| A38411 | 1992 | Ashton Gold Wa Ltd | Mistake | 1% | Annual Report for the period 01/01/92-31/12/92, Mistake Project, E38/384. |
| A35638 | 1992 | Ashton Gold Wa Ltd | Paillard Find | 13% | Paillard Find Project, Final Surrender Report for the period 23rd March 1987 to 31st December 1991, M38/77 & 7 |
| A35652 | 1992 | Ashton Gold Wa Ltd | Kirkpatrick | 2.3% | Kirkpatrick project, Annual Report for the period 1st January 1991 to 31st December 1991, M38/315, 322 - 324. |
| A36693 | 1992 | Ashton Gold Wa Ltd | Mistake | 1% | Annual Report for the Period 01/01/91 - 31/12/91, Mistake Project ,E38/384. |
| A38412 | 1992 | Ashton Gold Wa Ltd | Kirkpatrick | 2.3% | Kirkpatrick Project, Annual Report for the period 1st January 1992 to 31st December 1992, P38/1892-1900; M38/3 |
| A33666 | 1991 | Ashton Gold Wa Ltd | Paillard Find | 7.6% | Annual Technical Report H548 Paillard Find Project. M38/77-78,120,262 for the period 01/01/90-31/12/90. |
| A33672 | 1991 | Ashton Gold Mines Pty Ltd | King of Creation | <1% | King of Creation Project, Annual Report for the period 01/01/1990 to 31/12/1990, L38/160 M38/160. |
| A35644 | 1991 | Ashton Gold Wa Ltd | Paillard Find | 13% | Annual Report for the Period 01/01/91 - 31/12/91 Paillard Find Project M38/77,78,262 |
| A35687 | 1991 | Ashton Gold Wa Ltd | KIng of Creation | <1% | KIng of Creation Project, Annual Report for the period 01/01/1991 to 31/12/1991, M38/160. |
| A15925 | 1990 | Ashton Gold Mines Pty Ltd | King of Creation | <1% | King of Creation Project, Annual Report for the period 1st January 1989 to 31st December 1989, M38/160; L38/18 |
| A30493 | 1990 | Ashton Gold Mines Pty Ltd | Paillard Find | 7.6% | Annual Technical Report, Paillard Find Project Mining Leases M38/77,M38/78, M38/120 and M38/262 25 Jan 1989 to |
| A27534 | 1989 | Cesium International Pty Ltd | Bird | 41% | Bird Project, Annual [Progress] Report, March 1989, GML38/3051.[ Esmeralda- Red Rock JV] |
| A27734 | 1989 | Hillmin Gold Mines Pty Ltd | King of Creation | <1% | King of Creation Project, Annual Report for the period 1st January 1988 to 31st December 1988, M38/160. |
| A23486 | 1988 | Julia Mines Nl | Little Doris | 20% | Little Doris Prospect, Annual report 1987-1988, M38/78 |
| A26202 | 1988 | Bp Minerals Aust Pty Ltd | Paillards | 12% | Paillards Project, Final Report, P38/328-331, P38/1116, M38/115. |
| A24059 | 1988 | Esmeralda Exploration Ltd | Bird | 41% | Bird Gold Prospect, Annual report for period 1 January 1987 to 31 December 1987, GML38/3051 |
| A21841 | 1987 | Technomin Australia Nl | Little Doris | 20% | Little Doris Project, Annual Report for the period ending 6th October 1986, P38/21. |
| A15007 | 1985 | Mr Whitfield Gb | Bird | 41% | Bird Project, Annual Report for the period ending 31/12/1984, GML38/3051. |
| A17627 | 1985 | Delta Gold Ltd | Little Doris | 20% | Little Doris Project, Annual Report for the period ending 05/10/1985, P38/21. |
| A17828 | 1985 | Esmeralda Exploration Ltd | Bird | 41% | Bird, GML38/3051, Non-Statutory Report on 1985. |
| A13241 | 1984 | Mr Whitfield Gb | Bird | 41% | Bird Project, Annual Report for the period ending 31/12/1983, GML38/38/3051. |
| A14256 | 1984 | Delta Gold Ltd | Little Doris | 20% | Little Doris Project, Annual Report 1983/1984 for the period ending 05/10/1984, P38/21. |
| A12463 | 1982 | Mr Whitfield Gb | Bird | 41% | Bird Project, Annual Report for the period ending 31st December 1982, GML38/3051. |
| A2706 | 1981 | Cominco Exploration Pty Ltd | Erlistoun - Baneygo | <1% | Erlistoun - Baneygo Project, Non-statutory Report:Exploration Report , Miscellaneous Maps & Plans, November 19 |
| A5315 | 1974 | Poseidon Ltd | Mount Clarke | 12% | Mount Clarke Project, Non-statutory Report,01/01/1973 to18/06/1974, MC38/926-937. |
| A5359 | 1974 | Samin Ltd | Laverton | 4.1% | Laverton, Exploration report [non-statutory], For period 1st January 1973 - 18th June 1974, MC38/673 ... 38/63 |
| A6945 | 1973 | Kennecott Exp Aust Pty Ltd | Erlistoun | <1% | Aeromag- Raw Data |
| A9160 | 1973 | Cominco Exploration Pty Ltd | Erlistoun - Baneygo | 2.3% | Erlistoun - Baneygo Project, Annual Report for the period 0101/1972 to 15/10/1973, MC38/5299-5301, 5312, 5927- |
| A2470 | 1972 | Cominco Exploration Pty Ltd | Erlistoun - Baneygo | <1% | Erlistoun - Baneygo Project, Non-statutory Report: Final Report, April 1972, TR70/3813, 4490 & 4492H. |
| A2694 | 1972 | Cominco Exploration Pty Ltd | Erlistoun -Baneygo | <1% | Erlistoun - Baneygo Project, Final Surrender Report for the period ending 09/02/1972, TR70/3813H. |
| A3201 | 1972 | Poseidon Nl | Laverton | 2.3% | Laverton (JV) Project, Non-statutory Report: Exploration Report for the period ending December 1972, MC38/ 3 |
| A9159 | 1972 | Cominco Exploration Pty Ltd | Erlistoun- Baneygo | <1% | Erlistoun-Baneygo Project, Non-statutory Report:Exploration Report for the period 01/01/1971 to 31/12/1971, TR |
| A9156 | 1971 | Cominco Exploration Pty Ltd | Erlistoun - Baneygo | <1% | Erlistoun - Baneygo (JV) Project, Non-statutory Report:Progress Report for the period 31st May 1970 to 1st Ja |
| A2707 | 1971 | Cominco Exploration Pty Ltd | Erlistoun - Baneygo | <1% | Erlistoun - Baneygo Project, Non-statutory Report: Miscellaneous Plans (25) for Baneygo-King of Creation, for |
| A9157 | 1971 | Cominco Exploration Pty Ltd | Erlistoun - Baneygo | <1% | Erlistoun - Baneygo Project, Annual Report for the period 01/01/1970 to 31/12/1970, TR70/3813; MC38/3917...... |
| A9158 | 1971 | Cominco Exploration Pty Ltd | Erlistoun - Baneygo | <1% | Erlistoun-Baneygo (JV) Project, Non-statutory Report, Progress Report for the period 01/01/1971 to 30/06/1971, |
| A1118 | 1969 | Cominco Exploration Pty Ltd | Erlistoun-Baneygo | <1% | Erlistoun-Baneygo Project, Non-statutory Report: Quarterly Report for the period ending 30th June 1969, TR70/3 |
| A1112 | 1968 | Cominco Exploration Pty Ltd | Erlistoun-Baneygo | <1% | Erlistoun-Baneygo Project, Non-statutory Report: Report on the Induced Polarization & Resistivity Survey on Th |
| A1113 | 1968 | Cominco Exploration Pty Ltd | Erlistoun-Baneygo | <1% | Erlistoun-Baneygo Project, Non-statutory Report: Geological & Geochemical Maps & Magnetic Anomalies, December |
| A1114 | 1968 | Cominco Exploration Pty Ltd | Erlistoun | <1% | Erlistoun Project, Non-statutory Report: A Review of Activities to March 21st 1968, TR70/ 3813, 3899, 4490-449 |
| A1115 | 1968 | Cominco Exploration Pty Ltd | Erlistoun-Baneygo | <1% | Erlistoun-Baneygo Project, Non-statutory Report: Quarterly Report for the period ending 30th June 1968, TR70/3 |
| A1110 | 1967 | Cominco Exploration Pty Ltd | Erlistoun-Baneygo | <1% | Erlistoun-Baneygo Project, Non-statutory Report Progress Report for the period 01/09/1966 to 31/03/1967, TR70/ |
| A1111 | 1967 | Cominco Exploration Pty Ltd | Erlistoun-Baneygo | <1% | Erlistoun-Baneygo Project, Non-statutory Report: Geological & Geochemical Maps, December 1966 to April 1967,TR |
| A1117 | 1753 | Cominco Exploration Pty Ltd | Erlistoun-Baneygo | <1% | Erlistoun-Baneygo Project: |
| A1119 | 1753 | Cominco Exploration Pty Ltd | Erlistoun-Baneygo | <1% | Erlistoun-Baneygo Project, Non-statutory Report: |
| A1120 | 1753 | Cominco Exploration Pty Ltd | Erlistoun-Baneygo | <1% | Erlistoun-Baneygo Project, Annual Report for the period ending 30th June 1970, TR70/3813, 4490 & 4492H |
| A12355 | 1753 | Chevron Exploration Corp | Erlistoun base | <1% | Erlistoun, MC38/8064-38/8096 Inc. MC38/8244, EL 38/9. Annual Report. November 1981-December 1982 |
| A14502 | 1753 | Chevron Exploration Corp | Erlistoun base | <1% | Chevron Exploration Corporation Annual Report - MC 38/8096 Terminal Report- EL 38/9 and MC 38/8224 Mt Margaret |
| A38751 | 1753 | Inco Australia Ltd | Eastern Goldfields regional mapping | <1% | Eastern Goldfields regional mapping |
| A51107 | 1753 | Johnsons Well Mining Nl | Duketon Belt/Erlistoun | <1% | Exploration Licences E38/379 E38/565 Mining Leases M38/114 M38/262 M38/283 M38/292 M38/303 M38/316 M38/317 M38 |
What does the exploration record say about this ground?
NextMaps reads the WAMEX reports over L 38/365 into a referenced prospectivity assessment: the geology, the historical programs, the drill intercepts and geochemistry, and the untested gaps, with every claim cited back to its source report. New accounts include a free report (how the reports work). Prefer the raw due diligence? A Tenure Pack bundles the full register record, tenure history and spatial datasets for this ground.
Get the free report Full register record on the mapDo you hold L 38/365? Listing is free. A facilitation fee applies only if the ground ends up with a buyer we introduce.
List this tenementTenure data sourced from the DMPE public registers and SLIP WA (© Government of Western Australia, CC BY 4.0), as at 2026-10-09. Compiled by NextMaps. Verify against primary sources before reliance.