M 37/439
M 37/439 is a live mining lease in the Shire of Leonora, Western Australia, held by Round Oak Jaguar Project Pty Ltd (part of Aeris Resources Limited). Granted on 27 Apr 1994 for 21 years (renewed), it expires on 26 Apr 2036. The ground is covered by 91 historical WAMEX reports.
Register summary
- Holder
- Round Oak Jaguar Project Pty Ltd
- Part of
- Aeris Resources Limited (ASX:AIS) as at 2026-06-30
- Local government
- Shire of Leonora
- Application received
- 1 Dec 1993
- Commenced
- 27 Apr 1994
- Expiry
- 26 Apr 2036
- Term
- 21 Years (Renewed)
The full record on M 37/439
The register summary says who holds it today. The rest of the record says how they came to, what is attached to it, and whether it is being worked.
- Current holders and their shares, and all 6 changes of holder
- The full record: 33 years of expenditure, 10 conditions and 1 endorsement
- Native title context, combined reporting and rent status
- At-risk and opportunity signals, and expenditure compliance over five years
- Every register dealing (24 on record), with mortgages, caveats and transfers flagged
- Expiry band, and how long the holder has had it
Exploration history on this ground
| Report | Year | Operator | Project | On this ground | Title |
|---|---|---|---|---|---|
| A131139 | 2022 | Xplore Resources Pty Ltd | Weebo | <1% | Annual Combined Report C63/2017 for Exploration Activity - Weebo Project Period Ending 31 March 2022 |
| A127402 | 2021 | Xplore Resources Pty Ltd | Weebo | <1% | Annual Combined Report C63/2017 for Exploration Activity- Weebo Project Period Ending 31 March 2021 |
| A123220 | 2020 | Round Oak Jaguar Pty Ltd; Round Oak Jaguar Project Pty Ltd | Teutonic Bore Project | 1.8% | Combined Annual Report 2019 Teutonic Bore Project C/157/2002 for the period 1 January 2019 to 31 December 2019 |
| A124119 | 2020 | Tyranna Resources Limited | Weebo | <1% | Combined Annual Technical Report C63/2017 (Weebo) for the period ending 31/03/2020 |
| A125691 | 2020 | St Barbara Limited | Gwalia | <1% | Gwalia Project Combined Reporting Group C55/2004 - Annual Report for the Period 1 October 2019 to 30 September |
86 more reports
| A122153 | 2019 | St Barbara Limited | Gwalia | <1% | Gwalia Project Combined Reporting Group C55/2004 - Annual Report for the Period 1 October 2018 to 30 September |
| A119556 | 2019 | Round Oak Jaguar Project Pty Ltd; Round Oak Jaguar Pty Ltd | Teutonic Bore | 1.8% | C157/2002 Combined Annual Report for Teutonic Bore Project for the period 1 January 2018 to 31 December 2018 |
| A119854 | 2019 | Tyranna Resources Ltd | Weebo | <1% | C63/2017 Combined Annual Technical Report For the Period 1 April 2018 to 31 March 2019, E36/00880, E37/01275, |
| A115994 | 2018 | Independence Group Nl | Teutonic Bore | 1.8% | Combined Annual Report C157/2002 Teutonic Bore Project for the period from 1st January 2017 to 31st December 2 |
| A116925 | 2018 | Independence Group Nl | Jaguar | <1% | Final Surrender Report for Tenement E37/677 Jaguar Project for the period 26 June 2006 to 5 April 2018 |
| A118601 | 2018 | St Barbara Limited | Gwalia | <1% | Gwalia Project Combined Reporting Group C55/2004 - Annual Report for the Period 1 October 2017 to 30 September |
| A112037 | 2017 | Independence Group Nl | Teutonic Bore | 1.7% | Combined Annual Report on C157/2002 Teutonic Bore Project for the period 1 January 2016 to 31 December 2016 |
| A115512 | 2017 | St Barbara Limited | Gwalia | <1% | Gwalia Project Combined Reporting Group C55/2004 - Annual Report for the Period 1 October 2016 to 30 September |
| A107988 | 2016 | St Barbara Limited | Wilson Creek | 1.4% | Final Surrender Report E37/740 Wilson Creek Project for the period 08/06/2006 to 10/11/2015 |
| A110551 | 2016 | St Barbara Limited | Gwalia | <1% | Gwalia Project Combined Reporting Group C55/2004 - Annual Report for the Period 1 October 2015 to 30 September |
| A107737 | 2016 | Independence Group Nl | Teutonic Bore | 1.7% | Combined Annual Report on C157/2002, Teutonic Bore Project, for the period 1 January 2015 to 31 December 2015 |
| A105579 | 2015 | St Barbara Ltd | Leonora | <1% | Annual Mineral Exploration Report - DMP Combined Reporting Group C162/2006 (Leonora) Reporting Period 1 April |
| A105028 | 2015 | Independence Group Nl | Teutonic Bore | 2.1% | Combined Annual Report on C157/2002, Teutonic Bore Project, for the period 1 January 2014 to 31 December 2014, |
| A107603 | 2015 | St Barbara Limited | Gwalia | <1% | Gwalia Project C55/2004 Combined Annual Report for the Period 1 October 2014 to 30 September 2015 |
| A101281 | 2014 | Independence Group Nl | Teutonic Bore | 1.8% | Combined Annual Report on C157/2002, Teutonic Bore Project, for the period 1 January 2013 to 31 December 2013, |
| A102258 | 2014 | St Barbara Ltd | Leonora | <1% | Annual Mineral Exploration Report - DMP Combined Reporting Group C162/2006 (Leonora) Reporting Period 1 April |
| A98017 | 2013 | St Barbara Ltd | Leonora | <1% | Leonora Project, Annual Report for the period 1st April 2012 to 31st March 2013, E37/670.......E37/964; M36/41 |
| A97747 | 2013 | Independence Group Nl | Teutonic Bore | 1.8% | Combined Annual Report on C157/2002, Teutonic Bore Project, for the period 1 January 2012 to 31 December 2012, |
| A98608 | 2013 | Independence Group Nl | Teutonic Bore | 1.8% | Teutonic Bore Project, Annual Report for the period 1st January 2012 to 31st December 2012, E37/258........E37 |
| A93822 | 2012 | St Barbara Ltd | Leonora | <1% | Leonora C162/2006 Annual Report for the Period 1 April 2011 to 31 March 2012 |
| A93519 | 2012 | Jabiru Metals Ltd | Teutonic Bore | 1.8% | Teutonic Bore Project Combined Annual Report C157/2002 for the period 1st January 2011 to 31st December 2011 |
| A89792 | 2011 | Jabiru Metals Ltd | Teutonic Bore | 1.3% | Teutonic Bore Project Combined Annual Report C157/2002 for the period 1st January 2010 to 31st December 2010 |
| A90352 | 2011 | St Barbara Ltd | Leonora | 1.2% | Leonora Project, Annual Report for the period 1st April 2010 to 31st March 2011, Tenements as per Combined Rep |
| A85496 | 2010 | St Barbara Ltd | McEast | 13% | McEast C162/2006 E37/496, Partial Surrender Report for the Period 22 September 2005 to 21 September 2009 |
| A87123 | 2010 | St Barbara Ltd | Leonora | 1.2% | Annual Report for the Period 1 April 2009 to 31 March 2010, Leonora, C162/2006, E37/235, E37/496, E37/573, E37 |
| A88117 | 2010 | St Barbara Ltd | Wilson Creek | 1.4% | Partial Surrender Report for the Period 2 June 2006 to 31 August 2010 |
| A84566 | 2009 | St Barbara Ltd | Wilson Creek | <1% | Wilson Creek E37/677 Partial Surrender Report for the Period 26 June 2006 to 6 July 2009 |
| A78149 | 2008 | Jabiru Metals Ltd | Teutonic Bore | <1% | COMBINED ANNUAL REPORT, E37/512, E37/258, E37/319, M37/44, M37/515, M37/1132, M37/1153, P37/4326, P37/6794-P37 |
| A78842 | 2008 | St Barbara Ltd | Leonora | 1.7% | LEONORA PROJECT ANNUAL REPORT FOR THE PERIOD 1 APRIL 2007 - 31 MARCH 2008 GROUP: C162/2006 E37/235, E37/236, E |
| A79282 | 2008 | Bathurst Resources Ltd | Mount Clifford | 1.4% | Mount Clifford Project Annual Report E37/740 8th June 2007-7th June 2008 |
| A80228 | 2008 | Montezuma Mining Company Ltd | WEEBO | <1% | Annual Report on E37/802, WEEBO PROJECT, For the Period 23 November 2007 to 22 November 2008 |
| A74019 | 2007 | St Barbara Ltd | Cambrian | 1.7% | Cambrian Project E37/281, Surrender Report for the Period 29 January 1993 to 28 September 2006, (St Barbara Re |
| A75283 | 2007 | St Barbara Ltd | Leonora | 2.1% | Leonora Project, Annual Report for the Period 1 April 2006 - 31 March 2007, C162/2006.(Report No.0051-2007-02) |
| A75604 | 2007 | Cazaly Resources Ltd | Mount Clifford | 1.4% | Annual Report E37/0740 Mount Clifford Project For the period 8 June 2006 to 7 June 2007 |
| A77253 | 2007 | Montezuma Mining Company Ltd | Weebo | <1% | Annual Report on E37/802, WEEBO PROJECT, For the Period 23 November 2006 to 22 November 2007 |
| A74695 | 2007 | Jabiru Metals Ltd | Teutonic Bore | <1% | Combined Annual Report Teutonic Bore Project C157/2002 From 18 January 2006 to 17 January 2007 |
| A72988 | 2006 | St Barbara Mines Ltd | McEast - Robinsons | 3% | McEast / Robinsons Project, Annual Report for the Period 1 July 2005 to 30 June 2006, Combined Reporting No. C |
| A70216 | 2005 | Newmont Australia Ltd | Heather Bore | <1% | Annual report for the period 08/02/04 - 07/02/05 Heather Bore Project, E37/319, Leonora, Report number 31817 |
| A68376 | 2004 | Newmont Yandal Operations Ltd | Heather Bore | <1% | Annual Report for the period 08/02/2003-07/02/2004 Heather Bore Project E37/319 |
| A68561 | 2004 | Sons Of Gwalia Ltd | Wilson Creek | 23% | Wilson Creek Project, Annual report for the period 1 April 2003 to 30 June 2003, (C115/1999), M37/438-440, M37 |
| A68604 | 2004 | Gutnick Resources Nl | Teutonic Bore | 1.3% | Joint Surrender Report for the Period 19 October 2000 to 21 March 2003 (C68/2002) - Teutonic Bore E37/602, E37 |
| A68976 | 2004 | Sons Of Gwalia Ltd | McEast-Robinsons | 3.7% | McEast/Robinsons project, annual report for the period 5 June 2003 - 30 June 2004 |
| A65855 | 2003 | Sons Of Gwalia Ltd | Cambrian | <1% | Annual Report for period 05/06/01 to 04/06/02, C327/1995, Cambrian JV Project , E37/236, E37/281, E37/294, M3 |
| A65856 | 2003 | Sons Of Gwalia Ltd | Wilson Creek | 11% | Annual Report for period 01/04/01 to 31/03/02 Wilson Creek Project Area E36/306, P36/1246-1248, M37/437-440, M |
| A66101 | 2003 | Newmont Australia Ltd | Heather Bore | <1% | Annual Report for the period 01/01/2002 to 31/12/2002 Heather Bore Project,C72/2001 E37/319, 553, 556. |
| A66608 | 2003 | Sons Of Gwalia Ltd | Wilson Creek | 23% | Wilson Creek Project , Annual Report for the period 1 April 2002-31 March 2003, Group C115/1999, M37/438-40, 4 |
| A66925 | 2003 | Sons Of Gwalia Ltd | Cambrian | <1% | CAMBRIAN PROJECT ANNUAL REPORT FOR THE PERIOD 5 JUNE 2002 – 4 JUNE 2003 C327/1995, M37/479, E37/236,281,294, |
| A67765 | 2003 | Pacmin Mining Corporation Ltd | Cambrian | <1% | Annual Report for the period 05/06/1999- 04/06/2000 Cambrian Project C327/1995, E37/236, E37/281, E37/294, E37 |
| A64410 | 2002 | Newmont Yandal Operations Ltd | Heather Bore | <1% | Annual Report form the period 1/01/2001 To 31/12/2001. Project Heather Bore E37/319 E37/553 E37/556. |
| A62593 | 2001 | Normandy Yandal Operations Ltd | Heather Bore | <1% | Annual Report On Exploration For Period 7/02/2000 To 6/02/2001. Project Heather Bore E37/319. |
| A63374 | 2001 | Pacmin Mining Corporation Ltd | Wilson Creek | 8.6% | 2000/01 Annual Report Wilson Creek Project Area E36/306, P36/1246-1248, E37/261, M37/437-440, M37/493-495, P37 |
| A63376 | 2001 | Pacmin Mining Corporation Ltd | Cambrian | <1% | 2000/2001 Annual Report Cambrian Project Area - E37/236, E37 /281, E37/294, E37/492, M37/479, P37/4402, P37/44 |
| A59560 | 2000 | Pacmin Mining Corporation Ltd | Wilson Creek | 5.7% | 1998/99 Annual Report, Wilson Creek Project Area, E36/306, E37/183, E37/200, E37/261, E37/412, M37/403, M37/40 |
| A60957 | 2000 | Pacmin Mining Corporation Ltd | Wilson Creek | 8.9% | 1999/2000 Annual Report, Wilson Creek Project Area, E36/ 306, E37/261,M37/437-440,493-495, P37//5159, Combine |
| A57477 | 1999 | Pacific Mining Corporation Ltd | Cambrian | <1% | Annual Report for Cambrian Project for the period ending 04/06/98. E37/236,281,294,409. M37/479. P37/4402,4434 |
| A59344 | 1999 | Pacmin Mining Corporation Ltd | Cambrian | <1% | Cambrian Project, Annual Report for the period 05/06/1998 to 04/06/1999, E37/236,E37/281,E37/294,E37/409,M37/ |
| A54141 | 1998 | Great Central Mines Ltd | Clilfford Bore - Heather Bore | <1% | Exploration Licence E37/319 'Clifford Bore' (Heather Bore Project) Annual report for the period 07/02/97-06/02 |
| A55964 | 1998 | Pacific Mining Corporation Ltd | Wilson Creek | 8.7% | The Wilson Creek Project Area, Mt Margaret Mineral Field, W.A. 01/06/97 - 31/05/98 E36/306, E37/183, (MLA37/4 |
| A50583 | 1997 | Goldfields Exploration Pty Ltd | Teutonic Bore | 6% | Teutonic Bore Project, Final Report Exploration Licence E37/247 for the period 18th December 1991 to 17th Dece |
| A50936 | 1997 | Goldfields Exploration Pty Ltd | Teutonic Bore | 1.2% | Annual Report Teutonic Bore JV E37/247 E37/258 E37/353 E37/373 to E37/375 P37/4326 M37/44 MLA37/515 Technical |
| A52220 | 1997 | Mt Edon Gold Mines Aust Ltd | Wilson Creek | 5.7% | Annual report on the Exploration of the Wilson Creek Project area E37/183 E37/261 E36/306 P37/5117 P37/5118 P3 |
| A49707 | 1996 | Mt Edon Gold Mines Aust Ltd | Leonora | <1% | Leonora Project ( Cambrian JV Tenements) Annual Report for the period ending June 30th 1996, E37/236, 281, 294 |
| A47244 | 1996 | Goldfields Exploration Pty Ltd | Teutonic Bore | 1.2% | Annual report Teutonic Bore JV E37/247 E37/258 E37/282 E37/353 E37/373 to E37/375 P37/4326 M37/44 MLA37/515 Te |
| A49404 | 1996 | Mt Edon Gold Mines Aust Ltd | Wilson Creek | 2% | Annual report on Exploration of the Wilson Creek Project area West E37/183 M37/493 to M37/495 E37/200 E37/261 |
| A44162 | 1995 | Pancontinental Gold Operations Pty Ltd | Teutonic Bore | 1.3% | Teutonic Bore Project, Annual Report for the period ending 17th January 1995, E37/247 E37/258 & E37/282; M37/ |
| A48976 | 1995 | Mt Edon Gold Mines Aust Ltd | Cambrian | <1% | Cambrian (JV) Project, E37/236 E37/281 E37/294 M37/479 P37/4402 P37/4434 and P37/4988, for the period ending J |
| A43995 | 1995 | Mt Edon Gold Mines Aust Ltd | Leonora | 1.7% | Leonora Project, Annual Report for the period ending January 28, 1995, E37/281. |
| A46039 | 1995 | Mt Edon Gold Mines Aust Ltd | Wilson Creek | 4% | Annual report on the Exploration of the Wilson Creek Project area P37/3917 to P37/3920 P37/3870 to P37/3873 P3 |
| A41263 | 1994 | Mt Edon Gold Mines Nl | Cambrian | 1.7% | Annual Reprt for the period 28/01/94 - 28/01/95 Tenements E37/281 Mt Margaret Mineral Field WA (Cambrian Proje |
| A42934 | 1994 | Mt Edon Gold Mines Nl | Wilson Creek | 4% | Annual report on the Exploration of the Wilson Creek Project area P37/3917 to P37/3920 P37/3870 to P37/3873 P3 |
| A37726 | 1993 | Mt Edon Gold Mines Nl | Wilson Creek | 15% | Annual Report for the period ending 1992 ,Wilson Creek Project, E37/183. |
| A40253 | 1993 | Mim Exploration Pty Ltd | Junior Hill | 6% | Junior Hill Project, Annual Report for the year ending 17th December 1993, E37/247. |
| A38799 | 1993 | Mt Edon Gold Mines Nl | Wilson Creek | 4% | Annual Report for the period 06/92-05/93 Wilson Creek Project |
| A37540 | 1992 | Mim Exploration Pty Ltd | Junior Hill | 6% | Junior Hill Project, Annual Report for the year ending December 17th 1992, E37/247. |
| A37727 | 1992 | Mt Edon Gold Mines Nl | Wilson Creek | 15% | Wilson Creek Project, Partial Surrender Report, December 1992, E37/183. |
| A34674 | 1991 | Mt Edon Gold Mines Nl | Wilson Creek | 8.2% | Wilson Creek Project, Annual Report for the period 01/10/1990 to 01/10/1991, E37/183 & 200. |
| A32411 | 1990 | Mt Edon Gold Mines Nl | Wilson Creek | 8.2% | Wilson Creek Prospect,(3710) Annual Report 1990 (E37/183) |
| A20565 | 1987 | Chevron Exploration Corp | Smith Bore | 38% | M37/78, Smith Bore, Relinquishment [final surrender] report,To February 9 1987 |
| A10299 | 1981 | Seltrust Mining Corp Pty Ltd | Teutonic Bore | 3.7% | Teutonic Bore Project, Non-statutory Report: Report for the period 1st January 1979 to 31st December 1980, MC3 |
| A21875 | 1978 | Australian Selection Pty Ltd | Teutonic Bore | 3.4% | Teutonic Bore (JV) Project, Non-statutory Report: Progress Report for the period ending 31/12/1978, MC37/4648- |
| A7295 | 1977 | Australian Selection Pty Ltd | Teutonic Bore | 2.3% | Teutonic Bore (JV) Project, Non-statutory Report: Progress Report to 30th September 1977, (Vol 1), MC37/4648-4 |
| A6285 | 1976 | Cra Exploration Pty Ltd | Smith's Bore | 18% | Smith's Bore Project, Annual Report for the year ending 31/12/1975, MC37/4736-4752 & 5069. |
| A5725 | 1975 | Cra Exploration Pty Ltd | Smith's Bore | 18% | 1974 Annual report of MC37/4736 to 37/4752, Smith's Bore prospect, 10th March 1975 |
| A84016 | 1753 | St Barbara Ltd | WILSON CREEK | 1.4% | WILSON CREEK PROJECT - PARTIAL SURRENDER REPORT FOR THE PERIOD, 8 JUNE 2006 – 7 JUNE 2009 |
| A38751 | 1753 | Inco Australia Ltd | Eastern Goldfields regional mapping | <1% | Eastern Goldfields regional mapping |
| A82836 | 1753 | St Barbara Ltd | Leonora | 1.5% | LEONORA PROJECT ANNUAL REPORT FOR THE PERIOD 1 APRIL 2008 – 31 MARCH 2009 GROUP: C162/2006 TENEMENTS: E37/235, |
What does the exploration record say about this ground?
NextMaps reads the WAMEX reports over M 37/439 into a referenced prospectivity assessment: the geology, the historical programs, the drill intercepts and geochemistry, and the untested gaps, with every claim cited back to its source report. New accounts include a free report (how the reports work). Prefer the raw due diligence? A Tenure Pack bundles the full register record, tenure history and spatial datasets for this ground.