M 39/1204
M 39/1204 is a pending mining lease in the Shire of Leonora, Western Australia, applied for by Matsa Gold Pty Ltd (part of Matsa Resources Limited). The application was received on 30 Jan 2026 and is awaiting a decision. The ground is covered by 151 historical WAMEX reports.
Register summary
- Holder
- Matsa Gold Pty Ltd
- Part of
- Matsa Resources Limited (ASX:MAT) as at 2025-06-30
- Local government
- Shire of Leonora
- Application received
- 30 Jan 2026
The full record on M 39/1204
The register summary says who has applied for it. The rest of the record says what is attached to the application and how it is progressing.
- Current holders and their shares (no change of holder on record)
- Expenditure history, conditions and endorsements
- Native title context, combined reporting and rent status
- Expenditure compliance, expiry and ownership signals, once the application is granted
- Every register dealing (1 on record), with mortgages, caveats and transfers flagged
Exploration history on this ground
| Report | Year | Operator | Project | On this ground | Title |
|---|---|---|---|---|---|
| A125097 | 2020 | Matsa Gold Pty Ltd | Arrow | <1% | Arrow Prospect Annual Report P39/06117 for the period 9 August 2019 to 8 August 2020 |
| A125098 | 2020 | Matsa Gold Pty Ltd | Arrow | <1% | Indigo North Annual Report P39/6116 for the period 9 August 2019 to 8 August 2020 |
| A123688 | 2020 | Matsa Gold Pty Ltd | Lake Carey | <1% | Compulsory Partial Surrender Report of E39/1752, Lake Carey, 6 February 2014 to 4 February 2020 |
| A124881 | 2020 | Anova Metals Australia Pty Ltd | Linden | <1% | Combined Annual Report Linden Project C37/2009 for the period ending 05/07/2020 |
| A122827 | 2020 | Matsa Resources Limited | Red October | 3.7% | Red October Group Annual Report C173/2017 for the period ending 31/12/2019 |
146 more reports
| A123153 | 2020 | Matsa Gold Pty Ltd | Lake Carey | <1% | Combined Annual Report C5/2003, Lake Carey Project, 1 January 2019 to 31 December 2019 |
| A119197 | 2019 | Matsa Gold Pty Ltd | Lake Carey | <1% | Lake Carey Project C5/2003 Annual Report for the period 1 January 2018 to 31 December 2018 |
| A119510 | 2019 | Matsa Resources Limited | Red October | 3.5% | Annual Report on Exploration Carried out over Red October Project (C173/2017) for period to 1st March 2019 |
| A121504 | 2019 | Anova Metals Australia Pty Ltd | Linden | <1% | Surrender Report Linden E39/1754 for the period 12 March 2014 to 22 July 2019 |
| A119387 | 2019 | Gme Resources Ltd | Devon Olympic - New Years Gift | <1% | Annual Report for Devon Olympic and New Years Gift Projects C39/2014 for the period 1 January 2018 to 31 Decem |
| A121020 | 2019 | Anova Metals Australia Pty Ltd | Linden | <1% | Combined Annual Report-Linden Project-C37/2009 For the Period 6 July 2018 to 5 July 2019, E39/01539, E39/01977 |
| A116266 | 2018 | Matsa Gold Pty Ltd | Lake Carey | <1% | Lake Carey Project C5/2003 Annual Report for the period 01/01/2017 - 31/12/2017 |
| A116355 | 2018 | Gme Resources Ltd | Devon Olympic - New Years Gift | <1% | Annual Report for Devon Oympic and New Years Gift C39/2014 For the Period 1 January 2017 to 31 December 2017, |
| A117439 | 2018 | Anova Metals Australia Pty Ltd | Linden | 16% | Combined Annual Report-Linden Project-C37/2009 for the period 6 July 2017 to 5 July 2018, E39/01232, E39/01539 |
| A115708 | 2018 | Anova Metals Australia Pty Ltd | Linden | 89% | Final Surrender Report - M39/0780 Linden Project for the period 24/08/2010 - 09/10/2017 |
| A115709 | 2018 | Anova Metals Australia Pty Ltd | Linden | 59% | Final Surrender Report - M39/0781 Linden Project for the period 24/08/2010 - 09/10/2018 |
| A115990 | 2018 | Saracen Gold Mines Pty Limited | Red October | <1% | Red October Project (C173/2017) Annual Report for the Period 1 January to 31 December 2017, M 39/00411, M39/00 |
| A112338 | 2017 | Gme Resources Ltd | Linden | <1% | Annual Report Linden Reporting Group, Devon, Olympic and New Years Gift C39/2014 For the Period 1 January 2016 |
| A112356 | 2017 | Saracen Gold Mines Pty Ltd | Butcher Well | <1% | Butcher Well Project (C8/2016) – Volume II Annual Report for the Period 1 January to 31 December 2016, E39/014 |
| A112275 | 2017 | Matsa Resources Limited | Lake Carey | <1% | Lake Carey Project C05/2003 Annual Report for the period 1 January 2015 to 31 December 2016, E39/01287.....E39 |
| A114643 | 2017 | Exterra Resources Limited | Linden | 16% | C37/2009 Linden Project Combined Annual Report for the period 6 July 2016 to 5 July 2017, E39/01232, E39/01539 |
| A108476 | 2016 | Gme Resources Ltd | Linden | <1% | Annual Report Linden Project C39/2014 1 January 2015 to 31 December 2015 |
| A108808 | 2016 | Fortitude Gold Pty Ltd | Lake Carey | <1% | LAKE CAREY PROJECT Annual Report To The WA Department of Mines & Petroleum For The Period 1st January 2015 to |
| A108161 | 2016 | Saracen Gold Mines Pty Ltd | Butcher Well - Mount Minnie- Mount Flore | <1% | VOL 1 - Butcher Well Project (C345/1993) Annual Report for the Period 1 January 2015 to the 31 December 2015, |
| A109747 | 2016 | Exterra Resources Limited | Linden Project | 16% | Linden Project Annual Report on C37/2009, 6 July 2015 to 5 July 2016 |
| A105466 | 2015 | Saracen Gold Mines Pty Ltd | Butcher Well | <1% | Butcher Well Project C345/1993 Annual Report for the period 01/01/2014 - 31/12/2015, E38/2306.....P39/5063 |
| A105184 | 2015 | Gme Resources Ltd | Devon | <1% | Devon Project M39/1077 & M39/1078 Annual Report for the period 1st January 2014 to 31st December 2014 (C39/201 |
| A105191 | 2015 | Fortitude Gold Pty Ltd | Lake Carey | <1% | Annual Technical and Geological Report for Department of Mines and Petroleum in relation to the Lake Carey Pro |
| A106121 | 2015 | Fortitude Gold Pty Ltd | Fortitude | <1% | Fortitude Project E39/1752 – Annual Report For The Period 6th February 2014 to the 5th February 2015 |
| A106668 | 2015 | Exterra Resources Ltd | Linden | 17% | C37/2009 Linden Project Combined Annual Report for the period 6th July 2014 to 5th July 2015, E39/1232, E39/15 |
| A101830 | 2014 | Saracen Gold Mines Pty Ltd | Butcher Well | <1% | Butcher Well Project C345/1993 Annual Report for the period 01 January 2013 to 31 December 2013, E38/2306, E39 |
| A96848 | 2013 | Anglogold Ashanti Australia Ltd | Sunrise Dam | <1% | Sunrise Dam Group Annual Report for the period 1 January 2012 to 31 December 2012 (C144/1995) |
| A97624 | 2013 | Saracen Gold Mines Pty Ltd | Butcher Well | <1% | Butcher Well Project, Annual Report for the period 1st January 2012 to 31st December 2012, E38/2306; E39/1279; |
| A96357 | 2013 | Gme Resources Ltd | Linden | <1% | Linden Project, Annual Report for the period 16th October 2011 to 15th October 2012, P39/4637-4638 & E39/1375 |
| A98420 | 2013 | Exterra Resources Ltd | Linden | 19% | Linden Project Combined Annual Report for the period 6th July 2012 to 5th July 2013, E39/1232, E39/1539, M39/2 |
| A101365 | 2013 | Gme Resources Ltd | Linden | <1% | Linden Project P39/4637, P39/4638 and E39/1375 (C40/2009) Annual Report for the period 16th October 2012 to 15 |
| A93045 | 2012 | Rubicon Resources Ltd | Mount Howe | <1% | Mt Howe Project Combined Report C222/2007, Annual Report, 1st January 2011 – 31 December 2011 |
| A93583 | 2012 | Saracen Gold Mines Pty Ltd | Butcher Well | <1% | Butcher Well Project C345/1993 Annual Report for the period 1 January 2011 to 31 December 2011 |
| A94894 | 2012 | Exterra Resources Pty Ltd | Linden | 19% | Annual Report for the Period 6th July 2011 to 5th July 2012. LINDEN COMBINED REPORTING GROUP, C37/2009, |
| A103026 | 2012 | Exterra Resources Ltd | Linden | 16% | Linden Project, Combined Annual Report for the period 06/07/2013 to 05/07/2014, E39/1232, 1539, 1754; M39/255, |
| A89379 | 2011 | Rubicon Resources Ltd | Mount Howe | <1% | Mt Howe Project Combined Report C222/2007 2010, 1st January 2010 – 31 December 2010 |
| A89771 | 2011 | Gme Resources Ltd | Linden East | <1% | Linden East Project E39/1375 Annual Report 2010-2011, 28th January 2010 to 27th January 2011 |
| A92149 | 2011 | Gme Resources Ltd | Linden | <1% | Linden Project C40/2009 and E39/1375 Annual Report 2010-2011 |
| A89855 | 2011 | Saracen Gold Mines Pty Ltd | Butcher Well | <1% | Butcher Well Project Annual Report for the period 01 January 2010 to December 2010 |
| A86182 | 2010 | Gme Resources Ltd | Linden East | <1% | E39/1375 Linden East Annual Report, Reporting Period: 27th January 2009 to 26th January 2010 |
| A88734 | 2010 | Gme Resources Ltd | Linden | <1% | Linden Project C40/2009 Annual Report 2009 - 2010, 16th October 2009 to 15th October 2010 |
| A91171 | 2010 | Exterra Resources Pty Ltd | Linden | 23% | Annual Report for the Period 6th July 2010 to 5th July 2011. Linden Combined Reporting Group, C37/2009, M39/25 |
| A86442 | 2010 | Saracen Gold Mines Pty Ltd | Butcher Well | <1% | BUTCHER WELL PROJECT ANNUAL REPORT 01 JANUARY 2009 TO 31 DECEMBER 2009 (C345/1993) |
| A88147 | 2010 | Exterra Resources Pty Ltd | Linden | 23% | Annual Report for Linden Combined Reporting Group Report C37/2009 from 06/07/2009 to 05/07/2010 |
| A85371 | 2009 | Gme Resources Ltd | Linden | <1% | Linden Project C40/2009 Annual Report 2008-2009, P39/4637 and P39/4638, 15th August 2007 to 15th December 2009 |
| A77151 | 2008 | Haoma Mining Nl | Linden | 64% | Linden Project Annual Project for the period 19 SEPTEMBER 2006 - 18 SEPTEMBER 2007 E39/293 REPORT NO: 07-02-2 |
| A78034 | 2008 | Saracen Gold Mines Pty Ltd | Butcher Well | <1% | BUTCHER WELL PROJECT ANNUAL REPORT 01 JANUARY 2007 TO 31 DECEMBER 2007 CR GROUP: C345/1993 TENEMENTS: E38/1678 |
| A74099 | 2007 | Haoma Mining Nl | Linden | 64% | Linden Project, Annual Report for the Period 19 Sept 2005 - 18 Sept 2006, E39/293, Report No.07-02-2006-01 (E |
| A75083 | 2007 | Saracen Gold Mines Pty Ltd | Butcher Well | <1% | Butcher'S Well Project, Annual Report, 01 January 2006 to 31 December 2006. (C345/1993) |
| A75678 | 2007 | Haoma Mining Nl | Linden | 69% | Linden Project, Annual Report for the period 05 May 2006 - 04 May 2007 [Interim Report] |
| A75946 | 2007 | Great Gold Mines Nl | Yundamindera | <1% | Yundamindera C76/2000 Combined Group Reporting Annual Report for the period 1 June 2006 to 31 May 2007 Explora |
| A76337 | 2007 | Gme Resources Ltd | Linden | <1% | Linden Project P39/3417 & P39/3418 Annual Technical & Progress Report for the 12 Month Period Ended 14 August |
| A76647 | 2007 | Haoma Mining Nl | Linden | <1% | LINDEN PROJECTANNUAL REPORT FOR THE PERIOD 28 JULY 2006 - 27 JULY 2007, E39/379 (Edjudina) |
| A72847 | 2006 | Haoma Mining Nl | Linden | <1% | Linden Project Annual Report for the Period 27 July 2005 to 26 July 2006, E39/379,(Haoma Mining Report No. 07 |
| A72846 | 2006 | Haoma Mining Nl | Linden | 69% | Linden Project E39/428, Annual Report for the Period 5 May 2005 to 4 May 2006, (Haoma Mining Report No. 07-02- |
| A73480 | 2006 | Metex Resources Ltd | Linden | <1% | Linden Project Area E39/1099, Surrender Report, 23/06/2005 to 18/08/2006, (Edjudina). |
| A73530 | 2006 | Great Gold Mines Nl | Yundamindera | <1% | Yundamindera C76/2000, Combined Group Reporting Annual Report for the Period 1 June 2005 to 31 May 2006, (Edju |
| A73655 | 2006 | Gme Resources Ltd | Linden | <1% | Linden Project P39/3417-3418, Annual Technical & Progress Report for the 12 Month Period Ended 15 August 2006, |
| A71794 | 2006 | Haoma Mining Nl | Linden | 64% | Linden Project, Annual Report for the period 19 September 2004 to 18 September 2005, E39/293, (Haoma Mining Re |
| A71798 | 2006 | Haoma Mining Nl | Linden | <1% | Linden Project, Annual Report for the period 27 July 2004 to 26 July 2005, E39/379, (Haoma Mining Report No. 0 |
| A71990 | 2006 | Midas Resources Ltd | Lake Carey / Fortitude | <1% | Lake Carey Project, Western Australia, Annual Technical Report, (E39/348, E39/462, E39/535, E39/865, E39/866, |
| A69831 | 2005 | Haoma Mining Nl | Linden | 64% | Exploration Licence E39/293, Linden Project , Annual Report for the period Sept/2003 to Sept/2004 |
| A69832 | 2005 | Haoma Mining Nl | Linden | 69% | Exploration Licence E39/428, Linden Project - Mt Margaret Goldfield, Annual Report for the period 5/3/2003 to |
| A71389 | 2005 | Great Gold Mines Nl | Yundamindera | <1% | Yundamindera C76/2000, Combined group reporting annual report, For the period 1 June 2004 to 31 May 2005, (Ten |
| A71451 | 2005 | Gme Resources Ltd | Linden | <1% | Linden project, P39/3417 & P39/3418, Annual technical & progress report for the 12 month period ended 15 Augus |
| A71494 | 2005 | Haoma Mining Nl | Linden | 69% | Linden Project, Annual report for the period May 2004 - May 2005, (Tenement E39/428, Report no. 07-02-2005-01, |
| A69663 | 2005 | Sons Of Gwalia Ltd | Butcher Well | <1% | Annual report for the period 01/01/04 - 31/12/04 Butcher Well Project, C345/1993, P38/3083, P39/3939, E38/449 |
| A69833 | 2005 | Haoma Mining Nl | Linden | <1% | Exploration Licence E39/379, Linden Project - Mt Margaret Goldfield, Annual Report for the period Sept/2003 to |
| A69950 | 2005 | Midas Resources Ltd | Lake Carey / Fortitude | <1% | Annual technical report for the period 01/01/04 - 31/12/04 Lake Carey Project, C05/2003, E39/348, E39/462, E39 |
| A68195 | 2004 | Sons Of Gwalia Ltd | Butcher Well | <1% | Butcher Well Project, Annual Report for the period 01/01/2003 to 31/12/2003 : P38/3083, E39/173, E39/325, E39 |
| A69079 | 2004 | Gutnick Resources Nl | Yundermindera | <1% | Joint Annual Report for the Period 1 June 2003 to 31 May 200 4 C76/2000 - Yundamindera E39/708...P39/3860 |
| A69665 | 2004 | Gme Resources Nl | Linden | <1% | Annual report for the period 16/08/03 - 15/08/04 Linden Project, C137/1998, P39/3417, P39/3418, Lake Carey |
| A68398 | 2004 | Midas Resources Ltd | Lake Carey | <1% | Annual Report for the period 01/01/2003-31/12/2003 Lake Carey Project E39/348, E39/462, E39/535, E39/865, E39 |
| A66025 | 2003 | Aurora Gold (Wa) Pty Ltd | Linden | <1% | Annual Report for the period 17 March 2002 to 16 March 2003 Linden (Total) Project E39/323 and P39/2953 C59/19 |
| A66524 | 2003 | Sons Of Gwalia Ltd | Butcher Well | <1% | Annual Report for the period 1 January 2002 - 31 December 2002 Butcher Well C345/1993: E39/325, 328, 344, 423, |
| A67291 | 2003 | Gutnick Resources Nl | Yundamindera | <1% | Joint annual Report for the period 1 June 2002 - 31 May 2003 Yundamindera Project C76/2000: E39/708,719,721,72 |
| A67491 | 2003 | Gme Resources Ltd | Linden | <1% | Annual Report for the period 16/08/02 to 15/08/02 Linden Project P39/3417-3418 |
| A67763 | 2003 | Haoma Mining Nl | Linden | 64% | E39/293, Linden Project - Mt Margaret Goldfield, Annual Review, for the period ending 18/11/2003. |
| A67761 | 2003 | Haoma Gold Mines Nl | Linden | <1% | E39/379, Linden Project - Mt Margaret Goldfield,Annual Review, for the period ending 29/09/2003. |
| A64070 | 2002 | Sons Of Gwalia Ltd | Butcher Well | <1% | Butcher Well Project, Annual Report for the period 1st January 2001 to 31st December 2001, E39/325, 328, 344, |
| A64630 | 2002 | Aurora Gold (Wa) Pty Ltd | Linden (Total) | <1% | Annual Report Linden (Total) Project Western Australia Exploration Licence 39/323 and Prospecting Licence 39/2 |
| A65531 | 2002 | Elazac Mining Pty Ltd | Linden | 18% | Linden Project, Annual Report for the period 5/5/2001 to 5/5/2002, E39/293, 397 & 429. |
| A62467 | 2001 | Gill Mining Pty Ltd | Lone Hand | 7.2% | Mineral exploration surrender report for exploration licence E39/461 - Mt. Linden for the period 23 February 2 |
| A62854 | 2001 | Sons Of Gwalia Ltd | Camelback / Butcher Well / Linden | <1% | Butcher Well Annual Report For The Period 1 January 2000 - 31 December 2000. Tenements E39/173, E39/325, E39/3 |
| A63283 | 2001 | Haoma Mining Nl | Linden | 18% | Linden Project, E39/293, E39/379, E39/428 and M39/255 ,Annual Report for the period 30th June 2000 to 30th Jun |
| A59636 | 2000 | Goldfields Exploration Pty Ltd | Linden | 18% | Linden Project, E39/293,379,428, M39/255, Annual Report 01/0 5/1998 to 30/04/1999. |
| A59754 | 2000 | Acacia Resources Ltd | Lone Hand | 7.2% | Lone Hand E39/461 'Annual' Report on Exploration Completed Prior to Withdrawal from Option 07/11/1997 to 01/06 |
| A60493 | 2000 | Haoma Mining Nl | Linden | <1% | Linden Project Prospecting Licences P39/2974, P39/2975 & P39/2976. Annual Report for the Period Ending 12th Ma |
| A60563 | 2000 | Capricorn Resources Aust Nl | Linden | <1% | Linden Project, Mt Linden, WA, E39/323 and P39/2953, Annual Report for the Period 15/03/1999 to 16/03/2000. C |
| A60712 | 2000 | Goldfields Exploration Pty Ltd | Linden | 18% | Linden Project, E39/379,M39/255,E39/293,E39/428 Annual Report 01/05/1999 to 30/04/2000. |
| A61790 | 2000 | Sons Of Gwalia Ltd | Butcher Well | <1% | Butcher Well Annual Report for the Period 01/01/1999 to 31/12/1999. E39/173,325,328,344,384,423,475,532, M39/1 |
| A63041 | 2000 | Capricorn Resources Aust Nl | Linden | <1% | Linden Project Mt.Linden W.A E.L.39/323 and P.L.39/2953 Annual Report for period 15.03.2000 to 16.03.2001 Com |
| A57738 | 1999 | Acacia Resources Ltd | Lone Hand | 7.2% | Acacia Resources Limited, Lone Hand E39/461, Annual Report for the period 25 February 1998 to 24 February 1999 |
| A58497 | 1999 | Sons Of Gwalia Ltd | Butcher Well | <1% | Butcher Well JV - 01/01/98 - 31/12/98 M39/118-120, 165-166, 230-232 E39/173, 281, 325, 328, 344, 384, 423, 475 |
| A55383 | 1998 | Lone Hand & Associates Pty Ltd | Linden | 7.9% | Second Annual report Exploration Licence 39/516 Linden WA Reporting period 03/03/97-02/02/03/98 |
| A54368 | 1998 | Capricorn Resources Aust Nl | Linden | <1% | Linden Project, Annual Report for the period 17/03/1997 to 17/03/1998, E39/323;P39/2953. |
| A54584 | 1998 | Mount Burgess Mining Nl | Butcher Well | <1% | Butcher Well Project Combined Annual Technical Report For period 01/01/97-31/12/97 Ref:C345/93 Tenements E39/1 |
| A55120 | 1998 | Gme Resources Nl | Linden | <1% | Linden Project, Edjudina Annual Report 1996/1997 P39/3417-3418, 16/08/96 - 15/08/97 |
| A55156 | 1998 | Goldfields Exploration Pty Ltd | Linden | 18% | Linden Report, Annual Report 03/11/97 - 30/04/98 E39/293, M39/255, E39/379, E39/428 |
| A50334 | 1997 | Yardarino Mining Nl | Lone Hand | 7.2% | Yardarino Mining NL, Lone Hand Project E39/461, Annual Report for period ending 23 February 1997 |
| A51482 | 1997 | Lone Hand & Associates Pty Ltd | Linden | 7.9% | First Annual report Exploration Licence E39/516 Linden Western Australia Reporting period - 3rd March 1996 to |
| A50531 | 1997 | Sons Of Gwalia Ltd | Butcher Well | <1% | Butcher Well Project Combined Annual Technical Report for period 1st January 1996 to 31st December 1996 Teneme |
| A53181 | 1997 | Haoma Mining Nl | Linden North | 64% | Linden North Project, Exploration Licence: 39/293 Annual Report, Period Ending:18/09/1997 (Edjudina) |
| A52801 | 1997 | Haoma Mining Nl | Linden | <1% | Linden Project Exploration Licence 39/379, Annual report for the period ending 18 September 1997, Edjudina. |
| A47292 | 1996 | Yardarino Mining Nl | Lone Hand | 7.2% | Yardarino Mining NL, Lone Hand Project E39/461, Annual Report for period ending 23 February 1996 |
| A51283 | 1996 | Mr Hawtin Dj | Linden | <1% | Linden South Project Exploration Licence E39/379 Annual report for the period ending 27 July 1996 Edjudina Sh5 |
| A47727 | 1996 | Sons Of Gwalia Ltd | Camelback-Butcher Well | <1% | Butcher Well Gold Project Combined Annual Technical Report for period 1st January 1995 to 31st December 1995 R |
| A49365 | 1996 | Haoma Mining Nl | Linden | 64% | Linden Project, E39/293 Annual report for the period ending 18 September 1996. |
| A46043 | 1995 | Mr Hawtin Dj | Linden | <1% | Linden South Project Exploration Licence E39/379 Annual report for the period ending 27 July 1995 Edjudina SH5 |
| A43925 | 1995 | Mount Burgess Mining Nl | Butcher Well | <1% | Butcher Well Project, Combined Annual Report E39/173, 281, 323, 325, 328 & 344, M39/118-120, 165-166, 230-232 |
| A45203 | 1995 | Mr Hawtin Dj | Linden | 69% | Annual Report for the period 6th May 1994 to 5th May 1995, Exploration Licence 39/428,Linden Project. |
| A46575 | 1995 | Haoma Mining Nl | Linden | 64% | Linden Project, Annual Report for Linden Project Exploration Licence E39/293 for the year ending 18th Septem |
| A40388 | 1994 | Capella Holdings Pty Ltd | Linden | <1% | Linden Project, Exploration Licence No 39/328, Report for the Period Ending 17/3/1993. |
| A42501 | 1994 | Mr Hawtin Dj | Linden | <1% | Annual Report for the period 28/07/93-27/07/94 Linden South Project E39/379 18042005SN S/C |
| A40601 | 1994 | Mount Burgess Mining Nl | Camelback, Butcher Well, Linden | <1% | Butcher Well Project, Annual report for period 1 January 1993 to 31 December 1993, C345/93 |
| A42096 | 1994 | Haoma North West Nl | Linden | 64% | Linden Project, Partial Surrender Report for the period ending 18th September1993, E39/293. |
| A39523 | 1993 | Haoma North West Nl | Linden | 64% | Linden Project, Annual Report for the year ending 18th September 1993, E39/293. |
| A34576 | 1991 | Haoma North West Nl | Linden | 43% | Linden (JV) Project, Non-statutory Report: Initial Exploration Programme for 1991, Annual Report for Sept 1990 |
| A23744 | 1988 | Haoma North West Nl | Linden | 39% | Linden Joint Venture. Exploration report. 03/87-03/88. M39/68,87,105,125,137,144. |
| A20093 | 1986 | Haoma North West Nl | Linden | 87% | Annual report Linden Gold Project Mt Margaret Mineral Field Western Australia GML39/701 to GML39/705 GML39/715 |
| A16206 | 1985 | Haoma North West Nl | Linden | 27% | Linden Joint Venture Exploration Report January to September 1985 Linden Western Australia HW85-12 |
| A13194 | 1984 | Haoma North West Nl | Linden | <1% | Linden Project, Annual Report for the year ending 31/12/1983, GML39/705. |
| A12363 | 1983 | Haoma North West Nl | Linden | 100% | Linden Gold Project Annual Report (1982) GML39/702 and GML39/703 Mount Margaret Mineral Field, W.A. W/83/8 |
| A12365 | 1983 | Haoma North West Nl | Linden | <1% | Linden Project, Annual Report for the period 01/01/1982 to 31/12/1982, GML39/705. |
| A10302 | 1981 | International Nickel Aust Ltd | Linden | 73% | Linden Report , Non-statutory Report, Final Report for the period 09/07/1980 to 16/08/1981. TR70/7720-7723H. |
| A16368 | 1976 | North Flinders Mines Ltd | Yilgarn | <1% | Yilgarn Project, Non-statutory Report: Summary of Activities for Quarterly period ending 30th June 1976 [Mt G |
| A6011 | 1975 | International Nickel Australia Ltd | Lake Carey | 9% | Lake Carey Project, Non-statutory Report: Relinquishment Report for the period 1st January 1974 to 10th July 1 |
| A4910 | 1974 | International Nickel Aust Ltd | Lake Carey | 9% | Lake Carey Project, Non-statutory Report: Exploration Report for the period 1st July 1973 to 31st December 197 |
| A3932 | 1973 | International Nickel Aust Ltd | Lake Carey | <1% | Lake Carey Project, Non-statutory Report: Final Report for the period 1st July 1972 to 30th June 1973, TR70/37 |
| A2782 | 1972 | International Nickel Aust Ltd | Lake Carey | <1% | Lake Carey Project, Annual Report for the period ending 30th June 1971, TR70/3730 & 5279H. |
| A2829 | 1972 | International Nickel Aust Ltd | Lake Carey | <1% | Lake Carey Project, Annual Report for the period ending 30th June 1972, TR70/3730H. |
| A3618 | 1972 | International Nickel Aust Ltd | Lake Carey | <1% | Lake Carey Project, Non-statutory Report: Miscellaneous Maps (1-20), for the period ending 31/12/1972, TR70/3 |
| A941 | 1971 | International Nickel Aust Ltd | Lake Carey | <1% | Lake Carey Project, Annual Report for the period ending 30th June 1970, TR70/3730H & 5279H. |
| A271 | 1970 | International Nickel Aust Ltd | Lake Carey | <1% | Lake Carey Project, Annual Report for the period ending 30th June 1969, TR70/3730H. |
| A1121 | 1969 | International Nickel Aust Ltd | Lake Carey | <1% | Lake Carey Project, Non-statutory Report:;Volume 1: Report on the Induced Polarization & Resistivity Survey on |
| A1122 | 1969 | International Nickel Southern Exp Ltd | Lake Carey | <1% | Lake Carey Project, Non-statutory Report: Appendix 2:Annual Report, June 30th 1969, TR70/3730H; Report on the |
| A1123 | 1969 | International Nickel Southern Exp Ltd | Lake Carey | <1% | Lake Carey Project, Non-statutory Report: Annual Report for the period ending 30th June 1969, TR70/3730H. A Re |
| A269 | 1968 | International Nickel Aust Ltd | Lake Carey | <1% | Lake Carey Project, Annual Report for the year ending 30th June 1968, TR70/3730H. |
| A270 | 1968 | International Nickel Aust Ltd | Lake Carey | <1% | Lake Carey Project, Non-statutory Report: Report on the Induced Polarisation & Resistivity Survey on the Deep |
| A268 | 1967 | International Nickel Aust Ltd | Lake Carey | <1% | Lake Carey Project, Annual Report for the year ending 30th June 1967, TR70/3730H. |
| A79054 | 1753 | Haoma Mining Nl | Linden | 69% | LINDEN PROJECT E39/428 ANNUAL REPORT FOR THE PERIOD 05 MAY 2007 - 04 MAY 2008 |
| A84434 | 1753 | Haoma Mining Nl | LINDEN | 22% | LINDEN COMBINED REPORTING GROUP, Report from 06/07/2008 to 05/07/2009, C37/2009, E39/239, E39/428, M39/255, M3 |
| A38751 | 1753 | Inco Australia Ltd | Eastern Goldfields regional mapping | <1% | Eastern Goldfields regional mapping |
| A81193 | 1753 | Haoma Mining Nl | LINDEN | 64% | LINDEN PROJECT, ANNUAL REPORT FOR THE PERIOD, 19 SEPTEMBER 2007 – 18 SEPTEMBER 2008 |
| A81890 | 1753 | Saracen Gold Mines Pty Ltd | BUTCHER WELL | <1% | BUTCHER WELL PROJECT (C345/1993), ANNUAL REPORT – 01 JANUARY 2008 TO 31 DECEMBER 2008, E38/1678, E39/173, E39/ |
| A85884 | 1753 | Saracen Gold Mines Pty Ltd | Butcher Well | <1% | M39/721 – BUTCHER WELL PROJECT PARTIAL SURRENDER REPORT – 21 NOVEMBER 2007 TO 23 SEPTEMBER 2009 |
What does the exploration record say about this ground?
NextMaps reads the WAMEX reports over M 39/1204 into a referenced prospectivity assessment: the geology, the historical programs, the drill intercepts and geochemistry, and the untested gaps, with every claim cited back to its source report. New accounts include a free report (how the reports work). Prefer the raw due diligence? A Tenure Pack bundles the full register record, tenure history and spatial datasets for this ground.
Get the free report Full register record on the mapDo you hold M 39/1204? Listing is free. A facilitation fee applies only if the ground ends up with a buyer we introduce.
List this tenementTenure data sourced from the DMPE public registers and SLIP WA (© Government of Western Australia, CC BY 4.0), as at 2026-10-08. Compiled by NextMaps. Verify against primary sources before reliance.