E 28/2748
Register summary
- Holder
- Breaker Resources Nl
- Local government
- City of Kalgoorlie-Boulder
- Application received
- 6 Feb 2018
- Commenced
- 7 Feb 2019
- Expiry
- 6 Feb 2029
- Term
- 5 Years (Extended)
Exploration history on this ground
| Report | Year | Operator | Project | On this ground | Title |
|---|---|---|---|---|---|
| A129987 | 2022 | Breaker Resources Nl | Lake Roe | <1% | Partial Surrender Report for Lake Roe Project E28/2555 for the period 22/06/2016 to 21/02/2022 |
| A126350 | 2021 | St Barbara Ltd | Green Dam | <1% | Green Dam E28/2313 - Partial Surrender Report for the Period 17 November 2014 to 16 November 2020 |
| A127760 | 2021 | St Barbara Limited | Yindi | <1% | Yindi E28/2327 - Partial Surrender Report for the Period 2 June 2015 to 1 June 2021 |
| A124697 | 2020 | St Barbara Limited | Pinjin South | <1% | Pinjin South Project Combined Reporting Group C124/2015 - Annual Report for the Period 1 July 2019 to 30 June |
| A123510 | 2020 | Gold Geological Consulting Pty Ltd | Roe | 46% | Roe Project Annual Report, C28/2000, 1 March 2019 to 28 February 2020 |
84 more reports
| A125120 | 2020 | St Barbara Limited | Yindi | <1% | E28/2446 - Partial Surrender Report Yindi for the Period 25 August 2014 to 24 August 2020 |
| A124723 | 2020 | Breaker Resources Nl | Lake Roe | <1% | Lake Roe Project (C46/2016) Annual Report for the period 20 May 2019 to 19 May 2020. E 28/02515,E 28/02551,E 2 |
| A124559 | 2020 | Breaker Resources Nl | Lake Roe | <1% | Lake Roe Project Co-Funded Drilling Final Report (DAG2019/01562920), R19 |
| A124591 | 2020 | St Barbara Limited | Pinjin South | <1% | E28/2446 - Partial Surrender Report for the Period 25 August 2014 to 24 June 2020 Pinjin South project. |
| A124789 | 2020 | St Barbara Limited | Green Dam | <1% | Green Dam Project Combined Reporting Group C149/2018 - Annual Report for the Period 17 November 2019 to 30 Jun |
| A122126 | 2019 | St Barbara Limited | Green Dam | <1% | Green Dam Project Combined Reporting Group C149/2018 - Annual Report for the Period 17 November 2018 to 16 Nov |
| A120543 | 2019 | Breaker Resources Nl | Lake Roe | <1% | Lake Roe Project (C46/2016) Annual Report for the period 20 May 2018 to 19 May 2019 E 28/02515,E 28/02551,E 28 |
| A120894 | 2019 | St Barbara Limited | Pinjin South | <1% | Pinjin South Project Combined Reporting Group C124/2015 Annual Report for the Period 1 July 2018 to 30 June 20 |
| A119034 | 2019 | Element 25 Limited | Green Dam | <1% | Group Annual Report - Green Dam Project C149/2018 For the Period 17 November 2017 to 16 November 2018, E28/023 |
| A116460 | 2018 | Carnavale Resources Limited | Roe | 100% | Final Surrender Report E28/2304 Roe Project for the period 4 December 2013 to 6 February 2018 |
| A117533 | 2018 | St Barbara Limited | Pinjin South | <1% | Pinjin South Project Combined Reporting Group C124/2015 - Annual Report for the Period 1 July 2017 to 30 June |
| A117761 | 2018 | Element 25 Limited | Green Dam | <1% | Annual Report Green Dam E28/2327, 02 June 2017 - 01 June 2018 |
| A115841 | 2018 | Montezuma Mining Company Ltd | Green Dam | <1% | Annual Report on Green Dam E28/02313 for the period 17 November 2016 to 16 November 2017 |
| A117242 | 2018 | Breaker Resources Nl | Lake Roe | <1% | Lake Roe Project (C46/2016) 2018 Annual Report for the period 20 May 2017 to 19 May 2018, E28/02515, E28/02551 |
| A116229 | 2018 | Carnavale Resources Limited | Roe | 46% | Roe Project C14/2015, E28/02303, E28/02304 Annual Report for the period 4 December 2016 to 3 December 2017 |
| A114577 | 2017 | St Barbara Limited | Pinjin South | <1% | Pinjin South Project Combined Reporting Group C124/2015 - Annual Report for the Period 1 July 2016 to 30 June |
| A110716 | 2017 | Montezuma Mining Company Ltd | Green Dam | <1% | Annual Report on Green Dam Project E28/2313 17 November 2015 to 16 November 2016 |
| A112093 | 2017 | Carnavale Resources Limited | Roe | 46% | Roe Project C41/2015 Annual Mineral Exploration Report For the Period 4 December 2015 to 3 December 2016 |
| A114595 | 2017 | Breaker Resources Nl | Lake Roe | <1% | Lake Roe Project C46/2016 Annual Report For the Period 20 May 2016 to 19 May 2017, E28/02515, E28/02551, E28/0 |
| A114601 | 2017 | Montezuma Mining Company Ltd | Green Dam | <1% | Green Dam - E28/2327 - Annual Report for the period 2 June 2016 to 1 June 2017 |
| A109692 | 2016 | St Barbara Limited | Pinjin South | <1% | Pinjin South Project Combined Reporting Group C124/2015 - Annual Report for the Period 1 July 2015 to 30 June |
| A108792 | 2016 | Kalnorth Gold Mines Limited | Roe | 46% | Annual Mineral Exploration Report, For the Period 4 December 2014 to 3 December 2015, Roe Project, E28/02303, |
| A109377 | 2016 | Montezuma Mining Company Ltd | Green Dam | <1% | Green Dam Project E28/02327 Annual Report for the period 2 June 2015 to 1 June 2016 |
| A109378 | 2016 | Breaker Resources Nl | Lake Roe | <1% | Lake Roe Project C46/2016 Annual Report for the period 20/05/2015 to 19/05/2016, E28/02515, E28/02551, E28/025 |
| A107688 | 2016 | Montezuma Mining Company Ltd | Green Dam | <1% | Annual Report on Green Dam Project E28/2313 for the period 17/11/2014 to 16/11/2015 |
| A106703 | 2015 | St Barbara Limited | Away From It All Dam E28/2446 | <1% | Annual Report for the Period 25 August 2014 to 24 August 2015 |
| A104960 | 2015 | Kalnorth Gold Mines Ltd | Roe | 100% | Annual Report for the period ending 3 December 2014, Roe Project, E28/2304 |
| A104189 | 2014 | Enterprise Uranium Ltd | Ponton | <1% | Ponton Project E28/2333 Surrender Report for the period 25 March 2014 to 7 November 2014 |
| A100207 | 2013 | Renaissance Minerals Ltd | Eastern Goldfields | <1% | E28/2001 Surrender Report for the period 13 July 2010 to 15 July 2013 |
| A97554 | 2013 | Magma Metals Ltd | Roe | <1% | Partial Surrender Report E28/1659 for the period 21 March 2007 to 20 March 2013 |
| A97555 | 2013 | Magma Metals Ltd | Roe | 4.7% | Roe Project, Annual Report for the period 1st January 2012 to 31st December 2012, E28/1416 & 1659. [C408/1996 |
| A92642 | 2012 | Magma Metals Ltd | Roe | 4.7% | Roe Project, Annual Report for the period 1st January 2011 to 31st December 2011, E28/1659 & 1416. (C408/1996) |
| A96120 | 2012 | Renaissance Minerals Ltd | Yindi | <1% | C 268/2011 - Combined Annual Report on Exploration for the Period 13th July 2011 to 12th July 2012. |
| A91608 | 2011 | Renaissance Minerals Ltd | E28/2001 | <1% | E28/2001 Annual Report, 13 July 2010 to 12 July 2011 |
| A88152 | 2011 | Magma Metals Ltd | Roe | 4.7% | Annual Report for the period 1st January 2010 to 31st December 2010, Roe Project E28/1659, E28/1416 |
| A85573 | 2010 | Magma Metals Ltd | Roe | 4.7% | Roe Project Annual Report for period 1st January 2009 - 31st December2009, Group Reporting No C408/1996 E28/16 |
| A86395 | 2010 | Hawthorn Resources Limited | Yindana | <1% | Exploration Licence E28/1519 Yindana, Annual Report for the period 24 November 2008 to 23 November 2009 |
| A84263 | 2009 | Magma Metals Ltd | Roe | 8.6% | Roe Project, E28/1416, Partial Surrender Report for the period 29/09/2004 to 6/07/2009, Group Reporting Number |
| A77220 | 2008 | Magma Metals Ltd | Roe | 4% | Annual report for the period 1st January 2007 to 31st Decemb December 2007,Roe Project, E28/803, E28/1153, E28 |
| A80784 | 2008 | Magma Metals Ltd | ROE | 4.4% | ROE PROJECT, ANNUAL REPORT For Period 1st January 2008 – 31st December 2008, Group Reporting No C 408/1996 E28 |
| A77764 | 2008 | Great Gold Mines Nl | Yindana | <1% | Exploration Licence 28/1519 Yindana Annual Report for the period 25 November 2006 to 24 November 2007 |
| A74364 | 2007 | Metex Resources Ltd | Roe | 2.4% | Roe Project Area E28/620...E28/1598 Annual Technical Report for the Period 01/01/2006 to 31/12/2006 Combined R |
| A74876 | 2007 | Great Gold Mines Nl | Yindana | <1% | Exploration Licence 28/1519, Yindana (Project) Annual Report for the Period 24 November 2005 TO 23 November 20 |
| A76576 | 2007 | Metex Resources Ltd | Roe | 8.6% | Roe Project Area, Partial Surrender Report for the period 29 /09/2004 to 28/09/2007 (Group Reporting Number C4 |
| A73369 | 2006 | Metex Resources Ltd | Roe | 1.1% | Roe Joint Venture, Surrender Report E28/833, E28/1338, E28/672 (Partial) & E28/1105 (Partial), Combined Report |
| A71911 | 2006 | Metex Resources Ltd | Roe | 2.3% | Roe Project Area, Annual Technical Report for the Period 01/01/2005 to 31/12/2005, Combined Reporting No. C408 |
| A70622 | 2005 | Newcrest Mining Ltd | Roe | 2.3% | Annual Report Roe Project for the Period 1/1/2004 to 31/12/2004 Group Reporting No.: C408/1996 Report No: K420 |
| A68651 | 2004 | Metex Resources Ltd | Roe | <1% | 2003 Annual Report for Period 01/01/2003 to 31/12/2003 Roe Project (C408/1996), E28/620, E28/672, E28/720, E28 |
| A66142 | 2003 | Placer Dome Asia Pacific Ltd | Roe Metex | <1% | Annual Report 01/01/2002 - 31/12/2002 Roe Metex JV Project C408/1996: E28/620, 672, 720, 803-04, 810, 833, 836 |
| A64192 | 2002 | Delta Gold Ltd | Roe Joint Venture | <1% | Roe Joint Venture Project C408/1996 Annual Report 01/01/2001 to 31/12/2001 tenements E28/620, 672, 720, 803, 8 |
| A62882 | 2001 | Metex Resources Ltd | Roe | <1% | Combined Biannual Technical Report W503 Roe Project E28/620, E28/672, E28/720, E28/803-804, E28/810, E28/833, |
| A57575 | 1999 | Golden Valley Mines Nl | Roe | <1% | Annual Report, Roe Project E28/620,659-660,672,718-720 P28/942-943,P31/1527 For the Period 1/1/98 to 31/12/98 |
| A54681 | 1998 | Aberfoyle Resources Ltd | Swan Lake | 9.1% | Swan Lake, E28/504 Annual Report for the period 13th May 1997 to 12th May 1998. |
| A53915 | 1998 | Cove Mining Nl | Roe | <1% | Annual Report - Roe Project - Kurnalpi W.A. 01/01/1997 - 31/12/1997 E28/620, 659, R28/660, E28/672, 718-720, P |
| A55417 | 1998 | Aberfoyle Resources Ltd | Claypan | <1% | Claypan E28/475 Partial Surrender Report to 15th April 1998. |
| A54290 | 1998 | Eden Creek Pty Ltd | Lake Roe | 9.1% | Partial Surrender Report ,E28/504 ,Lake Roe WA for the period 13 May 1994 to 06 February 1998 |
| A50124 | 1997 | Western Mining Corporation Ltd | Swan Lake | <1% | Annual Report for the Period 5 November 1995 to 4 November 1996, Swan Lake Project Exploration Licence 28/475 |
| A50848 | 1997 | Wmc Resources Ltd | Swan Lake | <1% | Swan Lake Project, Annual Report Exploration Licence E28/475 for the period 5th November 1995 to 4th November |
| A51603 | 1997 | Aberfoyle Resources Ltd | Swan Lake | 9.1% | Swan Lake Project, Annual Report E28/504 for the period 13th May 1996 to 12th May 1997. |
| A53165 | 1997 | Aberfoyle Resources Ltd | Claypan | <1% | Claypan Project, Annual Report for the period 5th November 1996 to 4th November 1997,E28/475. |
| A48271 | 1996 | Aberfoyle Resources Ltd | Swan Lake | 9.1% | Swan Lake Project, Annual Report for the period 13th May 1995 to 12th May 1996, E28/504. |
| A46972 | 1996 | Western Mining Corporation Ltd | Swan Lake | <1% | Swan Lake Project, Annual Report for Period 5 November 1994 to 4 November 1995, E28/475. |
| A48003 | 1996 | Cra Exploration Pty Ltd | Christmas Bore | 3.3% | Christmas Bore Project, Final Report, May 1996, E28/433 ( Christmas Bore 2 ) & E28/572 ( Christmas Bore 4 ) |
| A46680 | 1996 | Cra Exploration Pty Ltd | Kurnalpi East | <1% | Annual Report to 7 December 1995 on E31/93 E31/94 E28/372 E28/372 E28/374 E28/433 E28/453 E28/572 Kurnalpi Eas |
| A44465 | 1995 | Western Mining Corporation Ltd | Swan Lake | <1% | Swan Lake Project, Annual Report Exploration Licence E28/475 for the period 05/11/1993 to 01/02/1995. |
| A45165 | 1995 | Eden Creek Pty Ltd | Lake Roe | 9.1% | Lake Roe Project, Annual Report Exploration Licence E28/504 covering the period 13/05/1994 to 12/05/1995. |
| A46788 | 1995 | Cra Exploration Pty Ltd | Kurnalpi East | <1% | Partial Surrender for the period 1995 Kurnalpi East Project E28/372 E28/374 E28/433 E28/453 E31/93 E31/94 |
| A43302 | 1994 | Cra Exploration Pty Ltd | Kurnalpi East | <1% | Annual Report to 7 December 1994 on E31/93-94, E28/372, 374, 433, 442, 453, Kurnalpi East Project. |
| A41598 | 1994 | Cra Exploration Pty Ltd | Kurnalpi East | <1% | First partial relinquishment report to April 1994 on E28/372, 374, 431, 433, E31/93, 94 Kurnalpi East Project |
| A41041 | 1993 | Cra Exploration Pty Ltd | Kurnalpi East | <1% | Annual report for the period 08/12/92-07/12/93 Kurnalpi East Project E28/372 E28/374 E28/431 E28/433 E28/442 E |
| A38589 | 1993 | Cra Exploration Pty Ltd | Kurnalpi East | <1% | Kurnalpi East Project, Annual Report for the period 08/12/1991 to 07/12/1992, E28/372 ,374, 431, 433, 442 & 45 |
| A36333 | 1991 | Cra Exploration Pty Ltd | Kurnalpi East | <1% | Annual Report for the period 08/12/90-07/12/91 Kurnalpi East Project, E31/92-94 E28/370-374,398,419,431-433,4 |
| A26964 | 1989 | Black Mountain Gold Nl | Mount Quinn | 1.9% | Mount Quinn, Report on Preliminary Aeromagnetic and Air-photo interpretation, E28/242. |
| A26963 | 1988 | Black Mountain Gold Nl | Mount Quinn | 1.9% | Mount Quinn, Preliminary Exploration, E28/242. |
| A21649 | 1987 | Bhp Minerals Pty Ltd | Lake Roe | 6.2% | Lake Roe Project, Annual Report for the period 01/02/1986 to 01/02/1987, E28/39. |
| A20129 | 1987 | Associated Resources Management | Yindi | <1% | Progress report Yindi exploration licence E28/30 for period 6 December 1985 to 5 December 1986 |
| A21850 | 1987 | Bhp Minerals Pty Ltd | Lake Roe | 6.2% | Lake Roe Project, Non-statutory Report: Partial Relinquishment Report for the period ending 16/02/1987, E28/39 |
| A19314 | 1986 | Bhp Minerals Pty Ltd | Lake Roe | 6.2% | Lake Roe, E28/39, Progress [annual] report to February 1986 |
| A16827 | 1985 | Associated Resources Management | Yindi | <1% | Site Inspection and Evaluation of E28/30, 'Yindi'. |
| A16314 | 1753 | Kalamunda Commodities Pty Ltd | Karonie | <1% | Karonie Project, Annual Report: Geology & Potential, March 1983, E28/30. |
| A89597 | 1753 | Hawthorn Resources Limited | Yindana | <1% | Exploration Licence E28/1519 YINDANA ANNUAL REPORT FOR THE PERIOD 24 NOVEMBER 2009 TO 23 NOVEMBER 2010 |
| A82479 | 1753 | Hawthorn Resources Limited | YINDANA | <1% | Exploration Licence E28/1519 YINDANA PARTIAL SURRENDER REPORT FOR THE PERIOD 24 NOVEMBER 2005 TO 23 NOVEMBER 2 |
| A81270 | 1753 | Hawthorn Resources Limited | YINDANA | <1% | Exploration Licence 28/1519 YINDANA ANNUAL REPORT FOR THE PERIOD 24 NOVEMBER 2007 TO 23 NOVEMBER 2008 |
| A38751 | 1753 | Inco Australia Ltd | Eastern Goldfields regional mapping | <1% | Eastern Goldfields regional mapping |
Tenure detail Free account
- Current holders & shares
- Holder change history
- Expenditure history
- Conditions & endorsements
- Native title context
- Combined reporting
- Rent status
Tenement intelligence Premium
- Time to expiry
- 2 years · 6 Feb 2029
- At-risk & opportunity signals
- Expenditure compliance
- 5-year track record
- Spend trend & exploration intensity
- Expiry band
- Ownership age
- Dealings, mortgages & caveats
- Transfer history
What does the exploration record say about this ground?
NextMaps reads every WAMEX report over E 28/2748 into a referenced prospectivity assessment: the geology, the historical programs, the drill intercepts and geochemistry, and the untested gaps — every claim cited back to its source report. New accounts include a free prospectivity report. Prefer the raw due diligence? The Tenure Pack bundles the full register record, tenure history and spatial datasets for this ground.
Open on the map — full register record About AI reports About Tenure PacksDo you hold E 28/2748? Listing is free. A facilitation fee applies only if you sell to a buyer we introduce.
List this tenementTenure data sourced from the DMPE public registers and SLIP WA (© Government of Western Australia, CC BY 4.0), as at 2026-08-21. Compiled by NextMaps. Verify against primary sources before reliance.