E 45/5609
Register summary
- Holder
- Ngungaju Lithium Operations Pty Ltd
- Local government
- Shire of East Pilbara
- Application received
- 31 Jan 2020
- Commenced
- 20 Sept 2023
- Expiry
- 19 Sept 2028
- Term
- 5 Years
Exploration history on this ground
| Report | Year | Operator | Project | On this ground | Title |
|---|---|---|---|---|---|
| A145185 | 2024 | Acme Pilbara Pty Ltd; Trek Metals Limited | Pincunah | <1% | Pincunah E45/4909 Partial Surrender Report for the period 31/08/2018 to 30/08/204 |
| A136860 | 2023 | Formosa Steel Ib Pty Ltd | Glacier Valley | <1% | C120/2008 (Glacier Valley) Combined Partial Surrender Report For the Period 8 August 2007 to 10 August 2023 |
| A137056 | 2023 | Kairos Minerals Limited; Pilbara Regional Exploration Pty Lt | Lalla Rookh | <1% | Partial Surrender Report E45/4741 Lalla Rookh Project for the period ending 23/7/2023 |
| A125866 | 2021 | Pacton Pilbara Pty Ltd | West Strelley | <1% | West Strelley Surrender Report E45/05097 for the period ending 06/01/2020 |
| A124934 | 2020 | Kairos Minerals Limited | Lalla Rookh | <1% | Lalla Rookh E45/4741 - Annual Technical Report for the period ending 23/07/2020 |
168 more reports
| A125149 | 2020 | Sqm Australia Pty Ltd | Lynas Find | <1% | Final Surrender Report E45/4356 for the period 17 November 2014 to 21 August 2020, Lynas Find project. |
| A123705 | 2020 | Sqm Australia Pty Ltd | Lynas Find | <1% | C108/2012 Lynas Find Annual Report, 13 March 2019 to 12 March 2020 |
| A123507 | 2020 | Altura Lithium Operations Pty Ltd | Pilgangoora | 28% | Pilgangoora - Annual Report C134_2011 - 1 May 2019 to 30 April 2020 |
| A124011 | 2020 | Pilbara Minerals Limited | Pilgangoora | <1% | Combined Annual Exploration Report C123/2002, Pilgangoora Lithium-Tantalum Project for the period ending 23/04 |
| A125234 | 2020 | Trek Metals Limited | Pincunah | <1% | Annual Technical Report for Pincunah E45/4909 for the period ending 30/8/2020 |
| A124376 | 2020 | Sqm Australia Pty Ltd | Lynas Find | <1% | Final Surrender E45/4227 Lynas Find Project for the period ending 23/07/2020 |
| A118854 | 2019 | Fortescue Metals Group Ltd | Glacier Valley | <1% | C120/2008 Glacier Valley Annual Report For the Period 1 December 2017 to 30 November 2018, E45/02510, E45/0253 |
| A119601 | 2019 | Venus Metals Corporation Limited; Pilgangoora Minerals Pty L | Pilgangoora | <1% | E45/4684 Pilgangoora Lithium-Tantalum Project For the Period 2 February 2018 to 1 February 2019 |
| A119947 | 2019 | Altura Lithium Operations Pty Ltd | Pilgangoora | 29% | C134_2019 Pilgangoora – Annual Report for the period 1 May 2018 to 30 April 2019, E45/02287, E45/02363, E45/03 |
| A121242 | 2019 | Kairos Minerals Limited | Lalla Rookh | <1% | Lalla Rookh E45/4741 Annual Technical Report for the period 24 July 2018 to 23 July 2019 |
| A120028 | 2019 | Sqm Australia Pty Ltd | Tabba Tabba | <1% | C108/2012 Tabba Tabba Annual Report for the period 13 March 2018 to 12 March 2019, E45/04227, E45/04356 |
| A120328 | 2019 | Pilbara Mines Limited | Pilgangoora | <1% | Combined Annual Exploration Report, Pilgangoora Lithium-Tantalum Project C123/2002 for the period 24 April 201 |
| A121647 | 2019 | Acme Pilbara Pty Ltd | Wallareenya | <1% | Annual Technical Report for Wallareenya E45/4909 for the period 31 August 2019 to 30 August 2019 |
| A119603 | 2019 | Venus Metals Corporation Limited; Pilgangoora Minerals Pty L | Pilgangoora | 100% | Pilgangoora E45/04630 Annual Report for the period 6 February 2018 to 5 February 2019 |
| A116425 | 2018 | Venus Metals Corporation Limited | Pilgangoora | <1% | Annual Report for Pilgangoora Lithium -Tantalum Project - Tenement No. E45/4684 For the Period 2 February 2017 |
| A116426 | 2018 | Venus Metals Corporation Limited | Pilgangoora | 100% | Pilgangoora Project E45/04630 Annual Report for the period 06/02/2017 - 05/02/2018 |
| A117065 | 2018 | Pilbara Minerals Limited | Pilgangoora | <1% | C123/2002 Combined Annual Exploration Report, Pilgangoora Lithium-Tantalum Project for the period 24/04/2017 - |
| A116600 | 2018 | Altura Lithium Operations Pty Ltd | Pilgangoora | 29% | Pilgangoora – Annual Report C134_2011, 01 May 2017 to 30 April 2018 |
| A116971 | 2018 | Metalicity Limited | Tabba Tabba | <1% | E45/04148, E45/04227, E45/04356, C108/2012 Tabba Tabba Project Annual Technical Report for the period 13 March |
| A117692 | 2018 | Metalicity Energy Pty Ltd | Tabba Tabba | <1% | Surrender Report E45_4148, Tabba Tabba Project, 13 March 2017 - 24 August 2018 |
| A117836 | 2018 | Kairos Minerals Limited | Croydon | <1% | Croydon Project E45/4741 Annual Report for the period 24/07/2017 - 23/07/2018 |
| A112767 | 2017 | Pilbara Minerals Limited | Lynas Find | <1% | Combined Annual Mineral Exploration Report C64/2016 for the Lynas Find Lithium Project C64/2016 for the period |
| A114041 | 2017 | Altura Lithium Operations Pty Ltd | Pilgangoora | 29% | C134/2011 Pilgangoora Project Combined Annual Report for the period 1 February 2016 to 30 April 2017, E45/0228 |
| A115251 | 2017 | Atlas Iron Limited | Abydos | <1% | Final Surrender Report for E45/2899-I Abydos Project for the period 21 April 2007 to 20 April 2017 |
| A114022 | 2017 | Metalicity Limited | Lynas Find | <1% | C108/2012 Annual Technical Report for the period 13 March 2016 to 12 March 2017, E45/04148, E45/04227, E45/04 |
| A114103 | 2017 | Pilbara Minerals Limited | Pilgangoora | <1% | Combined Annual Exploration Report, Pilgangoora Lithium-Tantalum Project For the Period 24 April 2016 to 23 Ap |
| A109927 | 2016 | Dakota Minerals Limited | Lynas Find | <1% | Exploration Annual Report E45/3648 Lynas Find for the period 07/09/2015 to 06/09/2016 |
| A108899 | 2016 | Altura Exploration Pty Ltd | Pilgangoora | 41% | Pilgangoora Exploration Licence 45/2363 Annual Report 1st May 2015 to 30th April 2016 |
| A108902 | 2016 | Altura Exploration Pty Ltd | Pilgangoora | <1% | Pilgangoora Exploration Licence 45/3488 Annual Report for the period 11th January 2015 - 10th January 2016 |
| A109069 | 2016 | Fortescue Metals Group Ltd | Tabba Tabba | <1% | C108/2012 Tabba Tabba Annual Report for the period 13 March 2015 to 12 March 2016, E 45/04148, E 45/04227, E 4 |
| A109405 | 2016 | Pilbara Minerals Ltd | Pilgangoora | <1% | Annual Mineral Exploration Report, Pilgangoora Project for the period 24 April 2015 to 23 April 2016. Combined |
| A108018 | 2016 | Haoma Mining Nl | Tabba Tabba - Strelley | <1% | FINAL SURRENDER REPORT For the Period 17 October 2013 to 9 December 2015 TABBA TABBA / STRELLEY PROJECT E45/40 |
| A109653 | 2016 | Atlas Iron Limited | Abydos | <1% | ABYDOS PROJECT C40/2007 Annual Technical Report to the Department of Mines and Petroleum for the Period Ending |
| A105825 | 2015 | Fortescue Metals Group Ltd | Tabba Tabba | <1% | ANNUAL REPORT For the Period 13 March 2014 to 12 March 2015 C108/2012 TABBA TABBA E45/2850, E45/4148, E45/4227 |
| A105939 | 2015 | Atlas Iron Ltd | Abydos | 7.3% | Abydos Project C40/2007 Annual Technical Report to the Department of Mines and Petroleum for the Period Ending |
| A106348 | 2015 | Pilbara Minerals Ltd | Pilgangoora | <1% | Pilgangoora Project, WA Annual Group Report C123/2002 24 April 2014 – 23 April 2015, [E45/2232, E45/2241, M45/ |
| A105312 | 2015 | Fmg Pilbara Pty Ltd | Turner River 5 | 8.6% | Final Surrender Mineral Exploration Report E45/2853 Turner River 5 for the period 13 February 2012 to 19 Decem |
| A105322 | 2015 | Fortescue Metals Group Ltd | Glacier Valley - Pinpin River 1 | 17% | Partial Surrender Mineral Exploration Report: E45/2854 (Pinpin River 1) Glacier Valley Project for the period |
| A107316 | 2015 | Asgard Metals Pty Ltd | McPhee's - Pilgangoora | <1% | ANNUAL REPORT For the Period 6 September 2014 to 5 September 2015 MCPHEE'S - PILGANGOORA Mineral Exploration A |
| A106614 | 2015 | Fortescue Metals Group Ltd | Glacier Valley | 4.3% | C120/2008 Glacier Valley Final Surrender Report for the period 13/02/2012 to 11/05/2015 |
| A104729 | 2015 | Altura Exploration Pty Ltd | Pilgangoora | <1% | Pilgangoora Project E45/3488 Annual Report for the period 11/01/2014 - 10/01/2015 |
| A105066 | 2015 | Fortescue Metals Group Ltd | Glacier Valley | 3.3% | Combined Annual Report for the Period 1 December 2013 to 30 November 2014, C120/2008, Glacier Valley Project E |
| A101798 | 2014 | Lithex Resources Ltd | Pilgangoora | <1% | Final Relinquishment Report E 45/3373 Pilgangoora For the Period 16 February 2010 to 7 February 2014. |
| A102272 | 2014 | Fortescue Metals Group Ltd | Tabba Tabba | <1% | Combined Mineral Exploration Report: C108/2012 Tabba Tabba Project for the period 13 March 2013 to 12 March 20 |
| A102322 | 2014 | Trafford Resources Ltd | Lynas Find | <1% | Combined Annual Mineral Exploration Report C348/2011, Lynas Find Project, for the period 01/04/2013 to 31/03/2 |
| A102356 | 2014 | Atlas Iron Ltd; Altura Mining Ltd | Abydos | 7.7% | Abydos Project, Annual Report for the period 01/05/2013 to 30/04/2014, E45/2308,2362-2363, 2728,2899, 3298, 33 |
| A103820 | 2014 | Asgard Metals Pty Ltd | McPhees | <1% | McPhees Project, Annual Report for the period 06/09/2013 to 05/09/2014, E45/3648. |
| A104043 | 2014 | Haoma Mining Nl | Tabba Tabba - Strelley | <1% | Tabba Tabba - Strelley Project, Annual Report for the period 17/10/2013 to 18/10/2014, E45/4062. |
| A101524 | 2014 | Fortescue Metals Group Ltd | Glacier Valley | 3.6% | Combined Report for the Period 1st December 2012 to 30th November 2013, C120/2008 Glacier Valley |
| A98064 | 2013 | Atlas Iron Ltd | Abydos | 11% | Abydos Project, Annual Report for the period ending 30th April 2013, E45/2308, 2362-2363, 2471, 2728, 2899, 32 |
| A98065 | 2013 | Altura Exploration Pty Ltd | Pilgangoor | 41% | Pilgangoor Project, Annual Report for the period 1st May 2012 to 30th April 2013, E45/2363. [C40/2007] |
| A98428 | 2013 | Atlas Iron Ltd | Abydos | 38% | Abydos Project E45/2471-I C40/2007 Surrender Report to the Department of Mines and Petroleum for the Period 1 |
| A100426 | 2013 | Kubwa Iron Ore Holdings Pty Ltd | Tabba Road | 100% | Tabba Road Project, Annual Report for the period 7th July 2012 to 6th July 2013, E45/3701. |
| A96559 | 2013 | Altura Exploration Pty Ltd | Pilgangoora | <1% | Exploration Licence 45/3488 Annual Report for the period 11th January 2012 to 10th January 2013 |
| A99558 | 2013 | Ascot Resources Ltd | McPhees | <1% | Mineral Exploration Annual Tenement Report E45/3648 McPhees Gold Project for the period 06/09/12 - 05/09/13 |
| A98263 | 2013 | Global Advance Metals Pty Ltd | Pilgangoora | <1% | Pilgangoora Project, Annual Report for the period 24th April 2012 to 23rd April 2013, E45/2232 & 2241; M45/78, |
| A96750 | 2013 | Fortescue Metals Group Ltd | Glacier Valley | 4.2% | Glacier Valley Combined Report (Iron Bridge Project) C120/2008 Annual Report for the period 1st December 2011 |
| A97778 | 2013 | Atlas Iron Ltd | Abydos | <1% | Abydos Project, Partial Surrender Report for the period 21/04/2007 to 20/04/2013, E45/2899. [C40/2007] |
| A98197 | 2013 | Lithex Resources Ltd | Pilgangoora | <1% | Pilgangoora Project, Annual Report for the period 1st March 2012 to 28th February 2013, E45/3373 & P45/2599. [ |
| A98484 | 2013 | Trafford Resources Ltd | Lynas Find | <1% | Combined Annual Mineral Exploration Report C348/2011, Lynas Find Project, for the period 01/04/2011 to 31/03/2 |
| A93821 | 2012 | Lithex Resources Ltd | Pilgangoora | <1% | Combined Annual Report E 45/3373 & P45/2599 Pilgangoora for the period 1 March 2011 – 29 February 2012, C345/2 |
| A93197 | 2012 | Fortescue Metals Group Ltd | Glacier Valley - Iron Bridge | <1% | Glacier Valley Annual Report for the period 1st December 2010 to 30th November 2011, E45/2510-1, E45/2535-1, a |
| A92951 | 2012 | Altura Mining Ltd | Pilgangoora | <1% | Pilgangoora E45/3488 Exploration Licence 45/3488 Annual Report 2012, 11th January 2011 - 10th January 2012 |
| A93939 | 2012 | Trafford Resources Ltd | Lynas Find | <1% | Combined Annual Mineral Exploration Report C348/2011, Lynas Find Project, for the period 01/04/2011 to 31/03/2 |
| A95325 | 2012 | Kubwa Iron Ore Holdings Pty Ltd | Tabba Road | 100% | Annual Mineral Exploration Report Tabba Road Project E45/3701 for the period 7th July 2011 to 6th July 2012 |
| A93980 | 2012 | Global Advance Metals Pty Ltd | Pilgangoora | <1% | Annual Report for the period 24th April 2011 to 23rd April 2012, Pilgangoora Project, C123/2002, E45/2232, E45 |
| A94018 | 2012 | Atlas Iron Ltd | Abydos | 8.1% | ABYDOS PROJECT C40/2007 Annual Technical Report to the Department of Mines and Petroleum for the Period Ending |
| A95262 | 2012 | Epic Resources Limited | McPhees | <1% | E45/3648 Annual Report for McPhees Gold Project for the period 01/09/11 to 31/08/12 |
| A89460 | 2011 | Fortescue Metals Group Ltd | Glacier Valley | <1% | Annual report for the period 1st December 2009 to 30th November 2010, Glacier Valley Project, E45/3084, E45/2 |
| A89568 | 2011 | Global Advanced Metals Pty Ltd | Pilgangoora | 2.7% | Pilgangoora Project, Surrender Report for the period 17 November 2005 - 16 November 2010, E45/2251. [C123/2002 |
| A90329 | 2011 | Trafford Resources Ltd | Lynas Find | <1% | Lynas Find Project, Annual Report for the period 13/02/2010 to 12/02/2011, E45/2375. (C207/2006) |
| A90513 | 2011 | Atlas Iron Ltd | Abydos | 9% | Abydos Project, Annual Report for the period ending 30th April 2011,E45/2362, 2363, 2404, 2471, 2728, 2765, 28 |
| A90293 | 2011 | Lithex Resources Ltd | Pilgangoora | <1% | Annual Exploration Report E 45/3373 Pilgangoora For the Period Ending 15 February 2011, (Shaw River). |
| A90379 | 2011 | Global Advanced Metals Pty Ltd | Pilgangoora | <1% | Pilgangoora Project, Annual Report for the period 24th April 2010 to 23rd April 2011, E45/2232, E45/2241, E45/ |
| A90380 | 2011 | Atlas Iron Ltd | Abydos - Pilgangoora | <1% | Abydos - Pilgangoora Project, Annual Report for the period ending 23rd April 2011, E45/2232, E45/ 2241; M45/78 |
| A87472 | 2010 | Atlas Iron Ltd | Abydos | 11% | Annual Report to the Department of Mines and Petroleum for the period 01/05/2009 to 30/04/2010 |
| A87091 | 2010 | Talison Minerals Pty Ltd | Pilgangoora | <1% | Annual Report for the period 24th April 2009 to 23rd April 2010, Pilgangoora Project, C123/2002 |
| A86813 | 2010 | Atlas Iron Ltd | Abydos | 38% | Partial Surrender Report to the Department of Mines and Petroleum E45/2471 for the period 01/05/2006 to 28/03/ |
| A87231 | 2010 | Trafford Resources Ltd | Lynas Find | <1% | Lynas Find Project Exploration Licence E45/2375 4th Year Partial Surrender Report of Hamersley Range 852 W & |
| A87232 | 2010 | Trafford Resources Ltd | Lynas | <1% | Lynas Find Project Exploration Licence E45/2375 Annual Technical Report on Exploration for the period 13/02/20 |
| A87454 | 2010 | Atlas Iron Ltd | Abydos | 38% | Abydos Project Partial Surrender Report to the Department of Mines and Petroleum E45/2471 for the period 01/05 |
| A85855 | 2010 | Fortescue Metals Group Ltd | Glacier Valley | <1% | Annual report for the period 1 December 2008 to 30 November 2009, Glacier Valley Project, E45/3084, E45/2510 & |
| A81935 | 2009 | Montezuma Mining Company Ltd | Pilgangoora | <1% | Partial Surrender Report on E45/2375, Pilgangoora Project, For the Period 13 February 2006 to 12 February 2009 |
| A80926 | 2009 | Montezuma Mining Company Ltd | Pilgangoora | <1% | Annual Report on E45/2375, Pilgangoora Project, for the Period 13 February 2008 to 12 February 2009 |
| A80932 | 2009 | Fortescue Metals Group Ltd | Glacier Valley | <1% | Annual report for the period 8 August 2007 to 30 November 2008, Glacier Valley Project, E45/3084, E45/2510 & E |
| A82658 | 2009 | Atlas Iron Ltd; Shaw River Resources Ltd | Abydos | 11% | Annual Report to the Department of Mines and Petroleum for the period 01/05/2008 to 30/04/2009 Tenements: E45 |
| A78704 | 2008 | Talison Minerals Ltd | Pilgangoora | <1% | PILGANGOORA PROJECT ANNUAL REPORT FOR THE PERIOD 24th April 2007 to 23rd April 2008 TENEMENT: C123/2002 GROUP, |
| A78725 | 2008 | Atlas Iron Ltd | Abydos | 11% | Annual Report to the Department of Industry and Resources Abydos for the period 01/05/07 to 30/05/08, TENEMENT |
| A77983 | 2008 | Montezuma Mining Company Ltd | Pilgangoora | <1% | Annual Report on E45/2375, Pilgangoora Project for the Period 13 Feb 2007 to 12 Feb 2008 |
| A82597 | 2008 | Atlas Iron Ltd | Abydos | <1% | Abydos Project C123/2002, E45/2232, E45/2241 and E45/2251Annual for the period 24/04/2008 to 23/04/2009 |
| A75373 | 2007 | Atlas Iron Ltd | Abydos | 9.2% | Annual Report for the Period 01/05/06 to 30/04/07 Tenements:E45/2362,E45/2363,E45/2404,E45/2471,E45/2594, E45/ |
| A75697 | 2007 | Sons Of Gwalia Ltd | Pilgangoora | <1% | Pilgangoora Project, Annual Report for the period 24th April 2006 to 23rd April 2007, E45/2241, M45/78, M45/33 |
| A74812 | 2007 | Montezuma Mining Company Ltd | Pilgangoora | <1% | Annual Report on E45/2375, Pilgangoora Project, For the Period 13 February 2006 to 12 February 2007 |
| A74747 | 2007 | Sons Of Gwalia Ltd | Pilgangoora | 2.7% | Pilgangoora Project E45/2251, Annual Report for the Period 17 Nov 2005 - 16 Nov 2006. Report No.2251-2006-11 |
| A73283 | 2006 | Sons Of Gwalia Ltd | Pilgangoora | <1% | Pilgangoora Project E45/2241,M45/78,333, Annual Report for the Period 24 April 2005 to 23 April 2006, Combined |
| A71916 | 2006 | Sons Of Gwalia Ltd | Pilgangoora | <1% | Pilgangoora Project, Annual Report for the period 24 April 2004 to 23 April 2005, E45/2241,M45/78,M45/333, Com |
| A68663 | 2004 | Sons Of Gwalia Ltd | Pilgangoora | <1% | Annual Report for the period 24/04/2003-23/04/2004 Pilgangoora Project(C123/2002), E45/2241, E45/2242 |
| A67020 | 2003 | Sons Of Gwalia Ltd | Pilgangoora | <1% | Pilgangoora Project, Annual Report for the period 24 April 2002 to 23 April 2003, C123/2002, E45/2241-2242. S |
| A66675 | 2003 | Lynas Gold Nl | Lynas Find | 3.4% | Surrender Report May 2003 Lynas Find Project C264/1993 for the tenements M45/281-2, 523-4, P45/2229, 2338, 235 |
| A67056 | 2003 | Sons Of Gwalia Ltd | Pilgangoora | <1% | Pilgangoora Project, Partial Surrender Report for the period 24 April 2002 to 24 June 2003, E45/2241. SOG Rep |
| A67065 | 2003 | Sons Of Gwalia Ltd | Pilgangoora | <1% | Pilgangoora Project, Surrender Report for the period14 February 2003 to 28 May 2003, E45/2307. SOG Report No. |
| A61721 | 2001 | Stockdale Prospecting Ltd | Pilton | <1% | C102/1999 Final report for exploration licences E45/1980, E45/1982, E45/1983 & E45/1993 January 2001. |
| A63518 | 2001 | De Beers Australia Exploration Ltd | Carlindi | 9.6% | Annual Report for Exploration Licences 45/2195 - 45/2200. |
| A61323 | 2000 | Stockdale Prospecting Ltd | Pilton | <1% | C102/1999 Second Annual Report for Exploration Licences E45/1980, E45/1982, E45/1983, E45/1988, E45/1989, E45/ |
| A57800 | 1999 | Sipa Resources Ltd | Panorama | 3.6% | SurrenderReport E45/825,1040,1207,1288,1290,1291,1351,1384,1423,1438,1478,1479,1564,1575,1592,1593,1646, 2029 |
| A59319 | 1999 | Stockdale Prospecting Ltd | Pilton | <1% | First Combined C102/1999 Annual Report for Exploration Licences E45/1980, 1982, 1983, 1993, November 1999 |
| A55500 | 1998 | Lynas Gold Nl | Panorama / Lynas East | 7.2% | Lynas East JV Annual Report for the Tenements E45/1207, 1288, 1290, 1423, & 1438 for the period 1st January 19 |
| A54854 | 1998 | Lynas Gold Nl | Lynas Find | 1.5% | Lynas Find Project Annual Report For The Tenemj!nts M45/278, 281, 282, 355, 356, 464, 511, 523 - 525, P45/233 |
| A53154 | 1997 | Lynas Gold Nl | Lynas Find | 47% | Lynas Find Project, Annual Report for the period 02/10/1996 to 01/10/1997, E45/1283. |
| A49963 | 1997 | Lynas Gold Nl | Lynas Find | 1.5% | Lynas Find Project Annual report for the tenements M45/278 M45/281 M45/282 M45/355 M45/356 M45/464 M45/511 M45 |
| A50546 | 1997 | Lynas Gold Nl | Lynas East | 7.2% | Lynas East (JV) Project, Annual Report for the Tenements E45/1207, 1288, 1290, 1423 & 1438 for the period 1st |
| A53743 | 1997 | Sipa Resources Ltd | Panorama | 12% | Dept of Minerals and Energy E45/1288 &1290 Partial Surrender Report Pincunah Exploration Area, Panorama Proje |
| A48323 | 1996 | Lynas Gold Nl | Lynas Find | 47% | Lynas Find Project, Annual Report for the period 02/10/1994 to 02/10/1995, E45/1283. |
| A48123 | 1996 | Lynas Gold Nl | Lynas Find | 6.3% | Lynas Find Project ,Exploration Licence E45/1577 Annual report for the period 02/06/1995 to 01/06/96 |
| A47225 | 1996 | Lynas Gold Nl | Lynas East | 7.2% | Lynas East Gold Exploration Project, Annual Report 1995, Tenements E45/1288, 1290, 1423, 1438 AND 1207. |
| A47226 | 1996 | Sipa Resources Ltd | Panorama | 7.2% | Panorama Project, Annual Report Overing the Period 1 January 1995 to 31 December 1995, Tenements E45/1207, 128 |
| A49588 | 1996 | Lynas Gold Nl | Lynas Find | 47% | Lynas Find Project E45/1283 Annual Report |
| A44305 | 1995 | Sipa Exploration Nl | McDonalds | 99% | McDonalds Project, 1994 Annual Report P45/2228 for the period ending 17th December 1994. |
| A45049 | 1995 | Sipa Resources Ltd | Panorama / Pincunah | 7.3% | Panorama / Pincunah Project, 1994 Annual Report on the Pincunah Exploration Area, Panorama Project (covering t |
| A43107 | 1994 | Lynas Gold Nl | Lynas Find | 47% | Lynas Find Project,Annual Report E45/1283 for period 01/12/1993 to 01/12/1994. |
| A41344 | 1994 | Sipa Resources Ltd | Panorama - Pincunah | 7.6% | Panorama - Pincunah Project, Annual Report for the period 27th November 1992 to 31st December 1993, E45/971, 1 |
| A39844 | 1993 | Lynas Gold Nl | Lynas Find | 47% | Lynas Find Project, Annual report for the period 01/01/1993 to 31/12/1993, E45/1238. |
| A39949 | 1993 | Mim Exploration Pty Ltd | McPhees Cairn | 99% | McPhees Cairn Project, Annual Report for the period to 17th December 1993, P45/2228. |
| A38526 | 1993 | Mim Exploration Pty Ltd | McPhees Cairn | 99% | McPhees Cairn Project, 1992 Annual Report, June 1993, P45/2228. |
| A38897 | 1993 | Lynas Gold Nl | Pilbara Gold | 5.1% | R Report for the period 03/93 Pilbara Gold Project M45/278,280-282,511,523-525 |
| A39176 | 1993 | Sipa Resources Ltd | Panorama - Pincunah | 11% | Panorama - Pincunah Project, Annual Report for the period 27th November 1991 to 26th November 1992, E45/971,12 |
| A36450 | 1992 | Mim Exploration Pty Ltd | Nosmada | <1% | Nosmada Project, Annual Report for the period to 1st March 1992, P45/2056 and 2057. |
| A36474 | 1992 | Mim Exploration Pty Ltd | McPhees Cairn | 99% | McPhees Cairn Project,1991 Annual Report, June 1992, M45/280. |
| A37185 | 1992 | Mim Exploration Pty Ltd | McPhee's Hill | 8.8% | McPhee's Hill (JV) Project, Annual Report for the period to October 1992, M45/501 & M45/526. |
| A34837 | 1992 | Mim Exploration Pty Ltd | McPhee's Hill | 7.7% | McPhee's Hill Project, Annual Report for year ending December 1991, P45/1462 ( Now MLA 45/526), M45/501. |
| A37339 | 1992 | Lynas Gold Nl | Lynas Find | 28% | Report for the period 01/03/92 - 01/06/92 Lynas Find Project M45/278,281-282,511,523-525, P45/2229, E4 5/1283 |
| A37340 | 1992 | Lynas Gold Nl | Lynas Find | 28% | LYNAS FIND, PILBARA, W .A. INTERIM REPORT FOR THE PERIOD I JULY - OCTOBER, 1992 I VOLUME I (M45/278, 281-282 |
| A33048 | 1991 | Carpentaria Exp Co Pty Ltd | McPhees Cairn | 99% | McPhees Cairn Project, 1990 Annual Report, February 1991, M45/280. |
| A34835 | 1991 | Mim Exploration Pty Ltd | Mali | 100% | Mali Project, Annual Report for the period 16/06/1990 to 15/06/1991, P45/1916. |
| A30417 | 1990 | Carpentaria Exp Co Pty Ltd | McPhees Cairn | 99% | McPhees Cairn Project, Non-statutory Report:Report on the work conducted by Carpentaria Exploration Company Lt |
| A31776 | 1990 | Carpentaria Exp Co Pty Ltd | Mali | 100% | Mali Project, 1989/1990 Annual Report, October 1990, |
| A32391 | 1990 | Carpentaria Exp Co Pty Ltd | McPhee's Hill | 8.8% | McPhee's Hill (JV) Project, Annual Report to December 1990, P45/1462, M45/501. |
| A31018 | 1990 | Lynas Gold Nl | McPhee's Patch South | 25% | Exploration Report on Reverse Circulation Percussion Drilling at McPhee's Patch South, Mining lease M45/282 an |
| A31602 | 1990 | Lynas Gold Nl | Lynas Find | 29% | Lynas Find Project, Final Surrender Report, July 1990, E45/967. |
| A31777 | 1990 | Carpentaria Exp Co Pty Ltd | Mali | 79% | Mali Project, Non-statutory Report: Surrender Report on the work conducted by Carpentaria Exploration Co Pty L |
| A28919 | 1989 | Lynas Gold Nl | Pilgangoora - Lynas Find | 17% | Non-statutory Report : Regional Assessment Pilgangoora District Central Pilbara WA (1989) M45/54, M45/278, M45 |
| A27823 | 1989 | Lynas Gold Nl | Lynas Find | 9.7% | Lynas Find Project, Annual report 1988 on M45/278, M45/281, M45/282, P45/1412, P45/1413, P45/1481, P45/1482, |
| A27293 | 1989 | Lynas Gold Nl | Pommy Well | 69% | Final Report, Exploration Licence 45/820, Pommy Well. |
| A27169 | 1989 | Carpentaria Exp Co Pty Ltd | Green Well | 42% | Green Well, E45/606, Progress Report to February 1989. |
| A36497 | 1989 | Carlindi Mining Corp Nl | Lalla Rookh | 92% | [ Lalla Rookh Gold Exploration, Non-statutory report, M45/461, P45/1036 ] |
| A27249 | 1988 | Lynas Gold Nl | Pilgangoora | 14% | Non-statutory Report ; Stream Sediment Sampling. Pilgangoora Area East Pilbara District W.A. 12/1988 P45/148 |
| A23913 | 1988 | Lynas Gold Nl | Lynas Find | 13% | Lynas Find Project, -1987 Annual Report . P45/193-194, 241-242, 278, 449-451, 632. M45/54 , February 1988. |
| A19763 | 1987 | Clackline Refractories Ltd | Lynas Find | 25% | Non-statutory Report: Report on Geochemical Exploration at the Lynas Find Project Report for P45/449 to P45/45 |
| A19304 | 1986 | Pancontinental Mining Ltd | Pilgangoora | 15% | E45/361, Pilgangoora Project, Annual Report for the year ending 14/09/1986. |
| A18530 | 1986 | Clackline Refractories Ltd | McPhee's Cairn | 96% | Annual Report on PL45/188 McPhee's Cairn Project, Lynas Find Gold` Prospect Western Australia (1986) |
| A17099 | 1986 | Pancontinental Mining Ltd | Pilgangoora | 15% | Annual report Pilgangoora E45/361 and M45/646 (1985) Pancontinental Mining Ltd |
| A18529 | 1985 | Clackline Refractories Ltd | Lynas Find | 21% | Lynas Find Project, Non-statutory Report, December 1985 PL45/188 PL45/193 PL45/194 PL45/241 PL45/242 PL45/278 |
| A19207 | 1983 | Pancontinental Mining Ltd | Pilgangoora - Paynes Find - Yinnietharra | 5.2% | An evaluation of the rare-metal potential of pegmatites at the Pilgangoora, Paynes Find, Yinnietharra, Wodgina |
| A11368 | 1982 | International Nickel Aust Ltd | McPhees | 98% | McPhees Project, Non- Statutory Report : Annual Report for the period 01/01/1982 to 31/12/1982, TR70/8275-8260 |
| A10107 | 1981 | Australian Hanna Ltd | Mungaleena | 15% | Mungaleena Project, Non-statutory Report: Final Report for the period 11th May 1979 to 19th May 1981, TR70/70 |
| A9135 | 1980 | Australian Hanna Ltd | Mungaleena | 15% | Mungaleena Project, Annual Report for the period 11th May 1979 to 10th May 1980, TR70/7037H. |
| A5561 | 1975 | Esso Australia Ltd | Chinnamon Creek | 18% | Chinnamon Creek, Annual report [non-statutory] for period ending 16th March 1975, Temporary Reserve 5723H [ TR |
| A5570 | 1975 | Esso Exploration Aust Inc | McPhee | 18% | Annual report for period ending March 1975, McPhee Claims, MC45/7251 ... 45/7698-7702 [Plates 7-30 see A5571] |
| A5571 | 1975 | Esso Exploration Aust Inc | McPhee | 18% | Annual report [non-statutory] for period ending March 1975, McPhee Claims, MC45/7251 ... 45/7702 [Plates 7-30, |
| A4517 | 1974 | Esso Australia Ltd | Chinnamon Creek | 18% | Chinnamon Creek Project, Annual Report for the period ending 16th March 1974, TR70/5723H. |
| A5476 | 1974 | Esso Australia Ltd | Chinnamon Creek | 18% | Temporary Reserve 5723H [ TR70/5723 ], Chinnamon Creek, Quarterly report [non-statutory] for period ending 16t |
| A5195 | 1974 | Esso Australia Ltd | Chinnamon Creek | 18% | TR70/5723, Chinnamon Creek Project, Quarterly report [non-statutory] for the period ending August 16th 1974 |
| A3664 | 1973 | Consolidated Gold Fields Aust Ltd | Pilgangoora | 36% | Pilgangoora Project, Final Surrender Report, (Appendix), March 1973, TR70/4931H; MC45/4974, 6527-6547. |
| A3663 | 1973 | Consolidated Gold Fields Aust Ltd | Pilgangoora | 36% | Pilgangoora (JV) Project, Final Surrender Report, March 1973, TR70/4931H; MC45/4974, 6527-6547. |
| A893 | 1971 | Mcintyre Mines (Aust) Pty Ltd | Pilgangoora | 36% | Pilgangoora Project, Annual (Progress) Report for the period ending 31/12/1970, ( Field Season) TR70/4931H. |
| A894 | 1971 | Mcintyre Mines (Aust) Pty Ltd | Pilgangoora | 36% | Pilgangoora Project, Non-statutory Report: Plans to accompany A893, for the period ending 31/12/1970, TR70/49 |
| A892 | 1970 | Mcintyre Mines Pty Ltd | Pilgangoora | 36% | Pilgangoora Project, Annual Report for the year ending 31/12/1969, TR70/4931H. |
| A102445 | 1753 | Global Advance Metals Pty Ltd | Pilgangoora | <1% | Annual Report for the period 24th April 2013 to 23rd April 2014, Pilgangoora Project, C123/2002 |
Tenure detail Free account
- Current holders & shares
- Holder change history
- Expenditure history
- Conditions & endorsements
- Native title context
- Combined reporting
- Rent status
Tenement intelligence Premium
- Time to expiry
- 2 years · 19 Sept 2028
- At-risk & opportunity signals
- Expenditure compliance
- 5-year track record
- Spend trend & exploration intensity
- Expiry band
- Ownership age
- Dealings, mortgages & caveats
- Transfer history
What does the exploration record say about this ground?
NextMaps reads every WAMEX report over E 45/5609 into a referenced prospectivity assessment: the geology, the historical programs, the drill intercepts and geochemistry, and the untested gaps — every claim cited back to its source report. New accounts include a free prospectivity report. Prefer the raw due diligence? The Tenure Pack bundles the full register record, tenure history and spatial datasets for this ground.
Open on the map — full register record About AI reports About Tenure PacksDo you hold E 45/5609? Listing is free. A facilitation fee applies only if you sell to a buyer we introduce.
List this tenementTenure data sourced from the DMPE public registers and SLIP WA (© Government of Western Australia, CC BY 4.0), as at 2026-08-21. Compiled by NextMaps. Verify against primary sources before reliance.