E 39/2526
Register summary
- Holder
- Wilson, Walter Scott
- Local government
- Shire of Leonora
- Application received
- 15 Nov 2024
- Commenced
- 7 Oct 2025
- Expiry
- 6 Oct 2030
- Term
- 5 Years
Exploration history on this ground
| Report | Year | Operator | Project | On this ground | Title |
|---|---|---|---|---|---|
| A145669 | 2024 | Northern Star Resources Ltd | E39/1791 | 100% | Mount Celia Project E39/1791 for the period ending 08/10/2024. |
| A136222 | 2023 | Anglogold Ashanti Australia Limited | Otway Project (E39/1697) | <1% | Otway Project (E39/1697) Final Surrender Report to the Department of Mines, Industry Regulation and Safety for |
| A136310 | 2023 | Anglogold Ashanti Australia | Otway | <1% | Otway Project (E39/2203) Final Surrender Report to the Department of Mines, Industry Regulation and Safety for |
| A128444 | 2021 | Anglogold Ashanti Australia | Otway | <1% | Otway Project (E39/1912) Final Surrender Report to the Department of Mines, Industry Regulation and Safety for |
| A128527 | 2021 | Northern Star (Carosue Dam) Pty Ltd | Mount Celia | <1% | Mount Celia Project - P39/5821 and P39/5822 Final Surrender Report for the period ending 25/08/2021 |
123 more reports
| A122389 | 2020 | Saracen Gold Mines Pty Limited | Yundamindera | 6.4% | Yundamindera Project (C96/2016) Annual Report for the Period 1 November 2018 to 31 October 2019 |
| A122817 | 2020 | Anglogold Ashanti Australia Limited | Otway | <1% | Otway (C145/2018) Annual Group Report for the period ending 31/12/2019 |
| A125292 | 2020 | Saracen Gold Mines Pty Limited | Yundamindera | <1% | Exploration Licence 39/1351 Final Surrender Report for the Period 28 July 2015 to 27 July 2020 |
| A125415 | 2020 | Saracen Gold Mines Pty Limited; Hawthorn Resources Limited | Yundamindera | <1% | Exploration Licence 39/1294 Final Surrender Report for the Period 22 August 2015 to 21 August 2020 |
| A125696 | 2020 | Saracen Gold Mines Pty Limited | Yundamindera | 7.8% | Yundamindera Project (C96/2016) Annual Report for the Period 1 November 2019 to 31 October 2020 |
| A119201 | 2019 | Anglogold Ashanti Australia Limited | Otway | <1% | Otway Group (C145/2018) Annual Report for the period 1 January 2018 to 31 December 2018 |
| A119280 | 2019 | Hawthorn Resources Limited; Westgold Resources Limited | Yundamindera | 6.4% | C96/2016 Yundamondera Project Annual Report for the period 1 November 2017 to 31 October 2018 |
| A115940 | 2018 | Anglogold Ashanti Australia Limited | Sunrise Dam Group | <1% | Sunrise Dam (C144/1995) Annual Report to the Department Mines and Petroleum For the Period 1 January 2017 to 3 |
| A115738 | 2018 | Hawthorn Resources Limited | Yundamindera | 6.4% | C96/2016 Combined Group Report 2017 - Yundamindera Project For the Period 1 November 2016 to 31 October 2017, |
| A112079 | 2017 | Anglogold Ashanti Australia Limited | Sunrise Dam Group | <1% | Sunrise Dam Group (C144/1995) Annual Report to the DMP for the period 01/01/2016 to 31/12/2016 |
| A112186 | 2017 | Hawthorn Resources Limited; Metals X Limited | Yundamindera | 6.5% | Yundamindera Project C96/2016 Annual Report For the Period 1 November 2015 to 31 October 2016, E39/01292, E39/ |
| A107894 | 2016 | Hawthorn Resources Limited | Yundamindera | 100% | Exploration Licence E39/1791 Yundamindera Project Annual Report for the period 16/10/2014 to 15/10/2016 |
| A107896 | 2016 | Hawthorn Resources Limited | Yundamindera - Top Box Well | <1% | Yundamindera Project E39/1292 – Top Box Well Annual Report for the period 24/10/2014 to 23/10/2015 |
| A108112 | 2016 | Anglogold Ashanti Australia Limited | Sunrise Dam Group | <1% | Annual Report for Sunrise Dam Group C144/1995 for the period 1 January 2015 to 31 December 2015 (M38/426, M38/ |
| A108266 | 2016 | Saracen Gold Mines Pty Ltd | Mount Howe | <1% | Mount Howe Project (C222/2007) Annual Report for the Period 1 January 2015 to the 31 December 2015, E31/949, E |
| A104530 | 2015 | Hawthorn Resources Limited | Yundamindera - Top Box Well | <1% | Yundamindera Project E39/1292 – Top Box Well Annual Report for the period 24/10/2013 to 23/10/2014 |
| A104898 | 2015 | Anglogold Ashanti Australia Ltd | Sunrise Dam Group | <1% | Sunrise Dam Group C144/1995 Combined Annual Report for the period 01/01/2014 to 31/12/2014, E38/2297....... P3 |
| A107156 | 2015 | Hawthorn Resources Limited | Yundamindera – White Quartz Bore | <1% | Annual Report for E39/1351 Yundamindera White Quartz Bore for the period 29 July 2014 to 28 July 2015 |
| A107496 | 2015 | Hawthorn Resources Limited | Yundamindera - Top Box Bore | <1% | Annual Mineral Exploration Report E39/1294 Yundamindera - Top Box Bore Project for the period 22 August 2014 t |
| A105467 | 2015 | Saracen Gold Mines Pty Ltd | Mount Howe | 1.1% | Mt Howe Project C222/2007 Annual Report for the period 01/01/2014 - 31/12/2014, E31/926-I......P39/4977-I |
| A105747 | 2015 | Hawthorn Resources Limited | Yundamindera – Top Box Well | 22% | Yundamindera – Top Box Well P39/4697 Annual Report for the period 24 July 2013 to 23 July 2014 |
| A105748 | 2015 | Hawthorn Resources Limited | Yundamindera – Top Box Well 2 | 14% | Yundamindera – Top Box Well 2 P39/4713 Annual Report for the period 24 July 2013 to 23 July 2014 |
| A106420 | 2015 | Saracen Gold Mines Pty Ltd | Mount Howe | <1% | Exploration Licence 39/1409 Mount Howe Surrender Report for the Period 23 July 2009 to the 15 April 2015 |
| A101216 | 2014 | Anglogold Ashanti Australia Ltd | Sunrise Dam | <1% | Sunrise Dam Group Combined Report No: C144/1995 Annual Report for the period 1 January 2013 to 31 December 201 |
| A101327 | 2014 | Hawthorn Resources Limited | Yundamindera - Top Box Well | <1% | Yundamindera Project E39/1292 – Top Box Well, Annual Report for the period 24 October 2012 TO 23 October 2013 |
| A101784 | 2014 | Saracen Gold Mines Pty Ltd | Mount Howe | 1.1% | Mt Howe Project C222/2007 Annual Report for the period 01/01/2013 to 31/12/2013, E31/926 I......P39/5036-I |
| A103523 | 2014 | Hawthorn Resources Limited | Yundamindera - Top Box Bore | <1% | Yundamindera – Top Box Bore E39/1294 – Partial Surrender Report for the period 22 August 2008 to 28 May 2014 |
| A103950 | 2014 | Hawthorn Resources Limited | Yundamindera – Top Box Bore | <1% | Yundamindera – Top Box Bore E39/1294 Annual Report for the period 22 August 2013 to 21 August 2014 |
| A103952 | 2014 | Hawthorn Resources Limited | Yundamindera - White Quartz Bore | <1% | Exploration Licence E39/1351 Yundamindera - White Quartz Bore, Annual Report for the period 28 July 2013 to 28 |
| A97466 | 2013 | Saracen Gold Mines Pty Ltd | Mount Howe | 1.1% | MT HOWE PROJECT ANNUAL REPORT 01 JANUARY 2012 TO 31 DECEMBER 2012 CR GROUP: C222/2007. |
| A100287 | 2013 | Hawthorn Resources Limited | Yundamindera – Top Box Bore | <1% | Yundamindera – Top Box Bore E39/1294 Annual Report for the period 22 August 2012 to 21 August 2013 |
| A100359 | 2013 | Hawthorn Resources Limited | Yundamindera - Mount Florence | <1% | Exploration Licence E39/1350 , Yundamindera - Mount Florence Project, Annual Report for the period 29 July 20 |
| A92684 | 2012 | Hawthorn Resources Limited | Yundamindera | <1% | YUNDAMINDERA PROJECT, E39/1292 – Top Box Well, ANNUAL REPORT FOR THE PERIOD 24 October 2010 TO 23 October 2011 |
| A93045 | 2012 | Rubicon Resources Ltd | Mount Howe | 1.1% | Mt Howe Project Combined Report C222/2007, Annual Report, 1st January 2011 – 31 December 2011 |
| A95811 | 2012 | Hawthorn Resources Limited | Yundamindera – Top Box Bore | <1% | Yundamindera – Top Box Bore E39/1294 Annual report for the period 22 August 2011 to 21 August 2012 |
| A94245 | 2012 | Midas Resources Ltd | Butcher Well | <1% | Butcher Well E39/1499 Relinquishment Report to the Department of Mines and Petroleum for E39/1499 for the peri |
| A95855 | 2012 | Hawthorn Resources Limited | Yundamindera | <1% | Exploration Licence E39/1351 YUNDAMINDERA White Quartz Bore ANNUAL REPORT FOR THE PERIOD 29 JULY 2011 TO 28 JU |
| A95857 | 2012 | Hawthorn Resources Limited | Yundamindera - Mount Florence | <1% | E39/1350, Yundamindera - Mt Florence Project, Annual Report for the period 29th July 2011 to 28th July 2012. |
| A96684 | 2012 | Hawthorn Resources Limited | Yundamindera - Top Box Well | <1% | YUNDAMINDERA PROJECT E39/1292 – Top Box Well Annual Report for the period 24 October 2011 TO 23 October 2012 |
| A89379 | 2011 | Rubicon Resources Ltd | Mount Howe | 1.5% | Mt Howe Project Combined Report C222/2007 2010, 1st January 2010 – 31 December 2010 |
| A91060 | 2011 | Midas Resources Ltd | Butcher Well | <1% | Butcher Well E39/1499 Annual Report to the Department of Mines and Petroleum for the period 22/06/10 to 21/06/ |
| A91240 | 2011 | Rubicon Resources Ltd | Celia | <1% | Final; report for the period 7 September 2006 to 6 September 2011, E39/831 |
| A91996 | 2011 | Hawthorn Resources Limited | Yundamindera - Mount Florence | <1% | E39/1350 Yundamindera - Mount Florence Project, Annual Report for the period 29 July 2010 to 28 July 2011. |
| A91997 | 2011 | Hawthorn Resources Limited | Yundamindera - White Quartz Bore | <1% | Exploration Licence E39/1351 Yundamindera - White Quartz Bore Annual Report for the period 29 July 2010 to 28 |
| A89166 | 2011 | Hawthorn Resources Limited | Yundamindera - Top Box Well | <1% | Yundamindera Project E39/1292 – Top Box Well Annual Report for the period 24 October 2009 TO 23 October 2010 |
| A90591 | 2011 | Hawthorn Resources Limited | Yundamindera – Bore Well | 50% | Yundamindera – Bore Well E39/1047 Final Surrender Report for the period 14 March 2006 to 12 March 2011 |
| A92010 | 2011 | Hawthorn Resources Limited | Yundamindera – Top Box Bore | <1% | Yundamindera – Top Box Bore E39/1294 Annual Report for the period 22 August 2010 to 21 August 2011 |
| A85714 | 2010 | Hawthorn Resources Limited | Yundamindera - Top Box Well | <1% | Yundamindera Project E39/1292 – Top Box Well Annual Report for the period 24 October 2008 - 23 October 2009 |
| A85596 | 2010 | Heron Resources Ltd | Murphy Well | <1% | Partial surrender report for the period 7 September 2006 to 6 September 2009, Murphy Well Project, E39/831 |
| A87167 | 2010 | Hawthorn Resources Limited | Yundamindera - Bore Well | 50% | Yundamindera – Bore Well E39/1047 Annual Report for the period 14 March 2009 to 13 March 2010 |
| A87168 | 2010 | Hawthorn Resources Limited | Yundamindera - Bore Well | 50% | Yundamindera – Bore Well E39/1047 Partial Surrender Report for the period 14 March 2006 to 13 March 2010 |
| A88495 | 2010 | Rubicon Resources Ltd | Murphy Well | <1% | Partial surrender report for the period 7 September 2006 to 6 September 2010, Murphy Well Project, E39/831 |
| A88500 | 2010 | Hawthorn Resources Limited | Yundamindera – Top Box Bore | <1% | Yundamindera – Top Box Bore E39/1294 Annual Report for the Period 22 August 2009 to 21 August 2010 |
| A83039 | 2009 | Heron Resources Ltd | Mount Percy | <1% | MOUNT PERCY PROJECT C77/2008 E39/831, E39/883, E39/1265 MOUNT MARGARET MINERAL FIELD Edjudina (SH51-06) 1:250, |
| A86118 | 2009 | Rubicon Resources Ltd | Mount Howe | <1% | Combined Annual Technical Report Mt Howe Project, 1st January 2009 – 31 December 2009, E39/1132, 1182, 1317, 1 |
| A86474 | 2009 | Hawthorn Resources Limited | Yundamindera /Top Box Bore | <1% | Tenement E39/1294, Annual Report for the Period 22 August 2008 to 21 August 2009 |
| A77545 | 2008 | Great Gold Mines Nl | Yundamindera | 100% | Exploration Licence E39/969 YUNDAMINDERA ANNUAL REPORT FOR THE PERIOD 2 NOVEMBER 2006 TO 1 NOVEMBER 2007 |
| A78782 | 2008 | Hawthorn Resources Limited | Yundamindera | 50% | Yundamindera E39/1047 ANNUAL REPORT FOR THE PERIOD 14 March 2007 TO 13 March 2008 |
| A79022 | 2008 | Heron Resources Ltd | Carr Boyd | <1% | MOUNT PERCY PROJECT C77/2008 E39/831, E39/883 MOUNT MARGARET MINERAL FIELD ANNUAL REPORT 2 May 2007 to 1 May 2 |
| A77510 | 2008 | Great Gold Mines Nl | Yundamindera | <1% | Exploration Licence E39/812 Yundamindera Annual Report for the period 17 October 2006 TO 18 October 2007 |
| A76054 | 2007 | Heron Resources Ltd | Murphy Well | <1% | Murphy Well Project E39/831 Annual Report 7th September 2006 to 6th September 2007 |
| A74692 | 2007 | Niwest Ltd | Eucalyptus Bore | <1% | Eucalyptus Bore Project E39/480 Surrender Report 2006 |
| A75237 | 2007 | Niwest Ltd | Eucalyptus Bore | <1% | Eacalyptus Bore Project M39/289, 313, 344, 430, 568, 570, 616, 665, 666, 674, 802, E39/703 and 480 Annual Tech |
| A72598 | 2006 | Niwest Ltd | Eucalyptus Bore | <1% | Eucalyptus Bore Project E39/480,703,M39/289,313,344,430,568, 570,616,665,666,674,802, Annual Technical & Progr |
| A73530 | 2006 | Great Gold Mines Nl | Yundamindera | <1% | Yundamindera C76/2000, Combined Group Reporting Annual Report for the Period 1 June 2005 to 31 May 2006, (Edju |
| A71389 | 2005 | Great Gold Mines Nl | Yundamindera | <1% | Yundamindera C76/2000, Combined group reporting annual report, For the period 1 June 2004 to 31 May 2005, (Ten |
| A68603 | 2004 | Gutnick Resources Nl | Yundamindera | 28% | Joint Surrender Report for the Period 23 May 2002 to 1 Augus t 2003 C76/2000 - Yundamindera, E39/776, E39/780, |
| A69279 | 2004 | Great Gold Mines Nl | Yundamindera | <1% | E39/719 and E39/721, C76/2000- Yundamindera, Joint Partial Surrender Report for the period 21 March 2000 to 14 |
| A69079 | 2004 | Gutnick Resources Nl | Yundermindera | 4.4% | Joint Annual Report for the Period 1 June 2003 to 31 May 200 4 C76/2000 - Yundamindera E39/708...P39/3860 |
| A67291 | 2003 | Gutnick Resources Nl | Yundamindera | 4.4% | Joint annual Report for the period 1 June 2002 - 31 May 2003 Yundamindera Project C76/2000: E39/708,719,721,72 |
| A64342 | 2002 | Anglogold Australia Ltd | Cornwall | 91% | Final Report Period ended 28 February 2002. Cornwall E39/733 Location Mt Morgan District Mt Margaret Mineral F |
| A64890 | 2002 | Gutnick Resources Nl | Yundamindera | 4.6% | C76/2000 - Yundamindera Joint Annual Report for the period 1 June 2001 to 31 May 2002 |
| A65728 | 2002 | Niwest Ltd | Eucalyptus South | <1% | Eucalyptus South Project E39/480 Annual Report For The Period 20th September 2001 To 19th September 2002. |
| A63891 | 2001 | Niwest Ltd | Eucalyptus South | <1% | Eucalyptus South Project E39/480 Annual Report for the period 20th September 2000 to 19th September 2001. |
| A62848 | 2001 | Anglogold Australasia Ltd | Cornwall | 91% | Cornwall Project E39/733 Annual Report for the period 19 May 2000 to 18 May 2001. Report No: 08.11573 |
| A63889 | 2001 | Gutnick Resources Nl | Yundamindera | 4.6% | Joint Annual Report for the period 1 June 2000 to 31 May 2001 C76/2000 - Yundamindera exploration licences: E3 |
| A61740 | 2000 | Niwest Ltd | Eucalyptus South | <1% | Eucalyptus South, E39/480, Annual report for the Period 20/09/1999 to 19/09/2000. |
| A59543 | 2000 | Western Metals Ltd | Eucalyptus South | <1% | Eucalyptus South project, E39/480, Partial Surrender Report for the Period 20/09/1995 to 19/09/1999. |
| A58694 | 1999 | Western Metals Ltd | Eucalyptus South | <1% | Eucalupytus South Project, Partial Surrender Report for the period 20/09/1995 to 04/03/1999, E39/480. |
| A58272 | 1999 | Acacia Resources Ltd | Bore Well | 46% | Acacia Resources Ltd, Bore Well E39/491 Surrender Report (01/03/99) |
| A59466 | 1999 | Western Metals Ltd | Eucalyptus South | <1% | Eucalyptus South Project, E39/480, Annual Report for the Period 20th September 1998 to 19th September 1999. |
| A56504 | 1998 | Aberfoyle Resources Ltd | Eucalyptus | <1% | Eucalyptus Project, E39/480, Annual technical and progress report for the 12 month period ended 19/09/98. |
| A53902 | 1998 | Acacia Resources Ltd | Camelback | 13% | Camelback Project P39/3458-3462,E39/491,E39/502, E39/503 E39/596 Annual report for the period 01/01/97-31/12/ |
| A55113 | 1998 | Delta Gold Ltd | Box Soak | 12% | Box Soak Project, Surrender Report 15/08/91 - 05/05/98 EL39/308 |
| A50237 | 1997 | Acacia Resources Ltd | Camelback | 17% | Camelback Project P39/3458 to P39/3462 E39/491 E39/502 E39/503 1996 Annual report for the period 1 January 199 |
| A52701 | 1997 | Aberfoyle Resources Ltd | Eucalyptus | <1% | Eucalyptus Nickel Project, WA. E39/480 Eucalyptus South. Annual report for the period 20/09/96-19/09/97. |
| A49393 | 1996 | Aberfoyle Resources Ltd | Eucalyptus South | <1% | E39/480 , Eucalyptus South Project, Annual report for the period 20/09/95 to 19/09/96. |
| A49812 | 1996 | Delta Gold Ltd | Box Soak | 12% | Box Soak Project E39/308 Annual Technical Report for the period 15th August 1995 to 14th August 1996 Delta Gol |
| A46389 | 1995 | Mount Burgess Mining Nl | Box Soak | 12% | Box Soak Project Annual Technical Report for period 15th August 1994 to 14th August 1995 E39/308 Mount Burgess |
| A46390 | 1995 | Mount Burgess Mining Nl | Box Soak | 12% | Partial Surrender Report for the period 1994 Box Soak Project E39/308 |
| A40601 | 1994 | Mount Burgess Mining Nl | Camelback, Butcher Well, Linden | 1.2% | Butcher Well Project, Annual report for period 1 January 1993 to 31 December 1993, C345/93 |
| A42334 | 1994 | Mount Burgess Mining Nl | Box Soak | 12% | Annual Report for the period 15/08/93 to 14/08/94 Box Soak Project E39/308 Mount Burgess Gold Mining Co NL Del |
| A38932 | 1993 | Delta Gold Ltd | Box Soak | 12% | Annual Report for the period 15/08/91-14/08/92 Box Soak Project E39/308 |
| A13815 | 1978 | Union Corp Australia Pty Ltd | Top Box Well | 86% | Top Box Well Project, Final Surrender Report for the period ending 05/07/1978, MC39/4614-4616. |
| A14214 | 1977 | Asarco Australia Ltd | Mount Florence | 60% | Mount Florence Project, Final Surrender Report for the period ending 24/05/1978, MC39/4636-4643. |
| A5741 | 1975 | Australian Selection Pty Ltd | Bald Hills | 81% | Final report [non-statutory] on Bald Hills Claims, MC39/15 & MC39/16 |
| A95270 | 1974 | Carpentaria Exp Co Pty Ltd | Mount Margaret | <1% | Technical Report Mineral Claims 39/4263 to 39/4276 incl."Bald Hills Bore" - Mount Margaret Goldfield, Western |
| A4755 | 1974 | Carpentaria Exp Co Pty Ltd | Bald Hills Bore | <1% | Bald Hills Bore Project, Non-statutory Report: Final Report for the period 04/02/1974 to 07/02/1974, MC39/4263 |
| A3932 | 1973 | International Nickel Aust Ltd | Lake Carey | <1% | Lake Carey Project, Non-statutory Report: Final Report for the period 1st July 1972 to 30th June 1973, TR70/37 |
| A4652 | 1973 | Carpentaria Exp Co Pty Ltd | Bald Hills Bore | <1% | Bald Hils Bore Project, Non-statutory Report: First Progress Report , October 1973, MC39/4267-4276. |
| A2782 | 1972 | International Nickel Aust Ltd | Lake Carey | <1% | Lake Carey Project, Annual Report for the period ending 30th June 1971, TR70/3730 & 5279H. |
| A2829 | 1972 | International Nickel Aust Ltd | Lake Carey | <1% | Lake Carey Project, Annual Report for the period ending 30th June 1972, TR70/3730H. |
| A3618 | 1972 | International Nickel Aust Ltd | Lake Carey | <1% | Lake Carey Project, Non-statutory Report: Miscellaneous Maps (1-20), for the period ending 31/12/1972, TR70/3 |
| A941 | 1971 | International Nickel Aust Ltd | Lake Carey | <1% | Lake Carey Project, Annual Report for the period ending 30th June 1970, TR70/3730H & 5279H. |
| A1415 | 1971 | Australian Selection Pty Ltd | Pyke Hill - Eucalyptus | <1% | Pyke Hill - Eucalyptus Project, Non-statutory Report:Index to Plans, Soil Geochemistry & Geology Grids ( for o |
| A1414 | 1971 | Australian Selection Pty Ltd | Pyke Hill - Eucalyptus | <1% | Pyke Hill - Eucalyptus Project, Annual Report (s) for the period(s) ending 31/12/1970 & 31/12/1971, TR70/3701 |
| A271 | 1970 | International Nickel Aust Ltd | Lake Carey | <1% | Lake Carey Project, Annual Report for the period ending 30th June 1969, TR70/3730H. |
| A1121 | 1969 | International Nickel Aust Ltd | Lake Carey | <1% | Lake Carey Project, Non-statutory Report:;Volume 1: Report on the Induced Polarization & Resistivity Survey on |
| A1122 | 1969 | International Nickel Southern Exp Ltd | Lake Carey | <1% | Lake Carey Project, Non-statutory Report: Appendix 2:Annual Report, June 30th 1969, TR70/3730H; Report on the |
| A1123 | 1969 | International Nickel Southern Exp Ltd | Lake Carey | <1% | Lake Carey Project, Non-statutory Report: Annual Report for the period ending 30th June 1969, TR70/3730H. A Re |
| A269 | 1968 | International Nickel Aust Ltd | Lake Carey | <1% | Lake Carey Project, Annual Report for the year ending 30th June 1968, TR70/3730H. |
| A270 | 1968 | International Nickel Aust Ltd | Lake Carey | <1% | Lake Carey Project, Non-statutory Report: Report on the Induced Polarisation & Resistivity Survey on the Deep |
| A268 | 1967 | International Nickel Aust Ltd | Lake Carey | <1% | Lake Carey Project, Annual Report for the year ending 30th June 1967, TR70/3730H. |
| A1590 | 1965 | Mount Margaret Prospecting Syndicate | Yundamindera | <1% | Yundamindera Project, Non-statutory Report: Report on 78 Gold Products received 13th August 1964, TR70/2685, 2 |
| A81492 | 1753 | Hawthorn Resources Limited | YUNDAMINDERA | <1% | Exploration Licence E39/812 YUNDAMINDERA FINAL SURRENDER REPORT, FOR THE PERIOD 18 OCTOBER 2005 TO 19 NOVEMBER |
| A81572 | 1753 | Hawthorn Resources Limited | YUNDAMINDERA | 100% | Exploration Licence E39/969 YUNDAMINDERA FINAL SURRENDER REPORT FOR THE PERIOD 1 NOVEMBER 2006 TO 19 NOVEMBER |
| A82519 | 1753 | Hawthorn Resources Limited | YUNDAMINDERA | 50% | Exploration Licence E39/1047 YUNDAMINDERA ANNUAL REPORT FOR THE PERIOD 15 MARCH 2008 TO 14 MARCH 2009 |
| A82541 | 1753 | Hawthorn Resources Limited | YUNDAMINDERA | 50% | Exploration Licence E39/1047 YUNDAMINDERA PARTIAL SURRENDER REPORT FOR THE PERIOD 15 MARCH 2006 TO 16 MARCH 20 |
| A84840 | 1753 | Hawthorn Resources Limited | YUNDAMINDERA | <1% | Exploration Licence E39/1350 YUNDAMINDERA ANNUAL REPORT FOR THE PERIOD 29 JULY 2008 TO 28 JULY 2009. |
| A88235 | 1753 | Hawthorn Resources Limited | Yundamindera - Mount Florence | <1% | E39/1350 ,Yundamindera - Mt Florence Project, Annual Report for the period 29th July 2009 to 28th July 2010. |
| A88236 | 1753 | Hawthorn Resources Limited | Yundamindera | <1% | Exploration Licence E39/1351 YUNDAMINDERA White Quartz Bore ANNUAL REPORT FOR THE PERIOD 29 JULY 2009 TO 28 JU |
| A100358 | 1753 | Hawthorn Resources Limited | Yundamindera - White Quartz Bore | <1% | Exploration Licence E39/1351 Yundamindera - White Quartz Bore Annual Report for the period 29 July 2012 to 28 |
| A38751 | 1753 | Inco Australia Ltd | Eastern Goldfields regional mapping | <1% | Eastern Goldfields regional mapping |
Tenure detail Free account
- Current holders & shares
- Holder change history
- Expenditure history
- Conditions & endorsements
- Native title context
- Combined reporting
- Rent status
Tenement intelligence Premium
- Time to expiry
- 4 years · 6 Oct 2030
- At-risk & opportunity signals
- Expenditure compliance
- 5-year track record
- Spend trend & exploration intensity
- Expiry band
- Ownership age
- Dealings, mortgages & caveats
- Transfer history
What does the exploration record say about this ground?
NextMaps reads every WAMEX report over E 39/2526 into a referenced prospectivity assessment: the geology, the historical programs, the drill intercepts and geochemistry, and the untested gaps — every claim cited back to its source report. New accounts include a free prospectivity report. Prefer the raw due diligence? The Tenure Pack bundles the full register record, tenure history and spatial datasets for this ground.
Open on the map — full register record About AI reports About Tenure PacksDo you hold E 39/2526? Listing is free. A facilitation fee applies only if you sell to a buyer we introduce.