E 77/3382
E 77/3382 is a pending exploration licence in the Shire of Yilgarn, Western Australia, applied for by Harbour Exploration Pty Ltd (part of Leeuwin Metals Ltd). The application was received on 23 Feb 2026 and is awaiting a decision. The ground is covered by 38 historical WAMEX reports.
Register summary
- Holder
- Harbour Exploration Pty Ltd
- Part of
- Leeuwin Metals Ltd (ASX:LM1) as at 2025-06-30
- Local government
- Shire of Yilgarn
- Application received
- 23 Feb 2026
The full record on E 77/3382
The register summary says who has applied for it. The rest of the record says what is attached to the application and how it is progressing.
- Current holders and their shares (no change of holder on record)
- Expenditure history, conditions and endorsements
- Native title context, combined reporting and rent status
- Expenditure compliance, expiry and ownership signals, once the application is granted
- Every register dealing (1 on record), with mortgages, caveats and transfers flagged
Exploration history on this ground
| Report | Year | Operator | Project | On this ground | Title |
|---|---|---|---|---|---|
| A153993 | 2026 | Midas Minerals (Newington) Pty Ltd | Newington | 39% | Partial Surrender report for E77/2602 For the Period 23 Jan 2020 to 22 Jan 2026, Newington project. (C147/2014 |
| A145378 | 2024 | Midas Minerals (Newington) Pty Ltd | Newington | <1% | Final Surrender report for E77/2955 For the Period 21 Sept 2023 to 13 Sept 2024 Newington Project |
| A129609 | 2022 | Discovex Resources Limited | Newfield | <1% | Partial Surrender Report for E77/2309 Newfield Project for the period 19/01/2022. |
| A127650 | 2021 | Fleet Street Holdings Pty Ltd; Discovex Resources Limited | Newfield | <1% | E77/2263 Partial Surrender Report For the Period 4 May 2015 to 3 May 2021 |
| A123649 | 2020 | Gateway Projects Wa Pty Ltd | Ennuin | <1% | Ennuin E77/2309 Annual Report for the period ending 19/1/2020 |
33 more reports
| A125014 | 2020 | Discovex Resources Limited; Fleet Street Holdings Pty Ltd; B | Newfield | <1% | Newfield C147/2014 Annual Report for the period ending 30 June 2020, E 77/02200, E 77/02263, E 77/02326, E 77/ |
| A119907 | 2019 | Omni Projects Pty Ltd | Carterton | <1% | Carterton Project E77/02309 Southern Cross Annual Report For the Period 20 January 2018 to 20 January 2019 |
| A120639 | 2019 | Fleet Street Holdings Pty Ltd | MOUNT JACKSON | 27% | FINAL SURRENDER REPORT for E77/2168 (C147/2014) Mount Jackson project for the period 18 June 2014 to 11 June 2 |
| A121157 | 2019 | Fleet Street Holdings Pty Ltd | Mount Jackson - Kawana | <1% | Annual Report for C147/2014 Mount Jackson (Kawana) for the period 1 July 2018 to 30 June 2019 |
| A115573 | 2018 | Omni Projects Pty Ltd | Southern Cross | <1% | Southern Cross Annual Report, E77/2309 for the period 20/01/2017-10/01/2018 |
| A117661 | 2018 | Fleet Street Holdings Pty Ltd | MOUNT JACKSON | 15% | ANNUAL REPORT for C147/2014 "MOUNT JACKSON", 01 JULY 2017 - 30 JUNE 2018 |
| A114701 | 2017 | Fleet Street Holdings Pty Ltd | Mount Jackson | 8.6% | Annual Report for C147/2014 "Mount Jackson" For the Period 1 July 2016 to 30 June 2017, E77/02168, E77/02200, |
| A112674 | 2017 | Omni Projects Pty Ltd | Carterton | <1% | Carterton Project E77/2309 Annual Report for the period 20 January 2016 to 19 January 2017 |
| A109797 | 2016 | Fleet Street Holdings Pty Ltd | Mount Jackson | 10% | ANNUAL REPORT FOR C147/2014 "MT JACKSON" FOR TGHE PERIOD 01/07/2015 TO 30/06/2016, E 77/02168, E 77/02200, E 7 |
| A105842 | 2015 | Fleet Street Holdings Pty Ltd | Kawana | <1% | Kawana Project E77/2187 Surrender Report for the period 13th August 2014 – 4th May 2015 |
| A106825 | 2015 | Fleet Street Holdings Pty Ltd | Kawana | 16% | Kawana Project Annual Combined Report C147/2014 E77/2168, E77/2200, E77/2263 for the period 1st July 2014 – 30 |
| A98595 | 2013 | Western Areas Nl | Kawana | 18% | Kawana Project, Final Surrender Report for the period 1st April 2009 to 6th June 2013, E77/1365. [C175/2008] |
| A98505 | 2013 | Western Areas Limited | Kawana | 10% | Kawana Project Annual Technical Report 2013 (C175/2008) E77/1355, 1365, 1394, 1438, 1674,1686 & 3618 for the p |
| A98400 | 2013 | Western Areas Limited | Kawana | 8.8% | Kawana Project, Final Surrender Report for the period 1st April 2012 to 26th March 2013, E77/1093. [C175/2008 |
| A98596 | 2013 | Western Areas Nl | Kawana | <1% | Kawana Project, Final Surrender Report fo the period 1st April 2009 to 6th June 2013, E77/1355. |
| A98597 | 2013 | Western Areas Nl | Kawana | 24% | Kawana Project, Final Surrender Report for the period 1st April 2009 to 12th June 2013, E77/1438. [C175/2008] |
| A93802 | 2012 | Western Areas Nl | Kawana | 8.6% | Kawana Project C175/2008 Annual Technical Report for the period 1st April 2011 to 31st March 2012, E77/1093, 1 |
| A90300 | 2011 | Western Areas Nl | Kawana | 8.6% | Kawana Project, Annual Report for the period 1st April 2010 to 31st March 2011, E77/1093, 1355, 1365, 1394, 14 |
| A87164 | 2010 | Western Areas Nl | Kawana | 8.8% | Combined Annual Report for Kawana Project (C175/2008), For the Period 1st April 2009 to 31st March 2010, E77/ |
| A82687 | 2009 | Cliffs Asia Pacific Iron Ore Pty Ltd | Kawana | 9.2% | Annual report for the period 01 April 2008 to 31 March 2009, Kawana Project, E77/1093, E77/1355, E77/1365, E77 |
| A78553 | 2008 | Southern Cross Goldfields Ltd | Kawana | 8.8% | 2008 ANNUAL REPORT KAWANA PROJECT EXPLORATION LICENCE 77/1093 For the Period 27 March 2007 - 26 March 2008 |
| A75177 | 2007 | Polaris Metals Nl | Kawana | 8.8% | Kawana Farm-in Project, Annual Report for the Period 27 March 2006 - 26 March 2007 for E77/1093. (Report No: 2 |
| A72621 | 2006 | Fleet Street Holdings Pty Ltd | Kawana | 8.8% | Kawana Project E77/1093, Annual Report Reporting Period: 27 March 2005 to 26 March 2006 |
| A70494 | 2005 | Fleet Street Holdings Pty Ltd | Kawana | 8.8% | Kawana Project - E77/1093 Annual Report Reporting period: 27 March 2004 to 26 March 2005 |
| A68633 | 2004 | Fleet Street Holdings Pty Ltd | Kawana | 8.8% | Kawana Project E77/1093 Annual Report Reporting Period: 27 M arch 2003 to 26 March 2004 |
| A61234 | 2000 | Mr Tew Ha | Bullfinch | 18% | Annual Report E77/789 22/08/1999 to 21/08/2000 |
| A54933 | 1998 | Sons Of Gwalia Ltd | Ennuin | 4.5% | Ennuin Project, E70/77/488, Final Surrender Report for the period 6th October 1992-17th December 1997. |
| A55084 | 1998 | Sons Of Gwalia Ltd | Ennuin | <1% | Ennuin Project, Annual Report Period 01/01/97 - 31/12/97 EL77/485, 488, 512, 513, 537, 733 |
| A56184 | 1998 | Mr Tew Ha | Bullfinch | 18% | Annual Report E77/789 Bullfinch Project 22/08/1997 to 21/08/1998 |
| A50364 | 1997 | Sons Of Gwalia Ltd | Ennuin | <1% | Ennuin Project,Annual report for the period 1 January 1996 to 31 December 1996 EL77/485 EL77/488 EL77/512 EL77 |
| A51780 | 1997 | Sons Of Gwalia Ltd | Ennuin | 4.5% | Ennuin Project, Partial Surrender Report for the period 06/10/1992 to 05/10/1996, E77/488. |
| A48526 | 1996 | Burmine Ltd | Ennuin | 1.8% | Ennuin Project E77/485 (Highclere Hills) and E77/488 (Kawana) annual report for period 01/01/94 to 31/12/95 |
| A44722 | 1995 | Burmine Ltd | Bullfinch - North | 1.8% | Bullfinch - North Project, E77/485 (Highclere Hills) & E77/488 (Kawana) Annual Report for Period 01/01/94 to |
What does the exploration record say about this ground?
NextMaps reads the WAMEX reports over E 77/3382 into a referenced prospectivity assessment: the geology, the historical programs, the drill intercepts and geochemistry, and the untested gaps, with every claim cited back to its source report. New accounts include a free report (how the reports work). Prefer the raw due diligence? A Tenure Pack bundles the full register record, tenure history and spatial datasets for this ground.
Get the free report Full register record on the mapDo you hold E 77/3382? Listing is free. A facilitation fee applies only if the ground ends up with a buyer we introduce.
List this tenementTenure data sourced from the DMPE public registers and SLIP WA (© Government of Western Australia, CC BY 4.0), as at 2026-10-09. Compiled by NextMaps. Verify against primary sources before reliance.